Resolved
AGREED (unanimously) that the Committee noted the report.
Mansfield and District Crematorium Joint Committee agreed this item on Monday 22 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that the Committee noted the report.
1.1During the JCC meeting in May 2025 a project timeline and the arrangements for the project monitoring of the crematorium refurbishment were presented. This report provides members with an update on progress against the project timeline.
2.0Proposal/Options Considered and Reasons for Recommendation
2.1External Project Management
2.2MDC Design Services team have been working with Nottinghamshire County Council who have been managing the procurement of an external project manager. 2.3 Collaboratively, Design Services, the crematorium manager and director for neighbourhood services contributed to the decision making around the weighting of the quality questions for the tender process and given the risks associated with the need for specialist experience the heavily weighted quality questions were around the bidders demonstrating the following: 2.3.1 Experience of crematorium, cemetery, or highly sensitive civic projects, where they have previously acted as Employer’s Agent or PM. 2.3.2 Experience of ensuring service continuity, health and safety, and dignity of operation during construction in a live crematorium environment. approach to the procurement and technical integration of specialist cremator equipment, including early supplier engagement and later novation
2.3.3 Describing their approach to the procurement and technical integration of specialist cremator equipment, including early supplier engagement and later novation
2.4In line with the project plan that can be seen in appendix a, the tender period was due to close at the end of July. Due to several requests to visit the site the tender period was extended by a week to accommodate all of these.
2.5A moderation meeting for the evaluated tenders took place on 11 September. With evaluation of the costs submitted now being carried out by Mansfield’s design services team.
2.6Five out of seven tender submissions received were proceedable to the evaluation process.
2.7Project Monitoring
2.8Considering the length of the procurement process for the external project manager, the first working party meeting took place on 11th September. With the agenda for the first meeting being the following:
2.8.1 Appointment of the PM 2.8.2 Financing updates including the current position with the VAT liability on the project 2.8.3 Communication strategy
2.9Member representative from each of the authority areas are scheduled to meet monthly from the 12th September which will provide members with monthly updates following the appointment of the external project manager.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Crematorium Development ReportReport | 147 KB | DownloadRead as text |
Follow Mansfield and District Crematorium Joint Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Feb 2026 | Operations ReportAGREED (with 6 votes for and 1 abstention) that: i) the committee approve the replacement of the existing crematorium... | Agreed | Open |
| 23 Feb 2026 | Financial Management Review April-December 2025AGREED (unanimously) that the financial information provided in Appendix 1 and Table 1 in the report be noted. | Agreed | Open |
| 23 Feb 2026 | Annual Review of Fees and Charges for 2026/27AGREED (unanimously) that: i) the proposed cremation fee as shown in Table 2 for the period 1 April 2026 to 31 March ... | Agreed | Open |
| 23 Feb 2026 | Revenue and Capital Budget 2026/27 - 2028/29AGREED (unanimously) that: i) the proposed revenue and capital budgets for 2026/27 be approved, as per Appendix 1; ii... | Agreed | Open |
| 23 Feb 2026 | Crematorium Development ReportAGREED (unanimously) that the Committee noted the report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.