That the application to modify the S106 agreement, by extending the period of time within which the developer must substantially commence development before the need for a revised viability report is triggered to 25 June 2022, be approved. The decision would have a note attached, advising that this Committee would be very unlikely to agree to any further extensions of time.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
That the application to modify the S106 agreement, by extending the period of time within which the developer must substantially commence development before the need for a revised viability report is triggered to 25 June 2022, be approved.
Reason for recommendation
The obligation continues to serve a useful purpose, but would serve that purpose equally well subject to the modifications specified in the application.
Key Issues
The application under Section 106A of the 1990 Town and Country Planning Act seeks to modify the planning obligations entered into on the 2nd April 2015 prior to the grant of outline planning permission (13/004970/OUT) for residential development of up to 100 dwellings, as varied by the Deed of Variation (DoV) dated 17 December 2019 and 20th August 2020.
As indicated above the modification sought is to paragraph 2 of Schedule 6 of the Agreement as amended by the DoV to provide a further 9 months for the development to be substantially commenced, at which point the developer is required to prepare and submit a revised viability report if this trigger is not reached. This is additional to the 12 months extension already granted. This would extend the period of time from 25th September 2021 to 25 June 2022.
This application is again made in response to the impact that Covid-19 has had on construction. Such impacts are acknowledged.
Keele Parish Council have expressed surprise in the delay in the commencement of development and the need for this application given the speed of house construction taking place in the local area. Whilst initially there was little interest in this site from house building companies it is understood that this has now changed and that a developer could be secured in the near future. It is, however, clear that substantial commencement of the development as defined in the planning obligation is no longer possible by the current deadline of 25th September. Unless modified the requirement to carry out a reappraisal will be triggered.
The significant abnormal costs involved in preparing the site for development, primarily the remediation works to address the burning spoil heap, remain unchanged. In light of this there is little prospect that the viability of the development will have improved and that more policy compliant contributions could be secured. Notwithstanding this the requirement to carry out a viability reappraisal will create uncertainty that could discourage development of this site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.