AI summaryNewark and Sherwood Planning Committee noted the quarterly planning enforcement update covering six case examples across the district, with two appeals still pending.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedContents and ongoing enforcement work acknowledged by committee
MoneyNot stated
What happens nextTwo appeals pendingOutbuilding and boundary wall enforcement notices under appeal
Who it affectsResidents, businesses and developersAcross Newark and Sherwood district

What was decided

The committee agreed to note the contents of the report and the ongoing work of the planning enforcement team.

Two ongoing enforcement cases are awaiting appeal outcomes: an unauthorised outbuilding (notice issued December 2025) and a high boundary wall at Lilac Farm Cottage (notice issued October 2025). Report P5, P9

Three breaches were resolved without formal action, including an unlawful advertising banner, an unauthorised frontage outbuilding at The Ivies, Newark, and the planting and ecology scheme at Petersmiths Park, Ollerton. Report P17, P23, P33

Why

The report sets out the work of the planning enforcement team during the quarter, illustrating different approaches used to resolve or pursue breaches. Report 6.1, 7.1

Officers considered Data Protection, Equality and Diversity, Financial, Human Rights, Legal, Safeguarding, Sustainability, and Crime and Disorder implications when writing the report. Report 6.1

What happens next

Two enforcement notice appeals are awaiting determination, one relating to an outbuilding requiring render and one to a wall encroaching onto the highway. Report P5, P9

The Petersmiths Park case was treated as a successful intervention, with no further action taken despite minor discrepancies from approved plans. Report P33

Options considered

  • Chosen: Negotiation and engagement with owners to resolve breaches. Used in multiple cases including The Ivies outbuilding, Petersmiths Park landscaping, and Edwinstowe annexe, where breaches were resolved without formal action. Report P22, P23, P31, P33, P43
  • Chosen: Issue Enforcement Notice. Used where negotiation failed, including the outbuilding case (December 2025) and the high wall case (October 2025), both now under appeal. Report P5, P9
  • Chosen: Issue Temporary Stop Notice and Stop Notice. Used at Bridge House Farm due to flood risk and the nature of the breach; both were complied with. Report P48, P49
  • Chosen: Issue Planning Contravention Notice (PCN). Used to confirm details of use at the Edwinstowe annexe; the breach was resolved when the tenant rented the whole dwelling. Report P41, P42, P43

Implications

  • Legal: Two enforcement notices are under appeal, with outcomes pending from the planning inspectorate. Report P5, P9
  • Legal: A planning appeal for retention of an advertising banner was dismissed by the planning inspectorate in April 2025; NSDC only learned of the decision after chasing in October 2025. Report P17
  • Legal: An appeal against refusal of change of use from annexe to independent dwelling at Edwinstowe was dismissed in July 2025. Report P42
  • Other: Officers considered Data Protection, Equality and Diversity, Financial, Human Rights, Legal, Safeguarding, Sustainability, and Crime and Disorder implications when writing the report. Report 6.1

Who and where

  • Owners of a property with an unauthorised outbuilding (case 3.1) Report P5
  • Owners of Lilac Farm Cottage, Water Lane, Oxton, with a high boundary wall Report P6, P7
  • Hoveringham Mammoth Self Store Ltd, operating an unlawful advertising banner at Thurgaton Report P13, P15
  • Owners of a property on The Ivies, Newark, with unauthorised frontage structures Report P20, P22
  • Developer (Gleeson) of Petersmiths Park Housing development, Ollerton, for breach of planting and ecology conditions Report P28, P29
  • Owners of the annexe to The Cottage, West Lane, Edwinstowe, for breach of condition on use Report P38, P40
  • Operator of Bridge House Farm, Winthorpe Road, for unauthorised expansion of a GRT site Report P45, P47

