Cabinet, Monday 25 February 2019 at 5.30pm

Central Gateway Phase 2

Agreed Executive 2 papers

Cabinet agreed this item on Monday 25 February 2019. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Cabinet agreed: i. The continued development of the CG2 programme with rail partners, including the submission of further funding applications in conjunction with rail partners for further phases of the CG2 programme as set out in Appendix 1 of the report. ii. Entry into a Grant Funding Agreement with the NELEP for £3.305m and delegate agreement of detailed terms to Assistant Director Capital Investment in consultation with relevant Cabinet Portfolio holders. iii. The procurement and delivery of the enabling works packages identified in Appendix 1 of the report, utilising existing framework agreements or via competition in accordance with approved Council and Public Contract Regulations, up to a combined value of £5m and that authority be delegated to Assistant Director Capital Investment in conjunction with the Assistant Director of Inclusion, Commissioning and Procurement, to award subsequent contracts and to the Assistant Director Legal Services to complete the necessary documentation. iv. The allocation of the identified balancing resources for the proposed enabling works identified in Appendix 1 of the report.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Cabinet

APPENDIX 1 - CG2 DESCRIPTION OF WORK SCOPE ENABLING WORKS FULL PROGRAMME Forth Goods Yard Forth Goods Yard The formation of a new vehicular access road junction into Forth The construction of a new multi storey car park (MSCP) on the Forth Goods Yard. Forth Goods Yard currently has a single point of access Goods Yard site to service the station, with pedestrian access directly via a narrow arch in the viaduct that is shared with the emergency to and from the station over the retained sections of the viaduct. This access point for the adjacent Northumbria Police headquarters could also provide access to the riverside industrial/business parks building. In order to ‘unlock’ the site and realise its development and residential sites to the west of the station. potential a new access point is required.

The relocation of rail staff parking from its current location on the viaduct to the existing eastern car park, currently used by long-stay rail passengers.

The decommissioning and removal of the existing branch line under Network Change to facilitate the adaptation or removal of the viaduct, opening up Forth Goods Yard for redevelopment. West Dock West Dock The formation of a new pedestrian/cycle access point in the west wall The complete removal of all station servicing from the West Dock to of the station. This will provide a through-route within the station and create a completely cleared area for an open public concourse. enable shorter pedestrian journey times, to Stephenson Quarter in particular.

Sub-dividing the West Dock by rearranging the servicing within the covered space to create an open public concourse from Central Parkway to Neville Street, suitable for retail units and other commercial/leisure/F&B offers.

Refurbishing the Forth Street road/pedestrian tunnel.

Creating a new station taxi pick up point in the existing western short stay car park thereby moving the station taxi ranking out of Orchard Street and closing Orchard Street to vehicular traffic. The short stay car park will be relocated into the eastern concourse. ENABLING WORKS FULL PROGRAMME Eastern Concourse Eastern Concourse Relocating the short stay car park into a demarked area within the The relocation of rail staff parking from the viaduct into the eastern existing eastern long stay car park. Introducing new ticketing car park. measures including the use of automatic number plate recognition (ANPR) equipment.

Creating a new ‘drive-through’ drop off point at the front of the station Short stay and private hire taxi pick-up to be located in the eastern outside of the Centurion pub, where station taxis currently pick up. car park.

The closure of the Orchard Street tunnel to traffic. Cleaning the tunnel Providing a new access/exit ramp from Westgate Road into the and installing vehicle access prevention measures. eastern car park, and the closure of the current vehicle entry point adjacent to the Royal Station Hotel and the exit via the ‘hairpin’ ramp.

The refurbishment of the Clavering Place and Orchard Street tunnels.

The provision of a new lift and stair access point from Orchard Street up to the Eastern Concourse.

The relocation of the station refuse compactors and other service accommodation into the former ‘hairpin’ ramp. Transport and Highway Improvements Transport and Highway Improvements Upgrades to the traffic signal controllers to the Westmorland Major highway improvements to the Westmorland Road/Marlborough Road/Marlborough Crescent junction.to integrate with the wider Crescent junction. Urban Traffic Management and Control (UTMC) system, leading to smoother traffic flows in a key congestion area (improved journey time reliability) and lower CO2/NO2 emissions due to reduced queuing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendices Central GatewayReport 8.1 MB DownloadRead as text
PDF
Central Gateway Phase 2Report 107 KB Download

More from Newcastle Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Property Team Response to the Corporate Scrutiny Committee Commercial Property Development Spotlight ReviewSummary Consideration was given to a report which outlined the response to recommendations received by Cabinet in Jun... Agreed Open
21 Sep 2026 Council PlanSummary Consideration was given to the 2026-2029, which set out six priority outcomes that will drive activity to ach... Agreed Open
21 Sep 2026 Scrutiny Response to the Draft Council PlanSummary Consideration was given to a report which outlined the findings and recommendations of the Corporate Scrutiny... Agreed Open
21 Sep 2026 Council Tax SupportSummary Consideration was given to a report which set out possible options for amendments to the working age scheme a... Refused Open
21 Sep 2026 Quarter 1 Projected OutturnSummary Consideration was given to a report which set out the outturn position for Quarter One, for all council servi... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies