New Newark & Sherwood Local Plan (Key Decision)

Noted Executive 3 papers

AI summaryNewark and Sherwood Cabinet adopts a new local plan timetable, agreeing to issue a notice of intention to commence plan making in March 2026 and prepare two supplementary planning documents by 30 June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlan making to start March 2026
MoneyNot stated in the reportGovernment letter cites national funding, not local sums
What happens nextMarch 2026Notice of intention to commence plan making
Who it affectsDistrict-wide plan and developersNewark and Sherwood local plan area

What was decided

Cabinet adopted the proposed timetable at paragraph 3.5 of the report and gave the Portfolio Holder for Sustainable Economic Development delegated authority to amend it to reflect any new plan-making regulations.

A notice of intention to commence plan making will be issued in March 2026, in line with the adopted timetable.

Supplementary Planning Documents on Affordable Housing and on Developer Contributions and Planning Obligations will be prepared before 30 June 2026.

Why

The government has set a national target of 1.5 million new homes this Parliament and expects all local planning authorities to have an up-to-date local plan as soon as possible. Report P6, P7, P8

The government is replacing the current plan-making system with new regulations expected to come into force early in the new year, removing the planned staged roll-out and the Duty to Cooperate. Report P9, P11, P16, P27

Authorities covered by NPPF transitional arrangements must commence formal plan making (Gateway 1) by 31 October 2026, and plans under the existing system must be submitted for examination by 31 December 2026. Report P17, P22, P23

What happens next

Issue the notice of intention to commence plan making in March 2026 and start preparing the two Supplementary Planning Documents ahead of 30 June 2026.

Bring the timetable into line with any requirements set out in the forthcoming plan-making regulations, using delegated authority held by the relevant Portfolio Holder.

The money

  • over £29 million Government funding already awarded to 188 local planning authorities to support rapid plan preparation Report P8
  • minimum of £14 million Additional government funding in this financial year to support local plan-making Report P18

Options considered

  • Chosen: Adopt the proposed local plan timetable and start plan making. The Council is required to have a Local Plan timetable and has already agreed to prepare a plan as soon as possible

Implications

  • Legal: Plan-making activity is being started in advance of new government regulations, with delegated authority to adjust the timetable once those regulations are published. Report P11, P15
  • Legal: The Duty to Cooperate requirement is being removed for plans progressing under the current system, with co-operation now expected to be guided by national policy and strategic planning. Report P26, P27, P28
  • Risk: The government has indicated it is willing to use intervention powers, including taking over plan-making, where local plans are not progressed as required. Report P24
  • Other: Supplementary Planning Documents on Affordable Housing and on Developer Contributions and Planning Obligations will be brought forward before 30 June 2026 to support the new plan.

Who and where

  • Residents and communities within Newark and Sherwood district Report P6, P7
  • Developers and applicants preparing planning applications in the district Report P7, P8
  • Neighbouring local planning authorities, through ongoing cross-boundary co-operation Report P28

Timeline

  • 27 November 2025: Date of the Minister's letter to council leaders on local plan reforms Report P3
  • March 2026: Notice of intention to commence plan making to be issued
  • 12 June 2026: Deadline for submitting certain plans that reached Regulation 19 before 12 March and meet less than 80% of local housing need, unless a return to Regulation 18 is required Report P23
  • 30 June 2026: Supplementary Planning Documents on Affordable Housing and Developer Contributions and Planning Obligations to be prepared
  • 31 October 2026: Backstop date for authorities covered by NPPF transitional arrangements to commence formal plan making at Gateway 1 Report P17
  • 31 December 2026: Final date for submission of plans for examination under the existing plan-making legal framework Report P22
  • 30 April 2027: Backstop date for authorities whose plan is already over five years old to commence plan making Report P17
  • Early next year: New plan-making regulations expected to come into force Report P15

Plain English for the jargon

  • Local Plan: The council's planning document that sets out the vision, strategy and policies for development in its area.
  • Supplementary Planning Document (SPD): A document that adds further detail to policies in the Local Plan, such as guidance on affordable housing or planning obligations.
  • Regulation 19: A stage under current plan-making rules where a council publishes its proposed submission version of the Local Plan for consultation.
  • Gateway 1: The first formal step in the new plan-making system where an authority notifies its intention to prepare a plan.
  • Duty to Cooperate: A legal duty under the current system requiring local planning authorities to work with neighbours on cross-boundary planning issues; to be removed for plans in the current system.
  • NPPF: The National Planning Policy Framework, the government's national planning policy document.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item362

