AI summaryCabinet approves publication of the Infrastructure Funding Statement by 31 December and changes CIL payments to Town and Parish Councils from twice yearly to once per year, starting 2025/2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedIFS publication, yearly CIL payment, guidance note and procedures
MoneyNot stated
What happens nextPublish IFS before 31 DecemberBegin yearly CIL payments from 2025/2026
Who it affectsNot stated
What was decided
Cabinet approved publication of the Infrastructure Funding Statement before the end of the calendar year, as required by Regulation 121B of the CIL Regulations 2019. Report P15
Cabinet approved paying the CIL meaningful proportion to Town and Parish Councils once per year, rather than twice, starting with monies collected in 2025/2026. Report P10, P25, P28
Cabinet approved the guidance note for Town and Parish Councils on CIL meaningful proportion, including their legal duty to produce an annual report on CIL receipts, spend and balances. Report P7, P15
Why
The Council has a statutory duty to publish the Infrastructure Funding Statement by 31 December each year under Regulation 121B of the CIL Regulations 2019. Report P15
The twice-yearly payment process is considered an unnecessary administrative burden for the Council; the legislation allows the collecting authority to pay annually instead. Report P10, P28
A consultation of all Town and Parish Councils ran from 17 June to 31 July 2025 and 16 councils responded, with the majority supporting the change to annual payment. Report P25, P26, P28
What happens next
Publish the Infrastructure Funding Statement on the Council's website before 31 December, with copies of returns from Town and Parish Councils included. Report P15, P28
Begin making one annual CIL payment to Town and Parish Councils at the end of the financial year for monies collected in 2025/2026. Report P10
Send the new monitoring form and guidance leaflet to all Town and Parish Councils and request completed returns for the Council's records. Report P28
Options considered
Chosen: Pay CIL meaningful proportion to Town and Parish Councils once per year instead of twice. Reduces administrative burden; majority of 16 responding councils supported the change Report P10, P28, P29
Rejected: Keep CIL payments to Town and Parish Councils at twice per year. One objection was received citing loss of interest on the first payment tranche for a six-month period, but this was outweighed Report P29
Rejected: Not publish the Infrastructure Funding Statement. There is a statutory requirement to publish it by the end of the calendar year
Implications
Legal: The Council must meet its duty under Regulation 121B of the CIL Regulations 2019 to publish the Infrastructure Funding Statement by 31 December each year. Report P15
Legal: Town and Parish Councils have a legal duty to publish an annual monitoring statement on CIL receipts, spend and balances. Report P7, P15
Financial: Moving to one annual payment is expected to reduce the administrative burden on the Council. Report P10, P28
Financial: One objector noted a loss of interest on the first payment tranche for a six-month period under the new arrangement. Report P29
Risk: If a Town or Parish Council does not spend CIL within five years of receipt, the Council may serve a repayment notice under Regulation 59E. Report P20
Who and where
Town and Parish Councils in Newark and Sherwood District Report P5, P6, P25, P26
Council officers administering CIL payments and monitoring Report P10, P14
Developers paying CIL on planning permissions (referenced in queries about phased payments) Report P31
Timeline
17th June 2025: Letter sent from Lead Practitioner to all Parish Clerks outlining CIL procedures and the proposed change to annual payment Report P4, P5, P25
17th June to 31st July 2025: Consultation on CIL procedures and payment frequency, with questionnaires issued to all Town and Parish Councils Report P10, P21, P25
31st July 2025: Consultation deadline; 16 Town and Parish Councils responded Report P10, P21, P26
9th December 2025: Cabinet decision to approve the Infrastructure Funding Statement and related CIL changes
by 31st December 2025: Statutory deadline to publish the Infrastructure Funding Statement Report P15
after 31st March 2026: First once-yearly CIL meaningful proportion payment to Town and Parish Councils, covering monies collected in 2025/2026 Report P10
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge developers can pay to local authorities to fund infrastructure
IFS: Infrastructure Funding Statement, the annual statement a charging authority must publish under Regulation 121B
NSDC: Newark and Sherwood District Council
Meaningful proportion: The share of CIL receipts passed to Town and Parish Councils where development has taken place
Regulation 59E: Provision allowing the charging authority to require repayment of CIL if a parish or town council does not spend it as required
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item335
Resolved
