Local Regeneration Fund Update (Key Decision)

Noted Executive 1 paper

AI summaryCabinet approves up to £1.5m extra for Castle Gatehouse, commits £500,000 to Ollerton enabling works, and notes progress across the £45m Local Regeneration Fund programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedExtra budget and forward-funding approved for LRF projects
MoneyUp to £1,500,000 plus £500,000Castle Gatehouse top-up and Ollerton enabling works
What happens nextOllerton planning decision June 2026Market Place works on site from January 2026
Who it affectsNewark, Ollerton and Clipstone residentsTown centre users, future home occupiers and businesses

What was decided

Cabinet noted the updates across the Local Regeneration Fund programme, covering eight projects in Newark and Sherwood with £45m of grant funding, four now complete and four ongoing. Report P4, P5

Cabinet approved a revenue budget from the Change Management Reserve for the 32 Stodman Street re-development, as set out in the exempt appendix. Report 1.3

Cabinet approved an additional capital budget of up to £1,500,000 for Castle Gatehouse from the Change Management Reserve, taking the overall project budget to £8,064,860, and agreed to commit £500,000 of capital for Ollerton enabling works ahead of planning consent and legal finalisation. Report P16, P22, P39, P40

Why

The Local Regeneration Fund, announced in September 2025, replaced the earlier Towns Deal and Levelling-Up Fund 3 awards, and all £45m must be spent by 31st March 2028. Report P2, P3, P4, P5

Castle Gatehouse has been hit by unexpected archaeological discoveries and chimney deterioration, requiring extra funding to keep Phase 1 on track within the spending deadline. Report P14, P15, P16

Forward-funding the Ollerton works is needed to keep utility orders and cinema fit-out design moving and avoid delays to the project critical path. Report P22

What happens next

Works on 32 Stodman Street are expected to complete within the coming months, with retail and residential tenants either secured or under negotiation. Report P8

Newark Cultural Heart Market Place Improvement site works are expected to start in January 2026 and complete in early 2027, within the £3,610,000 capital budget. Report P11, P37

The Ollerton planning application is expected to be determined in June 2026, with the construction contract and cinema operator Heads of Terms targeted for Summer 2026; a further Cabinet update on Clipstone is planned next month. Report P20, P27

The money

  • £25m Towns Deal awarded to Newark in 2020 Report 1.1
  • £20m Levelling-Up Fund 3 award covering Ollerton and Clipstone Report P2
  • £45m Total Local Regeneration Fund programme across Newark and Sherwood Report P4, P5
  • £1,500,000 Additional capital budget approved for Castle Gatehouse from the Change Management Reserve Report P16, P40
  • £500,000 Capital committed for Ollerton Regeneration enabling works, funded by LRF grant Report P22, P42
  • £8,064,860 New overall Castle Gatehouse project budget after the approved increase Report P39
  • £3,610,000 Capital Programme budget for Newark Cultural Heart Market Place Improvement, fully LRF funded Report P37

Options considered

  • Rejected: Do not proceed with delivery of the LRF programme. Would miss the opportunity to deliver transformational change and accelerate local economic growth

Implications

  • Financial: Castle Gatehouse budget increases by up to £1,500,000 from the Change Management Reserve; new overall project total of £8,064,860 is funded from Towns Fund Grant, NLHF, Change Management Reserve and NSDC borrowing, with NSDC contribution around 33%. Report P16, P17, P39, P40
  • Legal: Legal Services to be instructed on Castle Gatehouse additional funding arrangements and are supporting ongoing legal agreements for Ollerton with the Town Council and contractor. Report P31, P33
  • Risk: Archaeological findings at Castle Gatehouse (medieval wall, garderobe pit, well) and chimney deterioration are causing delays; the council is working with the contractor to limit cost and time impact. Report P14, P15, P16
  • Other: Officers also considered Data Protection, Equality and Diversity, Human Resources, Human Rights, Safeguarding, Sustainability, Crime and Disorder, and LGR implications, mostly assessed as not applicable. Report 2.0

Who and where

  • Newark town centre residents, visitors and businesses Report P8, P11
  • Future residents and tenants of 32 Stodman Street Report P8
  • Ollerton residents and town centre users Report P19, P20
  • Clipstone residents and prospective commercial occupiers Report P24, P25
  • Clipstone Miners Welfare Community Trust as eventual owner and operator of the new sports site Report P26
  • Newark and Sherwood District Council as LRF Accountable Body Report P27

