Resolved
The LSP Executive Group: a) noted the report; b) considered that projects should provide regular updates; and c) agreed that a project that was not working would have its funding cut.
Local Strategic Partnership - Executive Group noted this item on Friday 7 April 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
The LSP Executive Group: a) noted the report; b) considered that projects should provide regular updates; and c) agreed that a project that was not working would have its funding cut.
Executive Group is requested to: a) consider the proposed NRF allocations set out in the attached summary spreadsheets and b) make the necessary financial approvals along with any conditions as appropriate.
Originators of report:
Phil Mayer LSP Co-ordinator Tilat Mahiudin/Sarah Reid Joint NRF Programme Manager Neighbourhood Renewal Fund Allocation (2006/08)
Introduction:
The purpose of this report is to finalise the allocation of the 2006/08 NRF programme. The LSP has been awarded £38.8m for 2006/08 and the aim of the meeting today is to allocate this funding.
Executive Group has already identified the following areas for funding over 2006/08:
(i) Employment and Enterprise Workstream (reprovision of £4.5m funding provided over 2004/06) (ii) transitional funding for existing NRF schemes considered under the Mainstreaming Review (17.7m over 2 years, 100% for 2006/07, 50% for 2007/08 and 0% thereafter) (iii) 2012 Games legacy proposals (£12 m) (iv) Newham Household Panel Survey and LSP support costs (£3.64m)
If funding to this level were to be agreed at this meeting, it would total some £37.8m which is well within the total amount available for allocation.
However, it should be borne in mind that there are still a number of delivery plans outstanding, which will need to be considered at the Executive Group meeting on 2nd June 2006, which in total should amount to approximately £2.6m.
There is also a need to allow for a potential overspend on the NRF programme of 2004/06 of up to a maximum of £2m.
However, given that a degree of overprogramming is necessary to ensure that NRF expenditure targets can be met, we can conclude that Executive Group can safely approve all of the proposals being put forward in this report.
Workstream Appraisal Process:
All proposals for NRF funding must be assessed through the workstream appraisal process.
This has involved a considerable amount of work for both individual project managers and for the Workstream Appraisal Panel which has already met on 6 occasions for a total of over 5 working days.
The details of all project proposals were set out on a standard form and appraised at the Workstream Appraisal Panel according to a range of criteria including:
(i) evidence of need (ii) evidence of impact in 2004/06 (iii) contribution to narrowing the gap in performance on key floor targets (iv) links with Borough wide strategic priorities
The Panel will only permit viable and competent proposals to be brought forward for consideration by Executive Group.
Where there are still outstanding issues, the Panel has recommended projects for funding, but has also recommended that particular conditions should be attached. These are set out in the covering report for each theme area. Executive Group can of course vary or add to these conditions as part of the approval process. Employment and Enterprise Workstream (£4.5m):
Detailed delivery plans have been prepared for what are new proposals. There is still one delivery plan outstanding. The total amount requested for this workstream is likely to marginally exceed £4.5m because of inflation not previously allowed for.
Transitional Reserve Funding (£17.7m):
Following agreement by the LSP Executive Group to the mainstreaming review, £17.7m of NRF funding was set aside for 2006/08.
The NRF Transitional Reserve Fund provides tapered funding for supporting approved NRF projects to make the transition into mainstream services.
The following factors have been used to apportion NRF Transitional Reserve Funding across the different Community Strategy themes:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Neighbourhood Renewal Fund Allocations 2006-2008Report | 19 KB | DownloadRead as text |
Follow Local Strategic Partnership - Executive Group at Newham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Mar 2007 | Neighbourhood Renewal Fund (2006/07) - Quarter 3 Spend ReportThe LSP Executive Group agreed: i) to note the report; and ii) to receive an update on employment projects. | Agreed | Open |
| 2 Mar 2007 | NRF Supporting People with Chronic Illness 2007/2008 - Mainstream PickupThe LSP Executive Group: i) agreed to use the identified £165,000 NRF Health and Wellbeing underspend to provide matc... | Agreed | Open |
| 2 Mar 2007 | Newham's Vision StatementThe LSP Executive Group agreed to adopt the following as Newham Local Strategic Partnership’s vision statement: “Newh... | Agreed | Open |
| 2 Mar 2007 | Local Government and Involvement in Health BillThe LSP Executive Group agreed to adopt the approach outlined in the report. | Agreed | Open |
| 2 Mar 2007 | Briefing on Newham's Potential Large CasinoThe LSP Executive Group: i) noted the decision that Newham is a preferred location for one of the eight Large Casinos... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.