CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Newham

Better Environment for All Workstream

Decided Executive 4 papers

Local Strategic Partnership - Executive Group decided this item on Friday 7 April 2006. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

The LSP Executive Group: a) declined to provide £1,200,000 NRF for ENVT1 - Canning Town and Custom House Regeneration Scheme at this point of time; and b) requested a further paper be submitted to the next meeting of the LSP Executive Group for further discussion and decision at that meeting
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Local Strategic Partnership - Executive Group

NEIGHBOURHOOD RENEWAL FUND TRANSITION DELIVERY PLAN FORM 2006-08

BASIC PROJECT DETAILS

NAME OF PROJECT Canning Town & Custom House Regeneration Project

PROJECT NUMBER ENVT 1 DATE OF WAP 7th February 2006 DATE OF LSP EXEC 7th April 2006 Total NRF 2006/07 £800,000 Total NRF 2007/08 £400,000 Other funds 06/07 £499,000 Other funds 07/08 £399,000

PROJECT LEAD (this person is the lead officer from the delivery agency, and will be signing the project contract and acting as the budget holder for this work) Name Gemma Allen/Stephen Jacobs

Position Administration & Finance Officer/Project Director

Organisation London Borough Of Newham – Canning Town & Custom House Regeneration Project Team

Legal Status of Statutory service provider organisation Address 20 Freemason Road, London E16 3NA

Office Phone No. 0208 430 2408

Mobile Phone No. [phone removed]

Email Address [email protected]

Fax 0208 430 5485

LAPB APPROVAL To be signed by Chair, Improving Newham’s environment/ Building an Active & Inclusive Community / LAPB / Workstream (please delete as appropriate)

Signed:

Date:

NRF Project Transition Delivery Plan Form 2006-08 1 SECTION 1 SUMMARY OF NRF INTERVENTION NB: The information provided in this document will form the basis of your contract

UPDATE ABOUT 2004/06 NRF INTERVENTION (I) Outline the key impacts achieved by this intervention in 2004/06. If any of the agreed impacts from 04/06 were not achieved then please provide details and explanations for this.

A panel of 3 developer consortia has been selected. A report recommending the consortia to develop the first housing phase (Area 3) will be considered by the Mayor and Cabinet in February 2006.

Supplementary Planning Guidance has been achieved; detailed planning will be submitted once the final developer has been selected.

The developers will produce an Environmental Improvement Assessment on a phase by phase basis.

Design Statements have been produced for both the first housing phase as well as the entire project area.

Decanting in Area 3 is over 90% complete and has begun in the second phase (Area 7).

The first housing block in Area 3 has been demolished.

Negotiations with the developer for the Town Centre Phase are continuing, a Memorandum of Understanding has been produced and Heads of Terms are being developed.

A Partnership Board has been developed and regular schedule of meetings produced.

The Project has held several successful events to engage the community and regularly attends Community Forums and Area Tenant Liaison Committees. The Project produces a quarterly newsletter for residents and has developed a Business Forum to engage local businesses.

A number of public art hoardings have been erected in the area to improve eyesores.

Several primary schools have benefited from improvements to railings and common areas.

User Groups have been developed for hotspot areas to tackle crime and anti social behaviour.

A Health Action Plan has been developed and is being implemented.

A construction training and local labour model is being developed.

(II) Who benefited from the impacts achieved in 2004/06? Provide details about the recipients as well as service providers who may have benefited from the impact

Residents of Canning Town & Custom House, local schools and businesses.

NRF Project Transition Delivery Plan Form 2006-08 2 SECTION 2 SCOPING THE PROBLEMS AND ISSUES

SCOPING THE PROBLEMS AND ISSUES (III) Why does this intervention need to continue in 2006/08? Provide details about gaps in mainstream services and local needs. Please highlight the root cause of any problems that this proposal seeks to address and list the evidence for the problems identified

As outlined in the report to Executive Group on 20th January 2006 NRF is allocated to boroughs with Super Output Areas in the top 10% most deprived in the country. Canning Town & Custom House are scored as the most deprived SOAs in the borough. NRF would assist with achieving transformational change for the area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2006-08 NRF Transition Delivery Plan post WAP finalReport 69 KB DownloadRead as text
PDF
A Better Environment for All Summary Spreadsheet HTM 13 KBReport 13 KB Copy on its way
PDF
Better Environment for All WorkstreamReport 10 KB Download
PDF
NRF 2006-09 Project Budget HTM 31 KBReport 31 KB Copy on its way

At this meeting

Whole meeting

Who was there

22 of 24 attended
DS
David StoutVice-Chair, present
KH
Kara HudsonOfficer, present
MJ
Michael JohnsonVice-Chair, present
NT
Norman TurnerOfficer, present
PN
Peter NicholsonOfficer, present
SF
Sheila FoleyMember, present
TD
Terry DigginesVice-Chair, present
PB
Councillor Paul BrickellMember, present
GC
Graeme CambageMember, present
JC
Jane ConnorOfficer, present
ED
Ellen DoranOfficer, present
JH
John HermanOfficer, present

All 24 on the meeting page

More from Newham Local Strategic Partnership - Executive Group

All decisions
MeetingDecisionOutcome
2 Mar 2007 Neighbourhood Renewal Fund (2006/07) - Quarter 3 Spend ReportThe LSP Executive Group agreed: i) to note the report; and ii) to receive an update on employment projects. Agreed Open
2 Mar 2007 NRF Supporting People with Chronic Illness 2007/2008 - Mainstream PickupThe LSP Executive Group: i) agreed to use the identified £165,000 NRF Health and Wellbeing underspend to provide matc... Agreed Open
2 Mar 2007 Newham's Vision StatementThe LSP Executive Group agreed to adopt the following as Newham Local Strategic Partnership’s vision statement: “Newh... Agreed Open
2 Mar 2007 Local Government and Involvement in Health BillThe LSP Executive Group agreed to adopt the approach outlined in the report. Agreed Open