1) That the Committee confirms that it considers that a reappraisal of the financial viability of the development should be required if the development is not substantially commenced within 18 months of the date of the grant of planning permission; 2) That the Committee confirms that it considers clearance of the site in this case would not constitute “substantial commencement” of the development, for the purposes of the desired planning obligation; 3) That the Committee confirms that it considers that the agreement should not be worded so as to accommodate some provisions whereby if the applicant encounters adverse ground conditions on this then, in such circumstances, the deadline in the Section 106 after which a reappraisal would be required can be extended; and 4) That should the applicant not indicate that they are willing to enter into a Section 106 agreement on the basis set out within recommendation 1), within 14 days of being informed of this decision, that the application be refused on the ground that without such an undertaking account would not be able to be appropriately taken of a change in market conditions and a development that could have made required contributions would not do so
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
The Planning Committee resolved, at its meeting of 3rd February 2015, to grant full planning permission for the demolition of the former Newcastle Baptist Church and the erection of a residential development containing 14 two bed units and 8 one bed units, subject to the applicant first entering, by the 17th March 2015, into Section 106 Obligations to secure the review of the financial assessment of the scheme if there is no substantial commencement of the development within a year of the grant of planning permission and contributions then being made to affordable housing (up to 6 units), and public open space (up to £60,684 index linked) if the scheme is evaluated at that time as able to support such contributions. Any permission to be granted was to be the subject of a number of conditions as set out in the resolution.
Failing completion by the 17th March of the above planning obligations the Head of Planning was given delegated authority to either refuse the application on the grounds that without such an undertaking account would not be able to be taken of a change in market conditions and a development that could have made required contributions would not do so; or if he considered it appropriate, to extend the period of time within which the obligations could be secured
As previously reported at the end of March in the light of the inability of the Council, due to capacity issues at that time within Legal Services, to provide a draft in a timely manner, it was necessary to set a new deadline (for completion of the Section 106) beyond the 31st March. In June members were advised that since March the applicant had prepared a draft agreement, but that had not been responded to by your Officer, and they (the applicants) had actively being pursuing progress – i.e. the Council’s comments upon the Draft.
The applicant has now, following the provision of comments in late August by the Council on the Draft prepared by the applicant in early April, requested that the agreement be concluded on the basis that a reappraisal of the financial position is only required if, within two years of the planning permission rather than one, there is no substantial commencement of the development. This report addresses that request.
The applicant has also proposed a further alternative and this too also is considered within this report.
The reason this item is brought to the Committee as an item of urgent business is that the applicant, who is most concerned about delays on the Council’s part, is proposing unless agreement can be reached, to lodge an appeal against the non-determination by the Council of the application, and if the Council is to agree to the applicant’s request it needs to do so without delay. RECOMMENDATIONS
1) That the Committee confirms that it considers that a reappraisal of the financial viability of the development should be required if the development is not substantially commenced within 18 months of the date of the grant of planning permission;
2) That the Committee confirms that it considers clearance of the site in this case would not constitute “substantial commencement” of the development, for the purposes of the desired planning obligation;
3) That the Committee confirms that it considers that the agreement should not be worded so as to accommodate some provisions whereby if the applicant encounters adverse ground conditions on this then, in such circumstances, the deadline in the Section 106 after which a reappraisal would be required can be extended; and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.