That Cabinet: a) approve the publication of the Infrastructure Funding Statement, which has been produced in accordance with the legislative requirements, before the end of the calendar year; b) approve payment of the CIL meaningful proportion to Town and Parish Councils once per annum. This process to commerce for monies collected in the financial year 2025/2026; c) approve the proposed guidance note at Appendix C for Town and Parish Councils, regarding CIL Meaningful proportion including informing them of their legal duty to produce an annual report on CIL receipts, CIL Spend, and CIL monies held in their account; and d) approve the proposed procedures set out at paragraph 2.13 and 2.14 for the spend of CIL for Parish Meetings and Parishes with no meetings. To ensure that the District Council is operating in accordance with the requirements of the Community Infrastructure Regulations. To deliver resource efficiencies by reducing the administrative burden for Newark & Sherwood District Council To provide guidance on various aspects of CIL Meaningful Proportion Spend. Options Considered: None, there is a statutory requirement to publish the IFS by the end of the calendar year. To not make an amendment to the payment of the CIL meaningful proportion to Town and Parish Councils.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Castle House Great North Road Newark Nottinghamshire NG24 1BY
www.newark-sherwooddc.gov.uk
Telephone: 01636 655769 Email: planningpolicy@newark- sherwooddc.gov.uk Your ref: Our ref:
17th June 2025
Dear Parish Clerk,
Re: CIL Procedures and Legal Requirements for Town Councils and Parish Councils I write regarding the procedures and legal requirements relating to the Community Infrastructure Levy (CIL). The Council has a duty to ensure that CIL is managed in accordance with current CIL Regulations ( Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019 ). Consequently, the Council is seeking to engage with Town and Parish Councils on this matter. We would like to understand more about any difficulties you are encountering and to offer help and guidance where needed.
As you will be aware, there is a legal requirement for Town and Parish Councils to publish an annual monitoring statement. We are particularly interested in your annual monitoring process and the projects you have funded through CIL. Please see the attached monitoring form which has been drafted for Parish and Town Councils to use for monitoring purposes.
A CIL Procedures and Legal requirements draft information leaflet is currently being drafted. The Council would be grateful for any feedback on the issues you would like included in the leaflet.
Could you please complete the attached questionnaire on the matters raised above. The Council will use the information received to make any necessary changes.
The Council is also consulting on proposed changes to the number of times CIL is paid to Town and Parish Councils per annum. Currently CIL monies are handed out twice yearly, as required under the legislation. However, the twice annual payment process is considered to be an unnecessary administrative burden for the Council. The legislation does allow for the collecting authority to move to any annual payment and therefore the District Council’s is proposing that one payment is made to the Town and Parish Councils at the end of the financial year (e.g. after the 31st March). We would like to know your views on this proposed change through the enclosed questionnaire. Consultation on this matter will run for 6 weeks until 31st July.
SERVING PEOPLE, IMPROVING LIVES Please don’t hesitate to contact me if you have any queries.
Yours Faithfully,
D Broad Debbie Broad
Lead Practitioner - Infrastructure, Planning Policy and Infrastructure
2 Community Infrastructure Levy (CIL) Parish Council Funding Statement In accordance with Regulation 121B of the CIL Regulations 2019, this report is required to be completed and published no later than 31st December each year. It must be made available on the Parish Council website, and/or Newark and Sherwood District Council’s website. A copy must be sent to [email removed] no later than 31st December. The report must include:
Name of Town or Parish Council Postal Address of Parish Council
Name of Parish Clerk and/or Chairperson (please specify) Email address (es) Telephone number (s) Website address (Please include a link to the report if applicable)
A. Summary of CIL Funding for the reporting year [ADD DATE] Total Amount of CIL received by the Parish Council in the reporting year Total amount of CIL spent by the Parish Council in the reporting year B. Breakdown of CIL expenditure within the reporting year [Date] (Please include photographs of the project where possible) Description of project (please include Total cost of project Amount of CIL monies spent within commencement and end dates and a full reporting year description of the works)
C. Details of any CIL monies returned to NSDC (see CIL Regulations)1 Total monies which have been requested by NSDC from the Parish Council in the reporting year under Reg 59E Total monies which have been requested by NSDC from the Parish Council in the reporting year under Reg 59E BUT not repaid to NSDC by the end of the reporting year
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.