Resolved

That: a) the contents of the report are noted; b) the proposed timetable at paragraph 3.5 to the report is adopted; c) delegated authority be given to the Portfolio Holder for Sustainable Economic Development to amend the adopted timetable to reflect any regulatory requirements which emerge from the publication of plan making regulations; d) in line with the timetable the notice of intention to commence plan making is undertaken in March 2026; and e) Supplementary Planning Documents in relation to Affordable Housing and Developer Contributions & Planning Obligations are prepared before the 30 June 2026. To approve the New Local Plan Timetable and agree the proposal to begin plan making. Options Considered: None, the Council is required to have a Local Plan timetable and has already agreed to prepare a plan as soon as possible.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Matthew Pennycook MP Minister for Housing and Planning

Ministry of Housing, Communities & Local Government 4th Floor, Fry Building 2 Marsham Street London SW1P 4DF

To: Council Leaders and Metro Mayors in England Cc: Council Chief Executives in England 27 November 2025

Dear Leader,

Local plan reforms

This government was elected on a manifesto that included a clear commitment to build 1.5 million new homes in this Parliament, and all areas are required to play their part. In order to deliver the homes and growth the country needs, we expect all local planning authorities to make every effort to get up-to-date local plans in place as soon as possible.

The plan-led approach is, and must remain, the cornerstone of our planning system. Local plans are the best way for communities to shape decisions about how to deliver the housing and wider development their areas need. In the absence of an up-to-date plan, there is a high likelihood that development will come forward on a piecemeal and speculative basis, with reduced public engagement and fewer guarantees that it will make the most of an area’s potential. It is for these reasons that the level of up-to-date plan coverage we inherited is so problematic.

As a government, we have made a clear commitment to achieving universal local plan coverage. To that end, we have been clear that we intend to drive local plans to adoption as quickly as possible. That is why we introduced transitional arrangements for emerging plans in preparation as part of the changes we made to the National Planning Policy Framework (NPPF) in December last year, and why we have recently awarded over £29 million in funding to 188 local planning authorities to support the rapid preparation of plans that reflect that updated Framework.

However, the current system is optimised neither for speed nor for community participation. We are therefore clear that more fundamental reform is needed to ensure that local plans are faster to prepare and simpler for end users to access and understand. In February, we published the government’s response to the previous government’s consultation on implementation of plan- making reforms. I am today publishing more detailed information about the design of the legislation required to implement the new system; how we intend to roll it out across the country, and the resources that will be made available to support plan-makers to that end.

New plan-making regulations

We will shortly lay the regulations that will underpin our new approach to plan-making. These will reflect our February 2025 response to the previous government’s consultation on the new-plan making system, and their development will take into account responses to that consultation, as well as feedback provided through extensive engagement with the sector.

The regulations will set out a new process for producing plans with clear steps that a local planning authority will need to take. This should support faster preparation of plans and more frequent updates, in line with our aim of universal coverage of up-to-date plans that reflect local needs.

The government is today publishing a summary of what we intend these regulations to contain. This will provide plan-makers and other key stakeholders with the information they need to familiarise themselves with the new system in advance of it coming into force early next year.

Rolling out the new plan-making system

The government is acutely aware that many local planning authorities are keen to start work on plans in the new system at the earliest opportunity, to give themselves the best possible chance of success and provide much needed certainty for their communities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24.02.26: New Newark & Sherwood Local Plan: Appendix AAppendix 195 KB DownloadRead as text
PDF
24.02.26: New Newark & Sherwood Local Plan: Appendix BAppendix 94 KB Download
PDF
New Newark & Sherwood Local Plan (Key Decision)Decisions 323 KB Download

At this meeting

Whole meeting

Who was there

6 of 19 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, apologies
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, apologies
SF
Councillor Simon FordeCommittee Member, present
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected
SK
Sanjiv KohliOfficer, expected

All 19 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. New Newark & Sherwood Local Plan (Key Decision)This decision
  2. Newark A46 Bypass - Update and Next StepsNoted
  3. Newark & Sherwood Local Plan - Scoping Consultation (Key Decision)Noted
  4. Update on the LGA Newark and Sherwood District Council Cyber 360 ReportAgreed
  5. Newark Partnership Hub - A New Approach for Place Based Partnership Working in Town Centre Areas (Key Decision)Agreed
  6. Revisiting - Tenant Engagement at Newark & SherwoodAgreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open