Local Strategic Partnership - Executive Group agreed this item on Friday 7 April 2006. Below is the council's own wording, with the papers it was decided on.
The LSP Executive Group: (a) Agreed £615,750 2006/08 NRF for the SC1 - – NRF Programme Management; (b) Agreed £610,000 2006/08 NRF for the SC2 - – Communications; (c) Agreed £772,000 2006/08 NRF for the SC3 - – Corporate Strategy; (d) Agreed £305,000 2006/08 NRF for the SC4 - – Member Services; (e) Agreed £390,000 2006/08 NRF for the SC5 - – Culture and Community; (f) Agreed £300,000 2006/08 NRF for the SC6 - – Community Fora Budgets; and (g) Agreed that all LSP Support Costs were agreed subject to the condition that a further breakdown is provided to the LSP Executive Group meeting on 2 June 2006.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
Report to Local Strategic Partnership - Executive Group
Summary
This report follows the process agreed at the LSP Executive meeting on 29 November 2005 to bring forward transitional delivery plans for the 2006/08 NRF programme.
The report provides members with 6 projects for consideration as part of the 2006/08 NRF programme – Support Costs. Attached is a summary spreadsheet which gives a project description, funding requested, and floor targets for each proposal. The sum of the proposals being brought forward is within the indicative allocation of £3,640,000. One further delivery plan for the Newham Household Panel survey will be submitted to the LSP Executive meeting in June 2006.
The following projects will all be subject to technical appraisal of delivery plans at Workstream assessment panel meetings.
Recommendations
LSP Executive Group is recommended to agree:
a) £615,750 2006/08 NRF for the LSP Support Costs – NRF Programme Management b) £610,000 2006/08 NRF for the LSP Support Costs – Communications. c) £772,000 2006/08 NRF for the LSP Support Costs – Corporate Strategy. d) £305,000 2006/08 NRF for the LSP Support Costs – Member Services. e) £390,000 2006/08 NRF for the LSP Support Costs – Culture and Community. f) £300,000 2006/08 NRF for the LSP Support Costs – Community Fora Budgets.
Originator: Sarah Reid NRF Programme Manager
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Local Strategic Partnership - Executive Group at Newham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.