Timeline

  • 2020: Newark awarded £25m Towns Deal Report 1.1
  • April 2025: MHCLG formally confirms £20m Levelling-Up Fund 3 with a revised spend deadline of 31st March 2028 Report P2
  • September 2025: MHCLG announces the Local Regeneration Fund, merging Towns Deal and LUF 3 Report P3
  • January 2026: Newark Cultural Heart Market Place Improvement site works expected to commence Report P11
  • May 2026: Mansfield District Council expected to determine the former Lido Site planning application linked to Clipstone Phase 2 Report P26
  • June 2026: Ollerton planning application determination anticipated Report P20
  • Summer 2026: Ollerton construction contract and cinema operator Heads of Terms expected to be signed Report P20
  • 31st March 2028: Deadline for spending all Local Regeneration Fund grant monies Report P5, P22

Plain English for the jargon

  • Local Regeneration Fund (LRF): UK Government funding stream announced in September 2025 that merged the Towns Deal and Levelling-Up Fund 3 into a single programme.
  • Change Management Reserve: Newark and Sherwood District Council reserve used to fund the additional Castle Gatehouse capital budget and the Stodman Street revenue budget.
  • RIBA Stage 4: Detailed design stage in the Royal Institute of British Architects' Plan of Work, used here for the Market Place Improvement and Ollerton projects.
  • Full Business Case (FBC): Approved funding-stage document required before progression to detailed design on LRF projects.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item396

Resolved

That Cabinet: a) note the updates associated with the LRF projects, as detailed throughout this report; Stodman Street Re-Development b) approve a revenue budget from the Change Management Reserve as detailed in the exempt appendix to the report; Castle Gatehouse c) approve an additional capital budget of up to £1,500,000, funded by the Change Management Reserve, as detailed in section 1.5 of the report; and Ollerton Regeneration d) agree to commit £500,000 capital monies (fully funded by the LRF grant and NSDC committed Reserves) within the existing approved programme and add this to the proposed capital budget for 2026/27 to progress essential enabling works ahead of the completion of legal agreements and confirmation of planning consent, as set out in section 1.7 of the report. The projects detailed within this report deliver on the LRF strategic objectives set by the UK Government, as well local the ambitions set out within the Community Plan. This includes driving improved health and wellbeing through the creation of community infrastructure and cultural/leisure opportunities as well as and opportunities for local people through skills and employment-based interventions and unlocking long-term sustainable economic growth . Options Considered: There remains an option not to proceed with the delivery of the projects within the LRF programme. This is not recommended as it would present a missed opportunity to deliver transformational and impactful change for the local community and to accelerate local economic growth.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Background

1.1In 2020, Newark was awarded £25m through the UK Government’s Towns Deal to support the delivery of several transformational capital projects across the town. The fund aims to boost economic regeneration, infrastructure, and skills in over 100 towns across the UK. The local priority projects are underpinned by a 30-year Town Investment Plan (TIP), developed in partnership with the Newark Town Board at the time.

In addition to the Towns Deal, Newark and Sherwood District Council (NSDC) was awarded £20m through the UK Government’s Levelling-Up Fund 3 (LUF 3) to support the delivery of the ‘Shaping Sherwood’s Revival scheme’. This scheme comprises two local priority place-shaping projects including the redevelopment of Ollerton Town Centre and the Clipstone Regeneration project. Cabinet will re-call that this award was announced by the UK Government on an in-principle basis in late 2023. It should be noted that as a result of both the programme onboarding process and subsequent delays due to a national review of the LUF 3 programme at the time, planning and project development works for both the Ollerton and Clipstone projects were significantly restricted throughout 2024 and early 2025, until the LUF 3 grant was agreed. In April 2025, SDC received formal confirmation of the £20m funding from the Ministry of Housing, Communities and Local Government (MHCLG) (with a revised spend deadline of 31st March 2028), allowing both feasibility and development works to continue over recent months.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Regeneration Fund Update (Key Decision)Decisions 241 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 24 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
PH
Councillor Peter HarrisCommittee Member, apologies
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected

All 24 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Local Regeneration Fund Update (Key Decision)This decision
  2. Local Regeneration Fund (LRF) Programme UpdateNoted
  3. Local Regeneration Fund and Newark Capital Projects Update (Key Decision)Noted

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open