CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newark and Sherwood District Council
Cabinet, Tuesday 9 June 2026 at 6.00pm

Newark & Sherwood Local Plan - Scoping Consultation (Key Decision)

Noted Executive 2 papers

AI summaryCabinet approves Local Plan scoping consultation for July 2026, delegating final document sign-off to the Portfolio Holder for Sustainable Economic Development.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the report and approved proposals
MoneyNot stated
What happens nextScoping consultation July 2026Final document agreed by Portfolio Holder
Who it affectsLocal plan production timetableSets up plan to be adopted April 2029

What was decided

Cabinet approved the scoping consultation proposals set out in Appendix 1, covering the District Profile, evidence base, appraisal approach and consultation methods. Report P8, P9, P10

Authority was delegated to the Portfolio Holder for Sustainable Economic Development, in consultation with the Planning Policy Board, to agree the final Scoping Consultation document.

Authority was also delegated to the same Portfolio Holder to amend the proposed timetable if the Inspectors Report on the Amended Allocations and Development Management DPD requires it.

Why

Parts of the current plan are out of date due to changes in national policy, and the government has directed councils to prepare plans quickly regardless of local government reorganisation. Report P12

The Council must reach Gateway 1, a self-assessment checkpoint, with the aim of starting the formal 30-month process in September 2026. Report P4, P6, P7

Additional government funding is tied to progressing through Gateway 1 by the end of October 2026, which would be difficult if the scoping consultation slipped to August or September 2026.

What happens next

The Scoping Consultation will run for 4 weeks in July 2026, with direct invitations limited to general and specific consultation bodies, local members, town and parish councils, developers and landowners. Report P6, P99, P102, P103

After the consultation, a summary of feedback will be published following the Council passing through Gateway 1, targeted for September 2026. Report P6, P105

The plan will be adopted by April 2029 and become the responsibility of the new merged Council from that date. Report P6, P12

Options considered

  • Chosen: Approve the scoping consultation proposals as set out
  • Rejected: Delay the scoping consultation. Would cause knock-on consequences to the agreed timetable and would make it difficult to reach Gateway 1 by the end of October 2026, risking additional government funding.

Implications

  • Legal: The process must meet the requirements of the Town and Country Planning (Local Planning) (England) Regulations 2026, with statutory consultees identified as general and specific consultation bodies. Report P87, P88, P89, P90, P91
  • Equalities: The Council commits to engaging hard-to-reach groups including young people, older adults, ethnic minorities including gypsies and travellers, people with disabilities and homeless people. Report P93, P94
  • Climate: Ambition 6 of the Community Plan links to planning for climate change mitigation and adaptation, included as a proposed key issue for the new plan. Report P35
  • Risk: Additional stages of consultation beyond the three statutory stages are flagged as a risk that would add significant delay and are recommended to be avoided. Report P121
  • Other: The new plan will be the responsibility of the new Council from April 2029, following local government reorganisation merging the district with some neighbours and part of the County Council. Report P12

Who and where

  • Residents of Newark and Sherwood District Report P3, P8
  • Local members and town and parish councils Report P103, P104
  • Developers and landowners Report P103
  • Statutory consultation bodies including the Environment Agency, Natural England, Highways England, the Coal Authority, Network Rail and others Report P90, P91
  • Hard-to-reach groups including young people, older adults, ethnic minorities, people with disabilities and homeless people Report P93, P94
  • Local voluntary and interest groups and businesses Report P92

Timeline

  • July 2026: Scoping Consultation Report P6
  • September 2026: Gateway 1 Report P6
  • End of October 2026: Government funding deadline for passing through Gateway 1
  • June to July 2027: Consultation on proposed plan content and evidence Report P6
  • November to December 2027: Gateway 2 Report P6
  • March to April 2028: Consultation on proposed Local Plan Report P6
  • July 2028: Gateway 3 Report P6
  • September 2028 to March 2029: Examination of the Local Plan by an independent Planning Inspector Report P6
  • April 2029: Adoption of the Local Plan Report P6

Plain English for the jargon

  • Local Plan: The document setting out a vision for the district, local planning policy, development targets and sites to accommodate development.
  • Scoping Consultation: The initial stage of plan-making which sets out the key issues and how people want to be consulted before formal plan production begins.
  • Gateway: A new mechanism for checking if the Local Plan is progressing appropriately. Gateway 1 is a self-assessment; Gateways 2 and 3 are conducted by an independent Planning Inspector.
  • DPD: Development Plan Document, a formal part of the development plan, here referring to the Amended Allocations and Development Management DPD.
  • SHELAA: Strategic Housing and Employment Land Availability Assessment, the process of seeking and assessing potential development sites.
  • NPPF: National Planning Policy Framework, the government's national planning policy.
  • Grey Belt: Land within the Green Belt that the government has identified may be suitable for development because it is less important to the purposes of the Green Belt.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item397

