CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newark and Sherwood District Council
Planning Committee, Thursday 12 March 2026 at 4.00pm

Land To The Rear Of Home Farm Barn, Winkburn - 25/01941/PIP

Agreed Planning 1 paper

AI summaryNewark and Sherwood Planning Committee approves Permission in Principle for a site at Winkburn, with Technical Details Consent required within three years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedVote 9 for, 4 against
MoneyNot stated
What happens nextTechnical Details Consent neededMust be submitted within 3 years
Who it affectsWinkburn site rear of Home Farm Barn. Planning application 25/01941/PIP

What was decided

The Planning Committee approved Permission in Principle, with 9 votes for and 4 against. Report 10.1

The Director for Planning and Growth declared an other registerable interest and left the meeting for the next item.

Why

Officers recommended that Permission in Principle be granted, and the committee voted to follow that recommendation. Report 10.1

What happens next

An application for approval of Technical Details Consent must be submitted within 3 years of the decision date. Report P4

Biodiversity net gain will be considered at the Technical Details Consent stage, not at this Permission in Principle stage. Report P6

Options considered

  • Chosen: Grant Permission in Principle. Recommended by officers Report 10.1

Implications

  • Legal: An approval of Technical Details Consent is required within 3 years or the Permission in Principle lapses. Report P4
  • Environment and climate: Biodiversity net gain is not assessed at this stage but will apply to the subsequent Technical Details Consent as a planning condition. Report P5, P6

Who and where

  • The applicant for application 25/01941/PIP Report P2

Timeline

  • 2026-03-12: Planning Committee decision to grant Permission in Principle
  • Within 3 years of the decision: Deadline for submission of Technical Details Consent application Report P4

Plain English for the jargon

  • Permission in Principle: A route to establishing whether a site is suitable for housing-led development, separate from full planning permission.
  • Technical Details Consent: The later stage of planning consent that addresses detailed design after Permission in Principle is granted.
  • Biodiversity Net Gain: A requirement for development to deliver measurable improvements to biodiversity, applied as a condition to planning permissions.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item121

Resolved

AGREED (with 9votes For and 4 votes Against) that Permission in Principle be approved. Having declared an other registerable interest, the Director for Planning and Growth left the meeting for the duration of the following minute.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Planning Committee

Report to Planning Committee – 12 March 2026 Business Manager Lead: Oliver Scott – Planning Development Lead Officer: Dayo Adegbaju, Planner

Report Summary

Application No. 25/01941/PIP

Application for permission in principle for residential development Proposal for minimum of 1 and up to 2 dwellings Land To The Rear Of Home Farm Barn Location Winkburn GraceMachin Winkburn Estate - [name removed] & Property - Adrian Thornhill [name removed] 30.12.2025 Registered 25.11.2025 Target Date EOT until 16.03.2026

Recommendation Grant Permission in Principle

Link to Planning Application website: 25/01941/PIP | Application for permission in principle for residential development for up to 2 dwellings | Land To The Rear Of Home Farm Barn Winkburn

Procedural Matters Reason - Departure from the Development Plan This application is being referred to the Planning Committee for determination as the recommendation is contrary to the Development Plan (contrary to Policy DM8 – Development in the Open Countryside).

1.0The Site

1.1The application site is located within the open countryside, adjacent to the built-up area of Winkburn. It adjoins existing developments which lie to the south and southwest. Home Farm Barn, a Grade II listed building is part of the adjoining II

dwellings. See location plan and google aerial view below.

Google aerial view with site highlighted in red.

2.0Relevant Planning History

2.1None. III

3.0The Proposal

3.1The application is for permission in principle for the development of up to two new dwellings on land to the rear of Home Farm Barn, Winkburn.

3.2The application is to determine the principle of development only, regarding location, use, and amount of development. Detailed drawings would be required at Technical Details Stage if approved.

4.0Departure/Public Advertisement Procedure

4.1Occupiers of 17 properties have been individually notified by letter. A site notice has also been displayed near to the site.

4.2Site visit undertaken on 15.12.2025.

5.0Planning Policy Framework

5.1Newark and Sherwood Amended Core Strategy DPD (adopted March 2019)

Spatial Policy 1 – Settlement Hierarchy Spatial Policy 3 – Rural Areas Spatial Policy 7 – Sustainable Transport Core Policy 3 – Housing Mix Core Policy 9 -Sustainable Design Core Policy 12 – Biodiversity and Green Infrastructure Core Policy 13 – Landscape Character Core Policy 14 – Historic Environment

5.2Allocations & Development Management DPD (2013)

DM5 – Design DM7 – Biodiversity and Green Infrastructure DM8 – Development in the Open Countryside DM9 – Protecting and Enhancing the Historic Environment DM12 – Presumption in Favour of Sustainable Development

5.3The Draft Amended Allocations & Development Management DPD was submitted to the Secretary of State on the 18th January 2024. Following the close of the hearing sessions as part of the Examination in Public the Inspector has agreed a schedule of ‘main modifications’ to the submission DPD. The purpose of these main modifications is to resolve soundness and legal compliance issues which the Inspector has identified. Alongside this the Council has separately identified a range of minor modifications and points of clarification it wishes to make to the submission DPD. Consultation on the main modifications and minor modifications / points of clarification took place between Tuesday 16 September and Tuesday 28 October 2025. The next stage in the Examination process will be the Inspector issuing their draft report.

5.4Tests outlined through paragraph 49 of the NPPF determine the weight which can be afforded to emerging planning policy. The stage of examination which the Amended IV

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Land To The Rear Of Home Farm Barn, Winkburn: 25/01941/PIPReport 637 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
AF
Councillor Andy FreemanChair, present
DM
Councillor David MooreVice-Chair, present
CB
Councillor Celia BrooksCommittee Member, present
LD
Councillor Linda DalesCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
PH
Councillor Peter HarrisCommittee Member, present
MH
Councillor Michelle HomeCommittee Member, present
KM
Councillor Keith MeltonCommittee Member, present
PR
Councillor Penny RainbowCommittee Member, present
SS
Councillor Sue SaddingtonCommittee Member, present
MS
Councillor Maurice ShakeshaftCommittee Member, apologies
TS
Councillor Tom SmithCommittee Member, apologies

All 19 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Land To The Rear Of Home Farm Barn, Winkburn - 25/01941/PIPThis decision
  2. Land to Rear of Mill Lane, Caunton (25/01952/FUL)Agreed
  3. Land To The Rear Of 59 Beacon Hill Road, Newark On Trent, NG24 2JH - 25/02147/PIPAgreed
  4. Land rear of The Vineries, Lower Kirklington Road, Southwell - 23/01836/RMAM (MAJOR)Agreed
  5. Land rear of The Vineries, Lower Kirklington Road, Southwell - 23/01836/RMAM (MAJOR)Agreed
  6. Land to the rear of Ullyats Cottage, Fiskerton Road, Rolleston - 21/02435/OUTAgreed

More from Newark and Sherwood Planning Committee

All decisions
MeetingDecisionOutcome
7 May 2026 Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. Agreed Open
7 May 2026 Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... Agreed Open
7 May 2026 Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... Agreed Open
7 May 2026 Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... Agreed Open
7 May 2026 Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies