CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newark and Sherwood District Council
Planning Committee, Thursday 12 February 2026 at 4.00pm

Land Off Sand Lane, Spalford - 25/02146/PIP

Agreed Planning 1 paper

AI summaryNewark and Sherwood Planning Committee refused Permission in Principle for up to 2 dwellings on land off Sand Lane, Spalford, contrary to the officer recommendation to approve.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedRecorded vote: 12 For, 1 Against refusal
MoneyCIL at £70m2 if approvedHousing Very High Zone 3, CIL at technical stage
What happens nextNo further steps for this applicationApplication refused outright, not deferred
Who it affectsApplicant and Spalford residentsSite at Sand Lane, Rabbit Hill Lane and Chapel Lane

What was decided

Permission in Principle for up to 2 dwellings on land off Sand Lane, Spalford was refused, against the officer recommendation to approve. Report P3, 9.2

A recorded vote was taken because the motion was against officer recommendation, with 12 councillors voting to refuse and 1 against.

Four refusal reasons were recorded: conflict with policies SP3 and DM12, location surrounded by flood zones 2 and 3, unsustainable location, and out of character with the area.

Why

The committee judged the site to be in an unsustainable location for new residential development, contrary to the officer view that it qualified as infill within the village. Report 7.6, 7.7, 7.10

Members were concerned by flood risk, with the site and surrounding village lying in flood zones 1, 2 and 3, including the existing access within flood zone 3. Report P7, 7.16, 7.19

The committee considered the proposal out of character with the surrounding rural farmlands and village edge, despite officer findings that design details were for the technical stage. Report 7.14, 7.31, 7.32

What happens next

No further steps are set out in the papers for this refused application; the applicant would need to lodge a fresh application to progress.

The money

  • £70m2 Community Infrastructure Levy rate for residential development in Housing Very High Zone 3 Report P112, 7.53

Options considered

  • Rejected: Approve Permission in Principle (officer recommendation). Committee considered the site unsuitable due to policy conflict, flood risk, unsustainable location and harm to character Report 9.2, 7.6, 7.16, 7.14
  • Chosen: Refuse Permission in Principle. Conflict with policies SP3 and DM12, flood zones 2 and 3, unsustainable location, and out of character with the area

Implications

  • Legal: Legal advisor present at the meeting; legal reference LEG2526/9679 recorded for the report. Report 8.2, P119
  • Risk: Flood risk across flood zones 1, 2 and 3, with the existing functional access within flood zone 3 outside the red line. Report P7, 7.16, 7.19
  • Equalities: Officers considered Equality and Diversity implications in writing the report. Report 8.1

Who and where

  • The applicant, MC2 London Ltd Report P3
  • Neighbouring residents of properties on Chapel Lane, Sand Lane and Rabbit Hill Lane who objected on grounds of highway safety, cumulative impact, flooding, overlooking and loss of wildlife Report 6.7, 6.8
  • The local ward member, who raised concerns about site suitability and the sustainability of the area Report P4, 6.9
  • Spalford Parish Council, which did not comment at the time of the report Report 6.5

Timeline

  • 24 December 2025: Application form, site location plan, flood risk assessment and planning statement submitted Report P16
  • 5 January 2026: Application registered Report P3
  • 9 January 2026: Officer site visit undertaken
  • 30 January 2026: Site notice expiry date Report 4.1
  • 9 February 2026: Target determination date Report P3
  • 10.40am, 12 February 2026: Committee site visit prior to meeting
  • 12 February 2026: Planning Committee refuses Permission in Principle Report P1

Plain English for the jargon

  • Permission in Principle (PIP): A two stage planning process that establishes whether a site is suitable in principle in terms of location, land use and amount of development, with technical details assessed later.
  • Sequential test: A planning test requiring development to be directed to sites with the lowest risk of flooding.
  • Flood zone 1, 2 and 3: Areas classified by flood risk, with zone 1 being lowest risk and zone 3 the highest.
  • CIL: Community Infrastructure Levy, a charge on new development used to fund local infrastructure.
  • BNG: Biodiversity Net Gain, requiring development to deliver a measurable improvement in biodiversity.
  • DPD: Development Plan Document, part of the local development plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item112

Resolved

AGREED Moved Councillor L Dales and Seconded Councillor D Moore (with 12 votes For, 1 vote Against) that contrary to Officer recommendation Permission in Principle be refused for the following reasons: (i) Policy SP3 & DM12; (ii) Surrounded by flood zone 2 & 3; (iii) Unsustainable location; and (iv) Out of character with the area. In accordance with paragraph 18.5 of the Planning Protocol, as the motion was against Officer recommendation, a recorded vote was taken. Councillor Vote C Brooks For L Dales For S Forde For A Freeman For M Home For K Melton For D Moore For P Rainbow For S Saddington For M Shakeshaft For M Spoors For L Tift For T Wildgust Against The Planning Committee Chair indicated that the meeting duration of an additional one hour had expired therefore a motion was moved by the Chair and agreed by Members to continue the meeting ... view the full minutes text for item 112.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Planning Committee