Resolved

That Cabinet: a) note the report; b) approve the scoping consultation proposals contained in Appendix 1 to the report; c) delegate authority to the Portfolio Holder for Sustainable Economic Development to agree the final Scoping Consultation document in consultation with the Planning Policy Board ready for consultation in July 2026; and d) delegate authority to the Portfolio Holder for Sustainable Economic Development to amend the proposed timetable for the Local Plan Scoping consultation, should this be necessary if the Council receive the Inspectors Report on the Amended Allocations and Development Management DPD. To allow the Scoping Consultation in line with the agreed Newark & Sherwood Local Plan timetable. Options Considered: It was considered that the Scoping Consultation could be delayed, however this will have knock on consequences to the agreed timetable. Furthermore, additional government funding requires the Council to progress through Gateway 1 by the end of October 2026, which would be difficult if the scoping consultation was pushed into August and September 2026.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Appendix 1

Scoping Consultation Introduction

Newark & Sherwood District Council have started the production of new Local Plan. The Local Plan will set out a vision for the District, local planning policy, identifying development targets and sites to accommodate the development.

We are producing the Local Plan under a new system which aims to speed up production. This scoping consultation is the initial stage which we conduct before we formally start the process in September.

The timetable is available here (Local Plan Timetable) and the key dates are:

• Scoping Consultation July 2026 • Gateway 1 September 2026 • Consultation on proposed plan content and evidence June – July 2027 • Gateway 2 November – December 2027 • Consultation on proposed Local Plan March – April 2028 • Gateway 3 July 2028 • Examination of the Local Plan by an independent Planning Inspector - September 2028 to March 2029 • Adoption April 2029

Gateway stages are a new mechanism for checking if the Local Plan is progressing appropriately. Gateway 1 is a self-assessment but Gateways 2 and 3 are conducted by a independent Planning Inspector.

In this scoping consultation we want to set out what we believe the key issues are in producing a local plan for the district and ask how you want to be consulted as part of the production of the plan.

The remainder of the scoping consultation is set out in two parts. Firstly, we have prepared a District Profile which identifies some key information about the district and identify potential issues we need to address. It can be view here (insert link)

The second element sets out what will be in the plan, potential documents – evidence base – to support the delivery of the plan, ways of appraising the plan and our consultation approach.

Why are we doing this now?

This is a reasonable question, as we have only just taken our Allocations & Development Management DPD through examination and in less than two years’ time the District Council will merge with some of its neighbours and part of the County Council to form a new Council. The answer is that because of the changes to national policy elements of our current plan are out of date, the government has directed Councils to prepare plans as quickly as possible whether or not they are going through local government reorganisation. Therefore, we have commenced plan making. The Plan will be the responsibility of the new Council from April 2029 onwards.

Scoping Consultation – Vision & Objectives

<District Profile Results to be inserted>

Preparing a vision

It is important when preparing a plan to have a statement which sets out what you are aiming to achieve and how the place you are planning for will look at the end of the plan period if your plan is successful. The government say that any vision should:

• set out key aims and objectives for your area over the next 15 years or longer

• be ambitious but also reflect what the local plan can realistically achieve through its policies

Our current vision adopted in 2019 states:

By 2033, Newark and Sherwood will become:

“An area providing a high quality of life, made up of thriving sustainable urban and rural communities where people want to and can, live and work. These sustainable, balanced communities will feature good quality housing with a mix of different sizes, types and tenures which will address local needs.

The District will have a successful, diverse economy by providing employment opportunities to a local workforce, equipped with a wide range of skills arising from improved education, learning and training and encouraging tourism potential.

The District will be made up of a hierarchy of attractive and vibrant towns, and larger villages that provide a range of accessible facilities and activities for smaller villages and the surrounding rural areas that is effective and sustainable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09.06.26: Local Plan Scoping Consultation: Appendix 1Appendix 283 KB DownloadRead as text
PDF
Newark & Sherwood Local Plan: Scoping Consultation (Key Decision)Decisions 188 KB Download

At this meeting

Whole meeting

Who was there

8 of 24 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
PH
Councillor Peter HarrisCommittee Member, apologies
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected

All 24 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Newark & Sherwood Local Plan - Scoping Consultation (Key Decision)This decision
  2. Update on the LGA Newark and Sherwood District Council Cyber 360 ReportAgreed
  3. Revisiting - Tenant Engagement at Newark & SherwoodAgreed
  4. Bassetlaw, Newark and Sherwood Community Safety Partnership UpdateAgreed
  5. Enhancing Tenant Engagement at Newark and SherwoodAgreed
  6. Update on the LGA Newark and Sherwood District Council Cyber 360 ReportAgreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies