Decision The Development Control Committee agreed: (i) that the revised and simplified Planning Memorandum be put in place in place, as outlined in Appendix 1; and (ii) recommended to the CTRL High Level Forum that the Planning Forum is closed.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
a) agree that a revised and simplified Planning Memorandum be put in place in place, as outlined in Appendix 1; and
b) recommends to the CTRL High Level Forum that the Planning forum is closed.
2. SYNOPSIS
2.1It is recommended that now construction of the high speed rail link is complete, a revised, simplified Planning Memorandum is agreed, and the Planning Forum is no longer required.
3. SITE AND SURROUNDINGS
3.1The CTRL route runs underground from east to west across Newham, from Barrington Playing Fields in Manor Park to the Stratford City site. Within Newham there is a combined international and domestic station at Stratford International and are ventilation shafts along the route at Barrington Road and Woodgrange Road.
4. THE PROPOSAL
4.1Now construction of the high speed rail link is complete, a revised, simplified Planning Memorandum and the closure of the Planning Forum are proposed.
5. RELEVANT HISTORY
5.1During the construction of the rail link, Local Authorities that had signed up to the Planning Memorandum as ’qualifying authorities’ were able to exercise the powers in Schedule 6 of the CTRL Act. This gave the authorities, including this authority, the right to receive applications and exercise controls over a wide range of CTRL construction works and arrangements. 6. CONSULTATIONS & RESPONSES
6.1Adjoining Occupiers
N/A
6.3Statutory and Non Statutory Consultees
All other ‘qualifying’ local authorities will be responding directly to CTRL.
6.4Land Panel
This proposal has not been to Land Panel.
6.5Internal Consultees
Environmental Health: Supports the proposal
7. PLANNING POLICIES AND GUIDANCE
7.1London Borough of Newham UDP (adopted June 2001 – Saved from 27th Sept 2007 by direction from the Secretary of State):
Policy T6: Channel Tunnel Rail Link and International and Domestic Station at Stratford
7.2London Plan (adopted Feb 2004):
Policy 3C.5: London’s International, National and Regional Transport Links Policy 3C.8: Strategic Rail Networks
8. ASSESSMENT
8.1Section 1 of the Channel Tunnel Rail Link opened in 2003. CTRL, now renamed High Speed 1 (HS1), has now started operations, with the first train leaving from St Pancras in November 2007.
8.2During the construction of the rail link, Local Authorities such as Newham that had signed up to the Planning Memorandum as ‘qualifying authorities’ were able to exercise the powers in Schedule 6 of the CTRL Act. This gave the authorities, including this authority, the right to receive applications and exercise controls over a wide range of CTRL construction works and arrangements.
8.3The Planning Memorandum set out the standards that both the promoter and local authorities were to follow in requesting and determining planning applications. The Channel Tunnel Rail Link Act remains in force following completion of the railway. This special planning regime will continue to be the process by which HS1 gains approval for future development - albeit such developments are likely to be infrequent, small scale and of local rather than of cross boundary or route wide interest. The Planning Forum considers that a simplified Planning Memorandum which accompanies this report is now appropriate (see Appendix 1).
8.4The Planning Forum was established by the High Level Forum as the primary focus of officer liaison to ensure the successful operation of common procedures and interpretation of the Act, to facilitate the expedited handling of applications, and to resolve issues of cross boundary or route wide concern. The Planning Forum considers that its continued existence post HS1 operation is no longer required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.