( i ) That the report be received (ii) That the Head of the Planning with the Development Management Team Manager seek to maintain performance of the Development Management team where satisfactory and improve the service provided where the level of performance may otherwise fall below targets adopted in the 2018/19 Planning and Development Service Plan (iii) That the ‘Mid-Year Development Management Performance Report 2018/19’ be submitted to the Committee around November/December 2018 reporting on performance achieved for the first half of 2018/19 in relation to these targets, including the 7 indicators considered in the report.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide members with an end of year report on the performance recorded for Development Management between 1st April 2017 and 31st March 2018. Figures for 2015/16 and 2016/17 are also provided, as are the targets set out within the 2017/18 Planning and Development Service Plan, and performance targets adopted for 2018/19.
Recommendations
(a) That the report be received
(b) That the Head of the Planning with the Development Management Team Manager seek to maintain performance of the Development Management team where satisfactory and improve the service provided where the level of performance may otherwise fall below targets adopted in the 2018/19 Planning and Development Service Plan
(c) That the ‘Mid-Year Development Management Performance Report 2018/19’ be submitted to the Committee around November/December 2018 reporting on performance achieved for the first half of 2018/19 in relation to these targets, including the 7 indicators considered below.
Reasons
To ensure that appropriate monitoring and performance management procedures are in place and that the Council continues with its focus on improving performance, facilitating development and providing good service to all who use the Planning Service.
Background
An extensive set of indicators is collected to monitor the performance of the Development Management. These indicators have changed over time and officers have sought to ensure that the right things are being measured to enable us to improve performance in every significant area. The range of indicators included reflects the objective of providing a balanced end to end development management service, including dealing with pre-application enquiries, breaches of planning control, considering applications, and approving subsequent details and delivering development.
2. Matters for consideration:
There is an Appendix attached to this report:-
APPENDIX 1: PERFORMANCE INDICATORS FOR DEVELOPMENT MANAGEMENT 2015/16, 2016/17, and 2017/18: Contains quarterly and annual figures for the Performance Indicators applicable during 2017/18 (comparative figures for 2015/16 and 2016/17 are also shown).
This report provides a commentary on the performance achieved against the performance indicator targets as set out in detail in Appendix 1. It follows on from a report that was considered by the Planning Committee at its meeting on the 6h December 2017 which reported on the mid-year performance figures and gave predictions on whether the targets for 2017/18 set in the 2017/18 Planning & Development Service Plan would be likely to be achieved.
Cabinet receives a Quarterly Financial and Performance Management report on a series of performance indicators including currently the three below which relate to the speed of determination of planning applications, and any indicators failing to meet the set targets are reported by exception. A report on performance across the Planning Service is due to be considered by the Economy, Environment and Place Scrutiny Committee at its meeting on the 4th July.
3. The performance achieved in relation to the targets for 2017/18, and the targets for 2018/19:
7 indicators, all measuring speed of performance, were included in the 2017/18 Planning and Development Service Plan relating to Development Management. These are referred to in the commentaries below. Members will note that out of these 7 performance indicators, the target set by the Council for itself has been met in 2017/18 in only 2 cases, and has not been achieved in the other 5.
In consultation with the Planning Portfolio holder there has been a review of the Service’s targets and it has been agreed that in all but two of the indicators the target will remain unchanged for 2018/19. The change that has been agreed will be set out below.
INDICATOR Percentage of applications determined within the following timescales:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.