Cabinet: i. Delegated authority for the Assistant Director, Capital Investments, in consultation with the Director for People and Assistant Director Inclusion, Commissioning and Procurement, to procure Aura, our Strategic Partner under the Local Education Partnership, as the contractor to construct: · a new first school at Great Park, · a new primary school at Simonside , and · expanded/remodelled existing schools at Kingston Park and Gosforth Park subject to statutory approvals and confirmation of funding for each school being confirmed by the Director of Resources. ii. Authorised the Assistant Director Inclusion, Commissioning and Procurement in conjunction with the Assistant Director of Legal Services to complete the necessary documentation and award the contracts for the schools referred to in para 1.1 of the report. iii. Authorised the Acting Director of Place, in consultation with the Cabinet Member for Education and Skills, to conclude the detailed terms of the property transactions referred to in para 1.5 of the report. iv. Authorised the Assistant Director of Legal Services to arrange execution of the documentation arising out of required land transfers or leasehold agreements between: · the Council and Outer West Learning Trust (OWL) at Simonside · the Council and Gosforth Schools Trust at Great Park and the Council and ESFA or relevant Academy Trusts at Simonside and Great Park together with any ancillary documentation he may consider necessary, subject to settling the final terms in consultation with the other colleagues as appropriate. v. Authorised Council officers to liaise with Focus Education to develop design proposals for the expansion of Gosforth Central Middle School and approved delegated authority for the Director for People to agree implementation of the required works subject to statutory approvals.
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
School Places Expansion Programme: Next Stages Name of Cabinet Member: Councillor Norah Casey
Director presenting report: Ewen Weir, Director for People
Report Author: Deb Tyler, Service Manager, Education Mick Firth, Senior Specialist Advisor
Confidential/Not for publication: Key Decision No
Report summary: Approval is sought to progress with the delivery of a new primary school building at Simonside, a new first school building at Newcastle Great Park for Broadway East First School, an expansion of Kingston Park Primary School and remodelling to expand Gosforth Park First School into Broadway East’s existing building, through the procurement of a construction contractor using the Strategic Partnering Agreement with the Local Education Partnership (Aura). Delegations are also sought to proceed with the future award of the construction contract and associated land transactions.
Approval is also sought to progress with design work relating to the expansion of Gosforth Central Middle School with Focus Education under the existing PFI Contract.
Summary of decisions being asked: Approval is sought to procure a contractor for the construction of the new primary school at Simonside, the new first school at Newcastle Great Park and expansion of Kingston Park Primary and Gosforth Park First Schools and to progress design work to expand Gosforth Central Middle School. Appropriate delegations are also sought to proceed with property transactions at Great Park and Simonside. Cabinet report 25 February 2019 1. What is this report about?
1.1In November 2016, Cabinet approved the principles of a programme to provide additional primary and secondary school places in the outer west and north of the City. The first group of schools in the programme are:
i. New first school building/facilities at Newcastle Great Park (NGP) for relocation and expansion of Broadway East First School from 1.5FE to 3FE ii. New Simonside primary school building/facilities to relocate school on site and expand from 1.5 to 2 FE, enabling the provision of land for secondary provision iii. Expansion of Kingston Park Primary School from 2 to 3FE
In August 2018, delegated approval was given to award a contract to the Local Education Partnership (Aura) to progress design work of all three schools through RIBA stages 0-4 and since then the design team, working closely with the schools, has made good progress and planning applications are due to be submitted in March 2019.
1.2The Council is in receipt of RIBA Stage 2 reports from Aura following extensive engagement with the respective schools. For each school concept designs have been agreed enabling the design team to move onto the detailed design stages leading to planning applications and tendering the construction work. School travel plans will be revised during the next stages of the design process.
1.3Approval is therefore sought to progress with the delivery of the first group of schools through the procurement of a construction contractor using the existing Strategic Partnering Agreement with the Local Education Partnership (AURA)
1.4In addition to the three schools listed above it is now proposed to also include the expansion of Gosforth Park First School. In November 2017, Cabinet approved the relocation and expansion of Broadway East First School to the Great Park to provide the new first school in Cell A. The existing Broadway East First School is presently co-located on site with Gosforth Park First School and it is proposed that when Broadway East First moves to Great Park their building is remodelled to accommodate the expansion of Gosforth Park First School to ensure that residents of the local area continue to be provided with sufficient school places.
1.5The design and delivery of the schools comprising the first group in the School Places Expansion Programme has an estimated construction budget of £18.5m and is being funded as follows;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.