Resolved
AGREED that: (a) the report be noted; (b) the Council’s formal response be forwarded to the Planning Committee Chair and Vice-Chair for final sign off.
Planning Committee agreed this item on Thursday 13 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED that: (a) the report be noted; (b) the Council’s formal response be forwarded to the Planning Committee Chair and Vice-Chair for final sign off.
1.1This report seeks to provide an update on the current status of the GNR NSIP project which remains at the pre-application stage, but for which the applicant is currently undertaking their statutory consultation for the project.
1.2Members will recall that in a report to the Planning Committee on the 5th December 2024, a general update was provided on the GNR project (alongside the OESF scheme) which included future milestone dates. The statutory consultation period for the GNR project commenced on the 9th January and runs until the 20th February. Further information on the applicant’s consultation is provided below.
1.3Members may also recall the report, provided for information to the 1st August 2024 Planning Committee, which detailed the Council’s response to the pre-application statutory consultation on the OESF project. This report seeks to provide a similar update for the GNR project, although an opportunity is provided for members to highlight any key areas of concern, to be considered by officers in formulating the Council’s formal response to the statutory consultation.
2.0Update
2.1The Statutory consultation for the GNR project (and all NSIP projects) must be undertaken in accordance with Section 42 (Duty to Consult) of the Planning Act 2008 (PA2008), which requires applicants to consult ‘host’ local authorities (and other statutory consultees/affected parties). In addition to this, there is an obligation to consult the local community in accordance with Section 47 of the PA2008. In respect of the consultation with the community, this must be conducted in accordance with the applicant’s Statement of Community Consultation (SOCC). The SOCC (again, in accordance with Section 47 of the PA2008) was subject to formal consultation with the Council, before it was finalised and officers previously provided comments to the applicant on this document in August of 2024. The current consultation includes a mix of both ‘in person’ and virtual events, as part of the process of informing the community about the proposals and seeking feedback. A summary of these events is presented below, as an extract from the applicant’s consultation material.
2.2In addition to the above, the applicant also organised a pre-briefing ‘in person’ event at the Air and Space Institute on the 15th and 16th of January, open to Parish Councils, Members and Officers. Officers did attend the 15th of January event, as an opportunity to understand how the forthcoming public consultation events would be delivered.
2.3The consultation being undertaken by the applicant is accompanied by a variety of information. One of the key documents is the Preliminary Environmental Impact Report (PEIR), which in effect is an early-stage version of the eventual Environmental Statement (ES) that will be produced, to accompany the application submission (scheduled for the summer of 2025). Also included are the detailed masterplan proposals for scheme at this stage and a draft of the Development Consent Order (DCO) itself.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Great North Road Solar Park: Update ReportReport | 591 KB | DownloadRead as text |
Follow Planning Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 May 2026 | Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 7 May 2026 | Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... | Agreed | Open |
| 7 May 2026 | Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... | Agreed | Open |
| 7 May 2026 | Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... | Agreed | Open |
| 7 May 2026 | Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.