Resolved
For the reasons set out in the report and its appendices Cabinet RESOLVED to AGREE: i) The award of contract to Olli Construction Ltd in the sum of £1,498,113million for the refurbishment of Beckton Community Centre to start in October 2023. Alternatives Considered 1) Do Nothing - Not recommended. The Centre would fall into disrepair, cost more to refurbish in the future and ultimately may need to close for a longer period until funding is secured and the works are completed. 2) Different procurement route/cost and quality split - Not recommended. The procurement route was discussed with the Strategic Procurement Team who recommended the proposed procurement route to achieve competitive bids and best value.
Word for word from the decision Newham published for this meeting.
Source: mgov.newham.gov.uk