Timeline

  • May 2023: Petersmiths Park planting and ecology breach brought to enforcement team's attention. Report P28
  • June 2023: Outbuilding case (3.1) commenced following concerns about size compared to approved plans. Report P1
  • May 2024: Complaint received about unlawful advertising banner at Thurgaton. Report P14
  • October 2024: Site visit measured outbuilding as 7.1m long x 3.86m deep x 3.1m to ridge. Report P2
  • November 2024: Enquiry received about high wall at Lilac Farm Cottage, Oxton. Report P7
  • April 2025: Planning inspectorate dismissed appeal against refusal of advertising banner retention. Report P17
  • June 2025: First Temporary Stop Notice issued at Bridge House Farm GRT site. Report P48
  • July 2025: Annexe appeal dismissed by planning inspectorate. Report P42
  • September 2025: Further PCN issued to Edwinstowe annexe owner; bridge house farm works ceased after Stop Notice. Report P43, P48
  • October 2025: Enforcement Notice issued on high wall at Lilac Farm Cottage. Report P9
  • November 2025: Unauthorised structures at The Ivies removed by owners. Report P23
  • December 2025: Enforcement Notice issued on outbuilding; all hedging at Petersmiths Park confirmed planted; Bridge House Farm site found compliant. Report P5, P33, P49
  • January 2026: Outbuilding Enforcement Notice appealed by owner. Report P5

Plain English for the jargon

  • PD (Permitted Development): Building or works that can be carried out without needing a planning application, subject to size and location limits.
  • EN (Enforcement Notice): Formal notice issued by a local planning authority requiring action to remedy an unauthorised breach of planning control.
  • PCN (Planning Contravention Notice): Notice requiring information about land and activities to help investigate a possible breach of planning control.
  • BCN (Breach of Condition Notice): Formal notice served where a condition attached to a planning permission has not been complied with.
  • TSN (Temporary Stop Notice): Notice that can stop any activity that breaches planning control for up to 28 days while a decision is made.
  • Stop Notice: Notice that halts an activity which is itself a breach of planning control, even if an enforcement appeal is in progress.
  • GRT: Gypsy and Roma Traveller.
  • LPA (Local Planning Authority): The council responsible for deciding planning applications, here Newark and Sherwood District Council.
  • NCC Highways: Nottinghamshire County Council Highways, the highway authority consulted on highway safety matters.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item127

Resolved

AGREED that the contents of the report and the ongoing work of the planning enforcement team be noted.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Planning Committee

Report to Planning: 12 March 2026 Business Manager Lead: Oliver Scott - Planning Development Lead Officer: Richard Marshall - Senior Planner (Enforcement) [email protected]

Report Summary

Report Title Quarterly planning enforcement activity update report.

Purpose of Report To update Members as to the activity and performance of the planning enforcement function over the fourth quarter of the current financial year.

To provide Members with examples of cases that have been resolved (both through negotiation and via the service of notices) and to provide details and explanations of notices that have been issued during that period.

Period covered 2025/26 Q3 – 1st October 2025 to 31st December 2025

For noting.

The service assists in the delivery of Community Plan Objectives: Recommendation • Protect and enhance the district’s natural environment and green spaces.

• Be a top performing, modern and accessible Council. 1.0 BACKGROUND

1.1This report relates to the second quarter (Q3) of 2025/26 from 1st October 2025 – 31st December 2025 providing an update on enforcement activity during this period.

1.2Schedule A outlines the enforcement activity for Q3 in terms of numbers of cases received, the reasons for cases being closed and response times.

1.3Schedule B includes a small number of examples of where formal planning enforcement action has been taken (such as a notice being issued) in the quarter.

1.4Schedule C provides examples of cases where officers have managed to resolve the breaches through dialogue and negotiation during the quarter.

1.5Schedule D provides examples of Notices having been complied with. The examples within the report shows considerable success that has been achieved by the enforcement team. 2.0 SCHEDULE A – OUTLINE OF ENFORCEMENT ACTIVITY

2.1Chart 1 sets out the number of new enforcement cases that were received and closed during Q3.

