Resolved
AGREED that the contents of the report and the ongoing work of the planning enforcement team be noted.
Planning Committee agreed this item on Thursday 13 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED that the contents of the report and the ongoing work of the planning enforcement team be noted.
Report to Planning Committee: 13 February 2025 Business Manager Lead: Oliver Scott - Planning Development Lead Officer: Richard Marshall - Senior Planner (Enforcement) [email protected]
Report Summary
Report Title Quarterly planning enforcement activity update report.
Purpose of Report To update Members as to the activity and performance of the planning enforcement function over the third quarter of the current financial year.
To provide Members with examples of cases that have been resolved (both through negotiation and via the service of notices) and to provide details and explanations of notices that have been issued during that period.
Period covered 2024 Q3 - 1st October 2024 – 31st December 2024
For noting.
The service assists in the delivery of Community Plan Objectives: Recommendation • Protect and enhance the district’s natural environment and green spaces.
• Be a top performing, modern and accessible Council. 1.0 BACKGROUND
1.1This report relates to the third quarter of 2024/25 from 1st October 2024 to the 31st December 2024 providing an update on enforcement activity during this period.
1.2Schedule A outlines the enforcement activity for Q3 in terms of numbers of cases received, response times and the reasons for cases being closed.
1.3Schedule B includes a small number of examples of where formal planning enforcement action has been taken (such as a notice being issued).
1.4Schedule C provides an example of a case where officers have managed to resolve the breaches through dialogue and negotiation during the third quarter.
1.5Schedule D provides examples of Notices having been complied with. The examples within the report shows considerable success that has been achieved by the enforcement team. 2.0 SCHEDULE A – OUTLINE OF ENFORCEMENT ACTIVITY
2.1Chart 1 sets out the number of new enforcement cases that were received and closed during Q3. Members will note that Officers have managed to close significantly more cases in Q3 than have been opened. Whilst this is not necessarily a demonstration of ‘success’ (as the nature and complexity of cases varies from quarter to quarter) it does demonstrate the amount of hard work being undertaken by officers to resolve open cases.
2.2A project has recently commenced to review older cases and it should be noted that this has contributed to the number of cases being closed in Q3. This will be an ongoing focus going forward into Q4.
Chart 1 - Total Cases Opened and Closed in Q3 2024/25
122 89
Opened Closed
2.3Chart 2 provides a longer time-view of the number of enforcement cases that have been opened and closed in each quarter dating back to Q3 of 2022/23. It should be noted that, apart from the spike in cases during Q2 of 2023/24, the number of cases opened and closed each quarter remains relatively consistent. It will also be noted that the number of cases opened each quarter has been higher than those closed each quarter. This ‘look back’ helps to demonstrate the impressive performance from the entire enforcement team during this most recent quarter in their efforts to reduce the overall number of active cases. 2.4 Chart 3 sets out the reasons why cases have been resolved in Q3. As is generally the case, the chart shows approximately half of cases were closed as ‘No Breach’. It remains important to investigate these cases so there is a record of the complaint and a case file with any associated actions and notes. It is noteworthy that Q3 has seen a sharp increase in cases closed as ‘Breach Resolved’, increasing from 11 in Q1, 17 in Q2 to an impressive 49 in Q3. The remaining categories (BNFA and Other) have held close in Q3 to the numbers in Q2.
Chart 3 - Reasons for Case closures in Q3 2024/25
11 5
57 49
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarterly planning enforcement activity update reportReport | 2.3 MB | DownloadRead as text |
Follow Planning Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 May 2026 | Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 7 May 2026 | Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... | Agreed | Open |
| 7 May 2026 | Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... | Agreed | Open |
| 7 May 2026 | Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... | Agreed | Open |
| 7 May 2026 | Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.