That 1. Progress with Kidsgrove Town Deal be noted and Cabinet will continue to receive such updates as required. 2. Completion of the Kidsgrove Sports Centre be noted 3. Progress with the Chatterley Valley project be noted. 4. The Executive Director Growth & Development, in consultation with the Portfolio Holder be authorised to complete the Grant Funding Agreements with Network Rail, East Midlands Railway, and the Canal and Rivers Trust to enable progress with these projects. 5. That progress with the Shared Service Hub be noted and work continue with Kidsgrove Town Council and other partners to develop this project. 6. Cabinet receives a further report on delivery of the Shared Service Hub at a future meeting.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To update Cabinet on progress with the delivery of Kidsgrove Town Deal and to consider the next steps in its delivery
Recommendation
That 1. Progress with Kidsgrove Town Deal is noted and that Cabinet continues to receive such updates as required. 2. Completion of the Kidsgrove Sports Centre is noted 3. Progress with the Chatterley Valley project is noted. 4. The Executive Director Growth & Development, in consultation with the Portfolio Holder is authorised to complete the Grant Funding Agreements with Network Rail, East Midlands Railway, and the Canal and Rivers Trust to enable progress with these projects. 5. That progress with the Shared Service Hub is noted and work continues with Kidsgrove Town Council and other partners to develop this project. 6. Cabinet receives a further report on delivery of the Shared Service Hub at a future meeting.
Reasons
To enhance the economic, social and community wellbeing of the Kidsgrove town Deal area.
To deliver on the County Deal as it relates to Kidsgrove Town Centre
To pursue Council Plan Objective Four - Town Centres For All as it relates to Kidsgrove.
Background
1.1As previously noted by Cabinet, in September 2019 the Government invited 100 places to develop proposals for a Town Deal as a part of the £3.6 billion Towns Fund. Within the Borough both Newcastle and Kidsgrove were invited to participate in this valuable opportunity to drive significant investment into the borough. This report focuses on the Kidsgove element of that work.
1.2The Council worked with a Town Deal Board for Kidsgrove to establish robust and sustainable projects to deliver change to the area. These were submitted to Government October 2020 in a Town Investment Plan for Kidsgrove. In March 2021, Government confirmed that the Town Investment Plan had been successful and awarded the Kidsgrove Town Deal Board £16.9 million. It was necessary then to develop the projects in more detail for delivery in the form of Business Cases for each project.
2. Issues
2.1Projects within the Kidsgrove Town Investment Plan are themed around three objectives. These are: Objective 1: To drive growth and opportunity through enhanced enterprise structure in Kidsgrove. Objective 2: To create a connected, accessible town centre which links key assets, retains the heritage and uniqueness of Kidsgrove and delivers and drives new demand and footfall. Objective 3: to maximise the leisure and recreation opportunities available in Kidsgrove, providing facilities that are supported by communities and opportunities for residents to improve their health and wellbeing. Five projects were approved for delivery within those objectives. An update on progress with these projects is set out below.
2.2Kidsgrove Sports Centre. This project was fast tracked through the Government approval system. As the project was already well developed by the Council, we were able to provide all the necessary information to allow this to happen. Town Deal funding was approved, and the first grant payment was received from Government in June 2021. This has been used to support additional investment by the Council to bring this much valued community facility back into use under the management of Kidsgrove Sports Centre CIC. This project has successfully been completed with the Sports Centre opening to the public in July 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.