AI summaryCabinet noted housing compliance performance at 30 September 2025, including fire safety and solid fuel rated red, plus interim damp and mould reporting ahead of Awaab's Law.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNo decision taken; report received for assurance
MoneyNoneNo direct financial implications from this report
What happens nextContinued compliance workOutstanding fire risk assessments due by March 2026
Who it affectsCouncil tenants and leaseholdersAround 5,855 domestic properties in portfolio
What was decided
Cabinet noted exceptions to performance of the housing service compliance functions, including fire safety checks, fire door inspections, and solid fuel and oil servicing rated red. Report 2.2, 2.3, 2.8
Cabinet noted interim arrangements for monitoring damp and mould ahead of the introduction of Awaab's Law, with a bespoke report expected once the new Housing Management System is set up. Report 2.9
Cabinet noted ongoing actions to improve and maintain performance across gas, electrical, asbestos, water, and lift compliance. Report 2.1, 2.4, 2.5, 2.7
Why
The report provides assurance on the work undertaken to ensure the safety of tenants and compliance with regulatory standards, linking to Community Plan Ambitions 2 and 7. Report P4, 1.1, 1.3
Performance is rated against targets set at 100% green, 98 to 99.9% amber, and 0 to 97.99% red, as recommended by external auditors and the Regulator of Social Housing. Report 1.5, P10
What happens next
Remaining fire risk assessments for blocks and community centres are scheduled for completion between September 2025 and March 2026. Report 2.2, P21, P22
A new round of fire door inspections will start in January 2026, with major remedial works on flat entrance doors due to finish by the end of December 2025. Report 2.3
A pilot combining domestic legionella risk assessments with gas servicing began on 3 November 2025 to gain access to every property within the next year. Report 2.5
Options considered
Chosen: Note the report and exceptions. Provides assurance on tenant safety and regulatory compliance Report P4
Implications
Legal: Cabinet is the appropriate body to consider this compliance report under the Council's landlord responsibilities. Report 3.3, 3.4
Equalities: No direct equalities implications, though tenant individual circumstances are considered in managing compliance. Report P32
Financial: No direct financial implications arising from this report. Report 3.1
Risk: Fire risk assessment actions are being reviewed and completed weekly, with 389 actions completed and 124 with the contractor as of August. Report 2.2, P20
Other: Data Protection, Digital and Cyber Security, Human Resources, Human Rights, Safeguarding and Sustainability implications were considered by officers. Report 3.0
Who and where
Tenants of the Council's 5,180 properties with domestic gas, 5,855 with electrical installations, and others across the housing stock Report P40, P48
Residents of 106 blocks and 31 community centres subject to fire risk assessments Report 2.2, P83
Tenants reporting damp and mould issues, with 442 repair orders received between April and October 2025 Report P123
Timeline
30 September 2025: End of Quarter 2 performance position Report P4, 1.1, P37
3 November 2025: Pilot commenced combining domestic legionella risk assessments with gas servicing Report 2.5
End of December 2025: Major fire door remedial works due for completion Report 2.3
9 December 2025: Cabinet meeting at which report was noted Report P1
January 2026: New regime of fire door inspections begins Report 2.3
March 2026: Remaining fire risk assessments scheduled for completion Report 2.2, P22
Plain English for the jargon
Awaab's Law: New legal requirements for social landlords to address damp and mould in homes
EICR: Electrical Installation Condition Report, a certificate less than five years old required for properties
FRA: Fire Risk Assessment, a review of fire safety in a building
RAG rating: Red, Amber, Green performance rating system used by the Council
P1, P2, P3: Priority categories for damp and mould repair works, from emergency to major works
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item329
Resolved
That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangements for monitoring damp and mould ahead of introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance. This links to two ambitions in our Community Plan: Ambition 2: Increase the supply of housing, in particular decent homes that residents can afford to buy and rent, as well as improving housing standards and, Ambition 7: Be a top performing, modern and accessible Council that get its everyday services right for the residents and businesses that it serves To provide assurance on the work undertaken to ensure the safety of tenants and compliance with the regulatory standards. Options Considered: None Councillor L. Brazier left the meeting following consideration of this item.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to: Cabinet Meeting: 9th December 2025 Portfolio Holder: Councillor Lee Brazier, Housing Director Lead: Suzanne Shead, Director - Housing Health and Well Being Lead Officer: Norman Emery, Compliance Manager, Housing Maintenance & Asset Management Business Unit
Report Summary
Type of Report Open report / Non-key decision
Report Title Quarter 2 2025-26 - Housing Compliance Assurance Report To provide the performance position as of 30 September 2025 Purpose of Report (Quarter 2) for Housing related compliance and update on activities in the service area. That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangements for monitoring damp and mould ahead of introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance. Recommendations This links to two ambitions in our Community Plan: Ambition 2: Increase the supply of housing, in particular decent homes that residents can afford to buy and rent, as well as improving housing standards and, Ambition 7: Be a top performing, modern and accessible Council that get its everyday services right for the residents and businesses that it serves Alternative Options None. Considered To provide assurance on the work undertaken to ensure the Reason for safety of tenants and compliance with the regulatory Recommendations standards. 1.0 Background
1.1This report provides Members with the performance of housing compliance services at the end of September 2025, focusing on exceptions performance, which is outside the Council’s target parameters.
1.2The full performance summary is shared with SLT; the Portfolio Holder for Housing and discussed as a standard agenda item for the Tenant Engagement Board meetings ensuring that Health & Safety are at the heart of our conversations and actions. Performance is also discussed at Policy and Performance Committee (PPIC) before being presented quarterly at Cabinet (Performance) to ensure there is oversight at Board level.
1.3This report sets out the Council’s performance against the Council’s legal and regulatory landlord responsibilities for a range of building safety measures including fire protection, gas, asbestos, electrical and water. Further information on the Council’s responsibilities can be found here https://www.gov.uk/government/publications/safety-and-quality-standard.
1.4Full details of these performance indicators along with associated commentary are included at Appendix 1 to this report.
1.5The Council’s performance in the report is rated as set out in the table below - as recommended by external auditors and the Regulator of Social Housing:
RAG Rating Ratings detail Colour in 2024/25 Appendix Report Green 100% Amber 98 – 99.9% Red 0 – 97.99%
1.6The report also included information on the number of damp and mould cases and our performance in this area including:
• number of inspections conducted. • number of works order raised and completed. • average time taken to complete works. • percentage completed on time. • average cost of repairs not capitalised (Priority 1 & Priority 2 only)
across three categories (P1-P3) based on the amount and difficulty of the work and in total. The description for each category is listed below and can be found on page 3 of Appendix 1 Key Performance Reporting Scorecard for Housing Compliance.
• P1 - Emergency e.g. excessive mould or major leak. • P2 - Minor repair works and mould wash. • P3 - Major Works undertaken by Asset Team e.g. new Damp Proof Course 1.7 Due to the move to the new Housing Management System, an interim reporting arrangement is in place as the new system is set up for Awaab’s Law (Damp & Mould) and the associated reporting arrangements required. This means regular reports will produce to draws down all repairs with a reference to damp and mould. Post introduction of Awaab’s Law, the team have a bespoke report for damp and mould repairs, ensuring our information on performance is as accurate as possible.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.