Adoption of Public Open Space within the Fernwood North Development (Key Decision)
ApprovedExecutive1 paper
AI summaryCabinet approves Newark and Sherwood District Council buying Public Open Space at Fernwood North from Barratt David Wilson Homes for £1, with maintenance to be funded by a Section 106 contribution and the General Fund.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to Section 106 Deed of Variation and due diligence
Money£1 purchase pricePlus future maintenance from Section 106 and General Fund
What happens nextSection 106 Deed of VariationTo be submitted by Barratt David Wilson Homes
Who it affectsFernwood North residents and councilUp to 1050 new homes and District Council budget
What was decided
Cabinet agreed the Council will enter into arrangements with Barratt David Wilson Homes to buy and maintain the Public Open Space at Fernwood North for £1, subject to conditions. Report P3, P4
The Council will cover future maintenance revenue needs, topped up by an appropriate contribution from the developer, as set out in the exempt financial appendix. Report P5
Delegated authority was given to the Director of Communities and Environment, working with the Street Scene Manager, to complete the land transfer in phases. Report P6
Why
Barratt David Wilson Homes previously agreed in writing not to set up a Management Company on the condition that the Council takes the land for £1. Report P7, 1.6
Fernwood Parish Council resolved on 17 February 2025 that it could not take on the land, leaving the Council as the only realistic public owner. Report 2.0
The move fits with the Council's July 2025 'No Management Company' policy for Strategic Urban Extension sites and the Community Plan goals on biodiversity, environment and climate. Report P7, 2.7
What happens next
Barratt David Wilson Homes will submit a Section 106 Deed of Variation to repurpose money previously set aside for community facilities into Public Open Space maintenance. Report 2.4, 4.2
The Director of Communities and Environment, with the Street Scene Manager and Principal Legal Officer, will carry out due diligence on the extent, type, phasing and legal title of the open space. Report P5, 4.3
The first phase of open space will be inspected and adopted, with further phases following the same process.
The money
£1 Consideration to be paid by the Council to Barratt David Wilson Homes for the Public Open Space Report P3
£350,000 Invested by the Council in improving play parks at ten sites across Newark and Sherwood Report 2.7
£500,000 Transformation of Sherwood Avenue Park in Newark, delivered with Newark Town Council Report 2.7
Options considered
Chosen: Buy the Public Open Space from Barratt David Wilson Homes for £1 and maintain it through the Council. Honours a written agreement, avoids a Management Company charge on residents, and aligns with the No Management Company policy Report P7, 2.7, 3.0
Rejected: Do not buy the land, leaving the developer to find another management route, likely a Management Company. Would repeat past problems in original Fernwood and impose service charges on residents Report 3.0, 1.4
Implications
Financial: The Council will take on ongoing maintenance revenue costs, with details set out in the exempt appendix under reference FIN25-26/9152. Report P5, P27, 4.1
Legal: Legal Services will advise on title to the land and draft the transfer and any Section 106 Deed of Variation, under reference LEG2526/9323. Report 4.2, 4.3
Other: The decision supports the Council's aims on biodiversity, environment and climate change by bringing more open space into public control. Report P7, 2.7
Who and where
Future residents of the Fernwood North development of up to 1050 new homes Report P10, 1.6
Fernwood Parish Council, which decided not to take on the land Report 1.4, 2.0
Newark and Sherwood District Council, which will own and maintain the open space Report P3
Other developers and sites in Greater Fernwood, including Allison Homes and Persimmon Homes schemes Report P10, 1.5, 1.8, 1.9
Timeline
November 2019: Policy and Finance Committee noted agreement that no Management Company would be set up and open space would transfer to the Council Report P14
4 November 2024: Previous Cabinet update on Fernwood open space negotiations Report P32
17 February 2025: Fernwood Parish Council resolved it could not take on ownership of the open space Report 2.0
8 July 2025: Cabinet resolved a 'No Management Company' preferred approach for Strategic Urban Extension sites such as Fernwood Report P32
24 February 2026: Cabinet approves the Council buying and maintaining the Fernwood North Public Open Space Report P1
Plain English for the jargon
POS: Public Open Space, the green and amenity areas within a housing development
ManCo: Management Company, a private firm set up by a developer to charge residents for upkeep of open space and facilities
S106: Section 106 agreement, a legal planning obligation under which a developer provides contributions or works
Deed of Variation: A legal change to an existing Section 106 agreement to alter its terms
Strategic Urban Extension: A large planned housing expansion on the edge of an existing settlement
