Trad Scaffolding Co Ltd, Knights Road, London E16

Agreed Planning 1 paper

Development Control Committee agreed this item on Wednesday 12 March 2008. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Decision The Development Control Committee agreed the reasons for approval as outlined in this report, and granted planning permission subject to the following conditions: 1. The development hereby permitted is restricted to a time frame of one year expiring on the 1st April 2009 . After this date, the use shall cease, all buildings and structures shall be removed and the land reinstated to the satisfaction of the Local Planning Authority. Reasons: To prevent continued use of the site as a concrete batching plant from prejudicing the regeneration objectives of the area in accordance with the planning policy context set out in the Council’s Unitary Development Plan (adopted June 2001 and saved from the 27th September 2007 following the directive of the Secretary of State), and the London Plan adopted February 2004. 2. All works are to be completed in accordance with drawing numbers S1/02/06/07; 0606201 and SLV/204a prepared by Tarmac Limited and received 12.6.2007. No further drawings apply, unless otherwise approved in writing by the Local Planning Authority. Reasons: To ensure that the development is undertaken in accordance with the approved drawings, and to protect the local amenity with regard to Policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001 and saved from the 27th September 2007 following the directive of the Secretary of State), and Policy 4B.1 of the London Plan adopted February 2004. The development is acceptable on the basis of the particulars contained within the application and this condition seeks to ensure the development is undertaken in strict accordance with those details as approved. 3. No development shall take place until an Environmental Code of Practice has been submitted to and approved by the Local Planning Authority. The code shall cover all aspects of site preparation, construction and operation and include details of demolition, clearance and ground works, and the development shall not be constructed and operated other than in accordance with the approved environmental code. Reason: To ensure that the development does not adversely impact on the amenity of adjoining occupiers and the local environment in accordance with policy EQ45 of the Unitary Development Plan (adopted June 2001 and saved from the 27th September 2007 following the directive of the Secretary of State), and Policy 4A.14 of the London Plan adopted February 2004. 4. Wheel washing equipment and facility shall be used at all times to prevent the carriage of mud and other materials onto adjoining public, details of which shall be submitted to and approved in writing by the Local Planning Authority. The wheel washing facility shall be installed on the site in accordance with the approved details ... view the full minutes text for item 9.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Development Control Committee

Recommendations

1.1The Committee is asked to:

a) agree the reasons for approval as outlined in this report, and

b) grant planning permission subject to the following conditions:

1. The development hereby permitted is restricted to a time frame of one year expiring on the 1st April 2009. After this date, the use shall cease, all buildings and structures shall be removed and the land reinstated to the satisfaction of the Local Planning Authority.

Reasons: To prevent continued use of the site as a concrete batching plant from prejudicing the regeneration objectives of the area in accordance with the planning policy context set out in the Council’s Unitary Development Plan (adopted June 2001 and saved from the 27th September 2007 following the directive of the Secretary of State), and the London Plan adopted February 2004.

2. All works are to be completed in accordance with drawing numbers S1/02/06/07; 0606201 and SLV/204a prepared by Tarmac Limited and received 12.6.2007. No further drawings apply, unless otherwise approved in writing by the Local Planning Authority.

Reasons: To ensure that the development is undertaken in accordance with the approved drawings, and to protect the local amenity with regard to Policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001 and saved from the 27th September 2007 following the directive of the Secretary of State), and Policy 4B.1 of the London Plan adopted February 2004. The development is acceptable on the basis of the particulars contained within the application and this condition seeks to ensure the development is undertaken in strict accordance with those details as approved.

3. No development shall take place until an Environmental Code of Practice has been submitted to and approved by the Local Planning Authority. The code shall cover all aspects of site preparation, construction and operation and include details of demolition, clearance and ground works, and the development shall not be constructed and operated other than in accordance with the approved environmental code.

Reason: To ensure that the development does not adversely impact on the amenity of adjoining occupiers and the local environment in accordance with policy EQ45 of the Unitary Development Plan (adopted June 2001 and saved from the 27th September 2007 following the directive of the Secretary of State), and Policy 4A.14 of the London Plan adopted February 2004.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Trad Scaffolding Co Ltd, Knights Road, London E16Report 5.9 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
RM
Councillor Ron ManleyChair, present
MC
Councillor Marie CollierMember, present
PH
Councillor Patricia HollandMember, present
MJ
Councillor Maureen JonesMember, present
KK
Councillor Khalil Kazi OBEMember, present
RA
Councillor Riaz Ahmed MirzaMember, present
PM
Councillor Patrick MurphyMember, present
LS
Councillor Lakmini ShahMember, present
AS
Councillor Amarjit SinghMember, present

More from Newham Development Control Committee

All decisions
MeetingDecisionOutcome
3 Mar 2010 370 Romford Road, Forest Gate, London E7 8BSDecision The Committee agreed the reasons for approval as outlined in the report and granted planning permission subj... Agreed Open
3 Mar 2010 120 High Street, E6Decision The Committee agreed to defer consideration to a later meeting. Agreed Open
3 Mar 2010 Dersingham Infant School, Lawrence Avenue, Manor Park E12Decision The Committee agreed the reasons for approval as outlined in the report and granted outline planning permiss... Agreed Open
3 Mar 2010 Eastlea Community Comprehensive School, Exing Road E16Decision The Committee agreed the reasons for approval as outlined in the report and granted full planning permission... Agreed Open