The application to modify the S106 agreement, to change the red edge site boundary and to secure a financial contribution of £83,110 towards secondary school places at Madeley High School, Madeley, a contribution of £80,000 towards the maintenance and improvement of public open space at the playground facilities at Heath Row, Madeley Heath and a review mechanism of the scheme’s ability to make a more or fully policy compliant contribution to education places, off site public open space and/ or affordable housing, if the development is not substantially commenced within 12 months from the date of the decision, and the payment of such a contribution if then found financially viable, was approved.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
A) That the application to modify the S106 agreement, to change the red edge site boundary and to secure a financial contribution of £80,726 towards secondary school places at Madeley High School, Madeley, a contribution of £80,000 towards the maintenance and improvement of public open space at the playground facilities at Heath Row, Madeley Heath and a review mechanism of the scheme’s ability to make a more or fully policy compliant contribution to education places, off site public open space and/ or affordable housing, if the development is not substantially commenced within 12 months from the date of the decision, and the payment of such a contribution if then found financially viable, be approved.
Reason for recommendation
It is accepted, following the obtaining of independent financial advice, that a policy compliant scheme is not viable and that the scheme can only sustain reduced contributions. It is accepted that the benefits of the development are considered to outweigh the harm caused by the additional demand created by the development on education places and public open space in the area. A Section 106 agreement is required to secure those policy compliant contributions which can be afforded and a viability review mechanism should substantial commencement not be achieved promptly, along with the amendments to the red edge development site.
Key Issues
1.1A report came before the 14th September planning committee whereby members resolved not to accept the conclusions of independent financial advice that the scheme can only support a financial contribution of £83,110 towards secondary school places at Madeley High School. The reason was that the level of Section 106 Obligations that this development can support is not policy compliant and therefore not sufficient to mitigate the impact of the proposed development.
1.2The completed S106 agreement, dated the 10th August 2018, secured 25% Affordable Housing onsite, a financial contribution of £5,579 per dwelling towards the maintenance and improvement of public open space at the playground facilities at Heath Row, Madeley Heath and £77,217 towards primary school places at Sir John Offley CE(VC) Primary School in Madeley and £83,110 towards secondary school places at Madeley High School, Madeley. 1.3 Since the September meeting, legal advice has been received advising that the modification of the S106 Agreement application and the reserved matters application should have been treated separately. Therefore, notwithstanding the decision of members at the September meeting, separate reports have been prepared and a decision on each now needs to be made separately.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.