(i) That the progress made with the Kidsgrove Town Deal projects be noted (ii) That the Project Adjustment Form submission to MHCLG for the new Enterprise Units, the community learning facility on Kings Academy, Canal pathway improvements and the highway / public realm improvements to The Meadows, Station Road, Market Street, The Avenue, Heathcote Street along with the public toilets upgrade and Kings Street, be approved subject to Town Deal Board approval (iii) That the risks that currently sit against the Railway Station scheme be noted (iv) That further updates be received as necessary
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
Notes the progress made with the Kidsgrove Town Deal projects Approves the Project Adjustment Form submission to MHCLG for the new Enterprise Units, the community learning facility on Kings Academy, Canal pathway improvements and the highway / public realm improvements to The Meadows, Station Road, Market Street, The Avenue, Heathcote Street along with the public toilets upgrade and Kings Street, subject to Town Deal Board approval Notes the risks that currently sit against the Railway Station scheme Agrees to receive further updates as necessary
Reasons
To update Cabinet on the progress with the various projects that are being funded or part funded through the Kidsgrove Town Deal.
Background
1.1As reported to previous Cabinet meetings, the Council has secured Town Deal Funds for the redevelopment of several key regeneration sites across Kidsgrove Town Centre and its wider area as defined in the Kidsgrove Town Deal area.
1.2The Town Investment Plan for Kidsgrove set out 5 key projects for investment. The current status of these is set out in the updates below.
1 2. Updates
2.1Kidsgrove Sports Centre This element of the Town Deal project is complete and the Sports Centre is successfully operating as a community-managed facility. 2.2 Chatterley Valley This element of the Town Deal project is complete (site servicing works including a new entrance and roundabout to the site and utility main diversion). The developer is due to commence the build out of units later this year. Marketing of the site is active. 2.3 Canal Pathways
Works by the Canal and River Trust have now commenced and are now substantially complete. An extension to the scope is currently being looked into as part of the revised scope for the Shared Service Hub (as detailed in para 2.4 below).
2.4Shared Service Hub
2.4.1 The Kidsgrove Town Deal Board (KTDB) considered various options for a revised scope of works for this funding allocation, due to the original scheme being assessed to not be deliverable. The previous scheme was to provide a facility for public sector services to deliver to the community but due to service providers withdrawing from the scheme the facility became untenable. Therefore, a revised scope was agreed by the Kidsgrove Town Deal Board in early 2025 and currently the Project Adjustment Forms are being worked up for future consideration and agreement by the Board for various substitute schemes / scopes of work prior to the submission to MHCLG accordingly.
2.4.2 The new scopes include a community learning hub on the Kings Academy site, new small-scale enterprise units on the Meadows, canal pathway and access improvements (see 2.3 above), and, highway improvements earmarked from the original consultation at The Meadows / Station Road, and Market St / The Avenue / Heathcote St along with the public toilet upgrade, along with public realm improvements by Kings Street parade.
2.4.3 Community Learning Hub
This new facility will be provided on the Kings Academy site as a learning resource for the wider community. The hub will provide adult learning opportunities and will see the relocation of the Academy’s catering hub. It will link to a satellite facility providing targeted youth services in response to an identified lack of existing facilities and higher levels of antisocial behaviour in Kidsgrove.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.