Chart 1 - Total Cases Opened and Closed in Q3 2025/26

Opened Closed

2.2Members will note that the number of cases closed once again hit an impressive number (148), which is the 2nd highest quarter closure total going back to the start of 2022/23. This is on the back of 140 closures (now the 3rd highest quarter total) in Q2.

2.3The number of cases opened is a relatively low figure (62). After a high number of cases were opened in Q2, combined with ongoing demanding cases the enforcement team has been dealing with, this lower number of new cases is welcomed.

2.4Chart 2 sets out the reasons why cases have been resolved in Q3.

Chart 2 - Reasons for Case Closures in Q3 2025/26

24 7 57

No Breach Breach Resolved BNFA Other 2.5 The chart shows that, as is always the case, a substantial number of cases that have been closed are due to them not relating to an identified breach of planning control (and thus falling outside of the planning enforcement team’s remit).

2.6These ‘No Breach’ cases generally represent around 50% of cases, although for Q3 this figure is 39%.

2.7We continue to assert the importance of investigating these ‘No Breach’ outcome cases so there is a record of the complaint and any associated action.

2.8The number of cases closed as BNFA (24) in Q3 is the 2nd highest figure since the beginning of 2022/23. These are where a breach has been identified but the harm is minimal, and a decision has been taken that it would not be expedient to take the case any further. The closure reports for these cases are time consuming. This is a continuation of the good form shown in Q2 where 22 cases were closed as BNFA.

2.9Chart 3 provides a brief comparison of the total number of cases opened and closed over the 2025 calendar year versus the previous year (2024). This is just to give an insight into how the last 12-months compares with the previous 12-months

Chart 3 - Comparison of Total Opened and Closed Cases 2024 versus 2025

400 493 300 407 399 371 200

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarterly Planning Enforcement Activity Update ReportReport 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
AF
Councillor Andy FreemanChair, present
DM
Councillor David MooreVice-Chair, present
CB
Councillor Celia BrooksCommittee Member, present
LD
Councillor Linda DalesCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
PH
Councillor Peter HarrisCommittee Member, present
MH
Councillor Michelle HomeCommittee Member, present
KM
Councillor Keith MeltonCommittee Member, present
PR
Councillor Penny RainbowCommittee Member, present
SS
Councillor Sue SaddingtonCommittee Member, present
MS
Councillor Maurice ShakeshaftCommittee Member, apologies
TS
Councillor Tom SmithCommittee Member, apologies

All 19 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Quarterly Planning Enforcement Activity Update ReportThis decision
  2. Quarterly planning enforcement activity update reportAgreed
  3. Quarterly Planning Enforcement Activity Update ReportAgreed
  4. Quarterly planning enforcement activity update reportAgreed
  5. Quarterly planning enforcement activity update reportAgreed
  6. Quarterly Planning Enforcement Activity Update ReportAgreed

More from Newark and Sherwood Planning Committee

All decisions
MeetingDecisionOutcome
7 May 2026 Minutes of the meeting held on 9 April 2026AGREED that the minutes from the meeting held on 9 April 2026 were agreed as a correct record and signed by the Chair. Agreed Open
7 May 2026 Review of the Protocol for Planning Committee and the Planning Committee Scheme of Delegation to OfficersAGREED that: (a) no changes are currently required to the Protocol for Planning Committee or the Planning Scheme of D... Agreed Open
7 May 2026 Land to Rear of Mill Lane, Caunton (25/01952/FUL)AGREED Moved Councillor M Spoors and Seconded Councillor S Saddington (with 11 votes For and 2 votes Against) that co... Agreed Open
7 May 2026 Land to the East of Hockerton Road, Upton (26/00382/PIP)AGREED Moved Councillor K Melton and Seconded Councillor P Harris (with 7 votes For and 6 vote Against) that contrary... Agreed Open
7 May 2026 Land Adjacent Apple Cottage, Bilsthorpe Road, Eakring (26/00377/PIP)AGREED (with 10 votes For and 2 votes Against) that Permission in Principle be approved. Agreed Open