BDW: Barratt David Wilson Homes, the developer of the Fernwood North site
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item359
Resolved
That Cabinet: a) approve the Council entering into arrangements with Barratt David Wilson Homes (BDW) to purchase (for the consideration of £1) and maintain the Public Open Space within the Fernwood North development, subject to the Council securing: i) an appropriate contribution towards ongoing maintenance costs from BDW, subject to BDW successfully securing and legally executing an agreement with the Council, as the Local Planning Authority, a S106 Deed of Variation as detailed at paragraph 2.4 of the report and within Exempt Appendix A; and ii) completion of satisfactory due diligence by the Director - Communities & Environment, in consultation with the Street Scene Manager and Principal Legal Officer, on the Public Open Space extent, type, and phasing including in relation to the legal title to the land; b) approve the Council covering future maintenance revenue requirements, supplemented by and subject to the required ‘appropriate contribution’ details at a) i ) above, as detailed in the Financial Implications section in Exempt Appendix A; and c) approve that delegated authority be given to the Council’s Director - Communities & Environment, in consultation with the Street Scene Manager, to secure the land transfer from BDW, including appropriate phasing and onboarding of the Public Open Space.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to: Cabinet Meeting - 24 February 2026 Portfolio Holder: Councillor Simon Forde, Climate & the Environment Councillor Paul Peacock, Strategy, Performance & Finance Director Lead: Matthew Finch, Director - Communities & Environment Matt Lamb, Director - Planning & Growth Lead Officer: Ashley Kitchen, Street Scene Manager, Environmental Services, Ext 5738 Lynsey Preston, Senior Planner, Development Management, Ext 5329
Report Summary Open Report / Key Decision with Exempt Appendix The appendix to the report contains exempt information as defined under Schedule 12A of the Local Government Act 1972, Paragraph 3 under which the Cabinet has the power to exclude the press and public if it so wishes. Type of Report It is considered that the need to treat the information in this report as exempt outweighs the public interest in disclosure because a formal legal agreement has not been concluded between the two parties.
Adoption of Public Open Space within the Fernwood North Report Title Development. To put forward a proposal for the District Council to adopt Purpose of Report Public Open Space (POS), including its ownership and ongoing maintenance, within the Fernwood North development. That Cabinet: a) approve the Council entering into arrangements with Barratt David Wilson Homes (BDW) to purchase (for the consideration of £1) and maintain the POS within the Fernwood North development, subject to the Council Recommendations securing:
i) an appropriate contribution towards ongoing maintenance costs from Barratt David Wilson Homes (BDW), subject to BDW successfully securing and legally executing an agreement with the Council, as the Local Planning Authority, a S106 Deed of Variation as detailed at paragraph 2.4 below and within Exempt Appendix A; and
ii) completion of satisfactory due diligence by the Director - Communities & Environment, in consultation with the Street Scene Manager and Principal Legal Officer, on the Public Open Space extent, type, and phasing including in relation to the legal title to the land; b) approve the Council covering future maintenance revenue requirements, supplemented by and subject to the required ‘appropriate contribution’ details at a) i) above, as detailed in the Financial Implications section at Exempt Appendix A; and
c) approve that delegated authority be given to the Council’s Director - Communities & Environment, in consultation with the Street Scene Manager, to secure the land transfer from Barrat David Wilson Homes, including appropriate phasing and onboarding of the POS.
The extant S106 for the Fernwood North development allows Barratt David Wilson Homes (BDW) to set up a Management Company to cover maintenance costs of POS. BDW have honoured a previously verbally and written negotiated position that they would not introduce a Management Company in this instance, an agreement predicated on the land being Alternative Options transferred to the District Council for the consideration of £1. Considered The Council could choose not to purchase the POS for the previously agreed price, in which case BDW would need to find an alternative management route. This would likely mean introducing a management charge on future residents from this point forward, as has been done elsewhere within Fernwood. This would not be appropriate. The recommendations align with the Community Plan objectives in relation to biodiversity, the environment and Reason for climate change. As set out in the report, the development has Recommendations the potential to help the Council secure additionality which is above and beyond simply bringing POS into public ownership.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.