APPLICATION FOR MAJOR DEVELOPMENT - CHATTERLEY VALLEY DEVELOPMENT SITE, PEACOCK HAY ROAD. HARWORTH GROUP PLC. 21/00570/FUL

Approved Planning 3 papers

Planning Committee approved this item on Tuesday 14 September 2021. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

That the application be permitted subject to the undermentioned conditions: (i) Time limit (ii) Implementation in accordance with the approved plans (iii) No development to commence until a Sustainable Drainage Strategy has been submitted and agreed, which is to be fully implemented. (iv) No development to commence until intrusive site investigation works, if required by the Coal Authority, and remedial works have been undertaken in accordance with approved details (the final wording of the condition to be agreed with the Coal Authority prior to the issuing of the planning permission). (v) Detailed structural landscaping scheme to be submitted and approved within 12 months of the commencement of the earthworks on any phase which shall include the retention of Category B trees if possible, or their replacement if not. The scheme is to accord with the Green Infrastructure Strategy and should include the planting of a verge adjoining the footpaths. The structural landscaping scheme shall be implemented prior to the commencement the construction of buildings within that phase. (vi) Approval of tree and hedgerow protection measures. (vii) Approval and implementation of woodland and landscape management plans. (viii) No development shall take place on any part of the site until the development has secured the implementation of a programme of archaeological works (ix) Limit on the number of daily HGV movements for the duration of the earthworks to a maximum of 400 HGV two-way movements per day and not more than 20 HGV two-way movements in either the AM peak hour (08:00 to 09:00) or the PM (17:00 to 18:00). (x) Approval and implementation of a Construction Traffic Management Plan (xi) The reporting of unexpected contamination and preventing the importation of soil or soil forming material without approval.
Word for word from the decision Newcastle-under-Lyme published for this meeting. Source: moderngov.newcastle-staffs.gov.uk

Follow this further

Built from Newcastle-under-Lyme's papers

What the report saysPro

Report to Planning Committee

Chatterley Valley Development Site 21/00570/FUL

This map is reproduced from the Ordnance Survey material with the permission of Her Majesty's Stationery Office. © Crown copyright. Unauthorised reproduction infringes Crown copyright and may lead to civil proceedings. Newcastle-under-Lyme Borough Council - 100019654 - 2021

Newcastle Borough Council ¯ 1:8,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
21 570Report 827 KB DownloadRead as text
PDF
APPLICATION FOR MAJOR DEVELOPMENT: CHATTERLEY VALLEY DEVELOPMENT SITE, PEACOCK HAY ROAD. HARWORTH GROUP PLC. 21/00570/FULReport 178 KB Download
PDF
First supplementary report Chatterley Valley 2100570FUL EMSupplementary 254 KB Download

At this meeting

Whole meeting

Who was there

12 of 25 attended
AF
Councillor Andrew FearChair, present
MR
Councillor Marion ReddishVice-Chair, present
SB
Councillor Silvia BurgessCommittee Member, present
DJ
Councillor Dave JonesCommittee Member, present
SM
Councillor Sue MoffatCommittee Member, present
GW
Councillor Gillian WilliamsCommittee Member, present
JW
Councillor John WilliamsCommittee Member, present
JC
Councillor Jennifer CooperCommittee Member, apologies
HM
Councillor Helena MaxfieldCommittee Member, present
PN
Councillor Paul NorthcottCommittee Member, present
MH
Councillor Mark HollandCommittee Member, present
M-
Mayor - Councillor Kenneth OwenCommittee Member, present

All 25 on the meeting page

On this subject at Newcastle-under-Lyme

Search all
  1. APPLICATION FOR MAJOR DEVELOPMENT - CHATTERLEY VALLEY DEVELOPMENT SITE, PEACOCK HAY ROAD. HARWORTH GROUP PLC. 21/00570/FULThis decision
  2. Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulAgreed
  3. Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remApproved
  4. Application for major development - baldwin's gate farm, newcastle road, baldwin's gate. mr chris o'hanlon, bellway homes limited. 26/00447/fulRefused
  5. Application for major development - baldwin's gate farm, newcastle road, baldwin's gate. mr chris o'hanlon, bellway homes limited. 25/00931/fulRefused
  6. Application for major development - baldwins gate farm, newcastle road, baldwins gate, newcastle. st5 5es. mr chris o'hanlon. bellway homes ltd. 26/00052/fulRefused

More from Newcastle-under-Lyme Planning Committee

All decisions
MeetingDecisionOutcome
18 Aug 2026 Minutes of previous meeting(s)That the minutes of the meeting held on 21 July, 2026 be agreed as a correct record. Agreed Open
18 Aug 2026 Application for major development - tadgedale quarry. wain homes north west. 24/00589/fulThat the application be permitted subject to the undermentioned conditions: (i) Variation of condition 2 to refer to ... Agreed Open
18 Aug 2026 Application for major development - land off bar hill road onneley. owl homes limited. 25/00897/remThat the application be permitted, subject to the undermentioned conditions: (i) Link to outline planning permission ... Approved Open
18 Aug 2026 Application for other development - 25-27 well st & 82 garden st, newcastle. marshallsay. 26/00051/couThat the application be refused for the following reasons: (i) Contrary to Policy HOU7 (Homes in Multiple Occupation)... Refused Open
18 Aug 2026 Five-year housing land supply update report 2026-31(i) That Members note the content of the five-year housing Land supply position statement (appendix 1) and agree that... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies