Cabinet, Tuesday 3 November 2020

Brickyard Development, East Ham, by Populo - Increased Investment

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 3 November 2020. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

For the reasons set out in the report, Cabinet RESOLVED to AGREE To approve additional development funding of £200,000 and additional investment funding of £4m to Populo Living for the Brickyard scheme on the former car park located at Barking Road/St. John’s Road E6 1NN. This will increase the Newham equity and loan funding for the development phase to £35.5m and the Investment phase loan to £33m, supplemented by £2.8m GLA grant. Alternatives considered The alternatives considered are:- · No further funding is provided · Populo Living could seek a further planning variation · Populo Living could seek an alternative gym operator during the development period Not providing further funding would leave Populo needing to find an alternative user willing to fully fund the shortfall. No such user has been identified, and the uncertainty of doing so would be an ongoing risk to the project. Seeking a further planning approval (for example to accommodate additional residential in lieu of the gym) would delay the scheme considerably and would also be likely to require additional funding. Seeking a use for the space no longer required by the gym operator is a more practical solution. Finding an alternative operator during the development period may be possible, although the gym sector as a whole faces similar issues due to Covid and there is no certainty that another operator would currently be interested, although the situation may change as the scheme approaches completion in 2023. For the above reasons, and because the scheme remains viable for Populo Living, the report recommends provision of additional funding.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
St Johns Road Car Park Site Location PlanAppendix 1 441 KB Copy on its way
PDF
Brickyard Development, East Ham, by Populo: Increased InvestmentReport 174 KB Copy on its way

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies