Planning Committee, Thursday 12 February 2026 at 4.00pm

Middlebeck - Affordable Housing Review (S106)

Agreed Planning 1 paper

AI summaryNewark and Sherwood Planning Committee notes Middlebeck S106 viability review, finding the 15% IRR target unlikely, so no further affordable housing is expected until the next review around 2031.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedReport noted, no decision made
MoneyNot stated
What happens nextThird viability review expected around 2031Covers 1500 to 2000 dwellings
Who it affectsFuture affordable housing at MiddlebeckUp to 3150 home strategic site

What was decided

The Planning Committee agreed to note the S106 viability review report, with no further action required at this stage. Report P35

Why

An independent review by Mercer & Co found the developer's Internal Rate of Return at 9.5% under its own figures and 10.68% under the council's adjusted view, both well below the 15% threshold set in the 2020 S106. Report 2.1, 2.2, 2.6, 2.9

Reaching a 15% IRR would require house price inflation of 8.7% per annum for the rest of the development, which officers consider unlikely given current market forecasts of around 4.11%. Report 2.11, 3.4

Officers say the council has followed the S106 procedure and independent advice, and that the agreement allows for a nil affordable housing outcome within a review portion if the IRR is below 15%. Report 1.8, 3.5, 3.6

What happens next

The master developer Urban and Civic will need to submit a new viability review covering the third portion of 1500 to 2000 dwellings, which is not expected until around 2031 at current build rates. Report 3.4

The remaining 17 affordable units owed from the original 7.5% first tranche target are still expected to be delivered within Key Phase 2, subject to reserved matters approval. Report P15, 1.9

The council will continue to pursue commercial development on the site and progress the Hawton Mill (Middlebeck Basin) site as a community sport hub. Report 3.6

Options considered

  • Rejected: Scenario 1, Urban and Civic baseline figures. Produced a 9.5% IRR, below the 15% threshold Report 2.5, 2.6
  • Rejected: Scenario 2, council's adjusted view by Mercer & Co. Produced a 10.68% IRR, still below the 15% threshold Report 2.8, 2.9
  • Rejected: Scenario 3, goal-seek to reach 15% IRR. Would require 8.7% per annum house price inflation, considered unrealistic Report 2.10, 2.11, 3.4

Implications

  • Financial: No affordable housing is expected to be delivered for the remainder of the current 500 dwelling review portion because the 15% IRR trigger is unlikely to be met. Report 1.8, 3.4
  • Legal: The Planning Committee is the appropriate body to consider the report, which is for noting only; a legal advisor will be present at the meeting. Report P34, P35
  • Other: The S106 leaves room for nil affordable housing within a review portion if the IRR is below 15%, and the council is working to improve site profitability through commercial development and community facilities. Report 3.6

Who and where

  • Future residents of Middlebeck needing affordable housing in the second portion of the development Report 1.8, 3.4
  • Master developer Urban and Civic Report 2.1, 2.2
  • Volume housebuilders including Miller Homes and Bellway, currently on site or progressing contracts Report 1.9, P13, P14
  • Existing residents of the wider Newark area who may benefit from the proposed Hawton Mill community sport hub Report 3.6

Timeline

  • 2010/2011: Original S106 signed, just before the financial crisis stalled the development Report 1.3, 3.5
  • 2014: Development resumed after the financial crisis Report 3.5
  • 2015: S106 varied to revise affordable housing percentages and Southern Link Road phasing Report 1.2, 1.5, 1.6
  • 2020: S106 further revised to set 15% IRR trigger for affordable housing beyond the first 1000 dwellings Report 1.7, 1.8
  • As of October 2025: 623 dwellings occupied and 927 dwellings with reserved matters approval Report 1.9
  • November 2030: End of the 5 year period used in current market forecasts Report 3.4
  • Around 2031: Third viability review portion (1500 to 2000 dwellings) expected to be triggered
  • Q4 2025 to June 2037: Modelled period for house price inflation scenarios in the viability review Report 3.4

Plain English for the jargon

  • S106: Section 106 legal agreement, a planning obligation attached to a consent that can require affordable housing or contributions
  • IRR: Internal Rate of Return, a measure of an investment's profitability over time
  • First Tranche: The first 1000 dwellings of the Middlebeck development
  • Viability Triggers: Dwelling count points at which the developer must submit viability information for review
  • Master Developer: The lead developer for a large strategic site, here Urban and Civic
  • GDV: Gross Development Value, used in simpler viability models for smaller sites
  • Key Phase: A defined phase of residential development within the Middlebeck site allocation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item114

Resolved

AGREED that the report be noted.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Planning Committee

Background

1.1Middlebeck is a strategic site consented under planning permission 10/01536/OUTM for up to 3,150 homes with subsequent commercial, leisure and school developments, as well as the additional infrastructure including the Southern Link Road (SLR) linking the A46 to the west with the A1 to the east.

1.2In 2015 consent was granted for a variation to the original permission (and S106 legal agreement) to change the phasing of the development to allow development to start at the A1 end first and amending some of the contributions within the S106 relating to the sports provision, affordable housing agreed quantum and phasing of the SLR. Details of the original and revised affordable housing quantum are explained below.

1.3Original S106 2011

1.4First Tranche (1000 dwellings) of the development will be 7.5% affordable provision and for the remainder of the Development will be 20% (still less than the policy requirement of 30%) unless viability information is submitted demonstrating that this should be reduced. If viability is claimed, then this should be submitted prior to the first occupation of the 800th, 1300th, 1800th, 2300th, and 2800th dwellings (known as Viability Triggers). If the Council, as Local Planning Authority, concludes that viability challenges exist to justify a reduction in affordable housing (as is the case for all decision-making), a revised affordable percentage will be agreed.

1.5Revised S106 2015

1.6The First Tranche remains at 7.5% for the first 1000 dwellings, however beyond this for the remainder of the development the number of units for affordable housing is 11.5%.

1.7Revised S106 2020

1.8First Tranche remains at 7.5% for the first 1000 dwellings, however for the remainder of the development will be 0% unless at the next review portion (1000th dwelling with every 500 trigger thereafter), a target Internal Rate of Return (ungeared internal rate of return inclusive of growth), is achieved at 15%. For awareness an IRR is used for master developer sites as this given the need for both the master developer and housebuilders to receive reasonable profits. For sites which do not follow the master developer model, which are traditionally smaller and do not need strategic-level infrastructure to unlock them a simple GDV model is used, typically requiring 17.5- 20% profit for the housebuilder. In very simple terms large scale strategic ‘Urban Expansion Sites’ require very significant and costly up-front site infrastructure, meaning profits are not realised until significantly into the development.

1.9As at the time of writing the report, Middlebeck has Reserved Matters approval for 927 dwellings with, as of October 2025, 623 dwellings occupied. Key Phase 1 of the allocation, which is located to the east of the site, is practically completed in terms of residential development, with development moving in to Key Phase 3 with Miller Homes currently onsite. Parcels to the west of the site, in Key Phase 2 have gone out to market, with one volume housebuilder proceeding to contracts. This would then take the number of dwellings over the 1000, which is the First Tranche. Onsite at present, and consented, the affordable housing is spread across the site as follows:

AR = Affordable Rent

SO = Shared Ownership

FH = First Homes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Middlebeck: Affordable Housing Review (S106)Report 391 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
AF
Councillor Andy FreemanChair, present
DM
Councillor David MooreVice-Chair, present
CB
Councillor Celia BrooksCommittee Member, present
LD
Councillor Linda DalesCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
PH
Councillor Peter HarrisCommittee Member, apologies
MH
Councillor Michelle HomeCommittee Member, present
KM
Councillor Keith MeltonCommittee Member, present
PR
Councillor Penny RainbowCommittee Member, present
SS
Councillor Sue SaddingtonCommittee Member, present
MS
Councillor Maurice ShakeshaftCommittee Member, present
TS
Councillor Tom SmithCommittee Member, apologies

All 17 on the meeting page

More from Newark and Sherwood Planning Committee

All decisions
MeetingDecisionOutcome
7 May 2026 Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. Agreed Open
7 May 2026 Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... Agreed Open
7 May 2026 Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... Agreed Open
7 May 2026 Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... Agreed Open
7 May 2026 Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. Agreed Open