Report to Planning Committee 12 February 2026 Business Manager Lead: Oliver Scott – Planning Development Lead Officer: Jared Pailing – Planning Development Officer

Report Summary

Application Number 25/02146/PIP Application for permission in principle for a residential development of up Proposal to a maximum of 2 dwellings and a minimum of one Land Off Location Sand Lane Spalford MC2 London Ltd - [name removed] - [name removed] Daniel Evans Registered 05.01.2026 Target Date 09.02.2026 Recommendation That Permission in Principle is Approved

This application is being referred to the Planning Committee for determination as the local ward member has expressed concerns that the site is unsuitable for development.

1.0The Site

1.1The site (outlined in red) comprises of a square parcel of undeveloped land measuring 0.1 hectares in area, fronting onto Sand Lane and running along Rabbit Hill Lane and Chapel Lane. The site is enclosed by a level of foliage and hedging; however, it is noted that trees within the site boundary have been removed. Chapel Lane to the east has a strong residential character that is fairly densely populated, relative to the overall sparse nature of the village and area. Farm buildings are located to the north and west. The proposal relates only to part of the enclosed land as shown below. 1.2 The site is not within a conservation area and there are no listed buildings nearby. The site has the following constraints:

• The entrance to the site and parts of the site are at risk of flooding at varying levels ranging from medium to high risk with predominantly high risk at the site entrance and medium flood risk to the east and west with high risk to the south. It is noted that the proposed redline does not encompass the areas of flood zone 3 (except a sliver to the south) and predominantly encompasses Flood zone 1 and 2. 2.0 Relevant Planning History

2.121/01907/FUL- Provision of Two New Live/Work Dwellings including a building containing garage, car port and detached workspace. – Refused on grounds of inappropriate location for new development and refused on grounds of flood zones 2 and 3.

2.222/02430/FUL - Provision of two new Live/work Dwellings including a separate building containing detached workspaces and under cover parking. – Refused on grounds of inappropriate location for development, unsuitable loss of open/green space and loss of trees and hedgerows. The proposal was also considered to fail the sequential test.

3.0The Proposal

3.1The application seeks Permission in Principle (the first of a 2-stage process) for residential development of up to 2 dwellings. No specific details are required at this stage.

3.2Permission in Principle requires only the location, the land use, and the amount of development to be assessed. If residential development (as is the case in this application), the description must specify the minimum and maximum number of dwellings proposed.

3.3It is the second stage of the process, Technical Details Consent, which assesses the details of the proposal. This must be submitted within 3 years of the Permission in Principle decision.

3.4In terms of accessing the site, no details of this have been submitted. To the north is the existing functional access, however, this is not included within the red line boundary and therefore does not form part of the development. It is assumed as a consequence a new access will be created to the western boundary. As the proposal is for permission in principle, no site plan or elevational details are required to be submitted at this stage. Such details would be considered at the Technical Details Consent stage, if permission in principle is approved.

3.5Documents assessed in this appraisal:

• Application form – Submitted 24th December 2025; • Site Location Plan – Submitted 24th December 2025; • Flood Risk Assessment – Submitted 24th December 2025; • Planning Statement – Submitted 24th December 2025.

4.0Departure/Public Advertisement Procedure

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Land Off Sand Lane, Spalford: 25/02146/PIPReport 611 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
AF
Councillor Andy FreemanChair, present
DM
Councillor David MooreVice-Chair, present
CB
Councillor Celia BrooksCommittee Member, present
LD
Councillor Linda DalesCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
PH
Councillor Peter HarrisCommittee Member, apologies
MH
Councillor Michelle HomeCommittee Member, present
KM
Councillor Keith MeltonCommittee Member, present
PR
Councillor Penny RainbowCommittee Member, present
SS
Councillor Sue SaddingtonCommittee Member, present
MS
Councillor Maurice ShakeshaftCommittee Member, present
TS
Councillor Tom SmithCommittee Member, apologies

All 17 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Land Off Sand Lane, Spalford - 25/02146/PIPThis decision
  2. Land Off Bilsthorpe Road, Eakring - 26/00259/PIPAgreed
  3. Land Off Mansfield Road, Clipstone - 23/01846/FULMAgreed
  4. Land Off Swinderby Road, South Scarle - 25/01914/PIPAgreed
  5. Land Off St Michaels Close, Halam - 25/01319/PIPAgreed
  6. Land Off Sandhills Sconce, Tolney Lane, Newark-On-Trent - 24/02008/S73Agreed

More from Newark and Sherwood Planning Committee

All decisions
MeetingDecisionOutcome
7 May 2026 Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. Agreed Open
7 May 2026 Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... Agreed Open
7 May 2026 Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... Agreed Open
7 May 2026 Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... Agreed Open
7 May 2026 Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies