Decision The Development Control Committee agreed the reasons for approval as outlined within the report and granted planning permission subject to the following conditions:- 1. The development to which this permission relates must be commenced not later than the expiration of THREE YEARS from the date of this permission. Reasons: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990. 2. All works are to be completed in accordance with drawing numbers:- Location Plan - AS163_EX_01 Existing and Proposed Plan - AS163_PL_01 Proposed Playground Plan - AS163_PL_02 ... view the full minutes text for item 13.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
a) agree the reasons for approval as outlined in section 9.1 of this report;
b) grant planning permission subject to the following conditions:-
1. The development to which this permission relates must be commenced not later than the expiration of THREE YEARS from the date of this permission.
Reasons: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990.
2. All works are to be completed in accordance with drawing numbers:-
Location Plan - AS163_EX_01 Existing and Proposed Plan - AS163_PL_01 Proposed Playground Plan - AS163_PL_02 Proposed Playground Colour Plan- AS163_PL_03 Playground Sections - AS163_PL_04 Playground Elevations - AS163_PL_05 Proposed Playground Planting Plan - AS163_PL_06
Prepared by Adams & Sutherland and dated as received by the Council 09/01/2008. No further drawings apply, unless otherwise approved in writing by the Local Planning Authority. Reasons: To ensure that the development is undertaken in accordance with the approved drawing(s), and to protect the local amenity with regard to Policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001 saved from the 27th of September 2007 in accordance with the direction from the Secretary of State), and Policy 4B.1 of the adopted London Plan, February 2004. The development is acceptable on the basis of the particulars contained within the application and this condition seeks to ensure the development is undertaken in strict accordance with those details as approved.
3. Development shall not begin until a scheme to deal with contamination of the site has been submitted to and approved in writing by the local planning authority. The said scheme shall include an investigation and assessment to identify the extent of contamination, a risk assessment regarding the future land use, and a statement regarding any remedial works to be carried out to avoid risk to the public when the site is developed. Use of the development shall not commence unless and until the measures approved in the scheme have been implemented and completed. The measures approved in the scheme shall been implemented and completed before use of the development shall commence. As soon as reasonably practicable, and before the occupation of any remediated area of the site, a validation report shall be submitted and approved by the Local Planning Authority in writing, stating what works were undertaken and that the works were completed in accordance with the approved scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.