Small Sites Options Appraisal and Modular- Next Steps

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 6 July 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

For the reasons set out in the report and its appendices Cabinet RESOLVED to AGREE: i) A budget of £200,000 to enable the appointment of an Asset Strategy consultant to undertake the option appraisals and other ancillary works on the small sites; ii) A budget of £1,000,000 in order to undertake surveys and other ancillary works in order to proceed with designing Vicarage Lane; Berwick Road and Chargeable Lane or other suitable sites, to RIBA stage 3, (pre submission of planning), with the intent of delivering through modular construction where this is more effective than adopting a traditional approach; iii) To delegate authority to the Corporate Director of Resources, in consultation with the Cabinet member for Finance and Resources to approve any necessary procurement process and to award a contract or contracts for the services as per (ii) above; and iv) To note that a further report will be brought to Cabinet in December 2023 to submit planning for suitable modular sites that are proposed to be taken forward Alternatives Considered 1) Not to proceed with this options appraisal would potentially leave 375 Council owned sites being underutilised for several outcomes, including redevelopment and for community use. 2) The Council currently do not have the internal resource or expertise to carry out the options appraisal process. Given it’s likely to only take six months and needs specialist asset strategy knowledge it is seen more time and cost effective to hire an external consultant to carry out the initial options appraisal. 3) The three sites identified suitable for modular housing could be left as is but this would result in a loss of 14 additional homes and a loss of the opportunity for the Council to properly explore a new method of housing delivery.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet, 7 pages

Executive summary

1.1This report proposes that option appraisals are undertaken on a range of Council-owned small sites. The small sites identified are mostly garage sites or small parcels of in-fill land. The option appraisals will enable the Council to make the best possible decisions as to how to use the sites to

1 deliver Building a Fairer Newham objectives, such as for housing and community uses.

1.2Work on small sites to date has also identified the opportunity for the Council to utilise modular construction where this will enable more affordable or specialist homes to be constructed more quickly and efficiently than by using traditional methods. Therefore, it is proposed to take up to three small sites up to planning in the development process to explore using modular construction to enable the Council to investigate using modern methods of construction, with both estimated cost and time savings.

2. Recommendations For the reasons set out in the report and its appendices, Cabinet is recommended:

2.1To agree a budget of £200,000 to enable the appointment of an Asset Strategy consultant to undertake the option appraisals and other ancillary works on the small sites. 2.2 To agree a budget of £1,000,000 in order to undertake surveys and other ancillary works in order to proceed with designing Vicarage Lane; Berwick Road and Chargeable Lane or other suitable sites, to RIBA stage 3, (pre submission of planning), with the intent of delivering through modular construction where this is more effective than adopting a traditional approach. 2.3 Delegate authority to the Corporate Director of Resources, in consultation with the Cabinet member for Finance and Resources to approve any necessary procurement process and to award a contract or contracts for the services as per 3.2. 2.4 Note that a further report will be brought to Cabinet in December 2023 to submit planning for suitable modular sites that are proposed to be taken forward.

3. Background 3.1 Newham Council is taking proactive steps to continue to provide good quality affordable housing. The Affordable Homes for Newham programme has 958 homes under contract and on site and Populo have contracted a further 317.

3.2In the next four years the Council has an ambitious yet achievable target of providing at least 1,500 more affordable new homes, through its development and acquisitions programmes and by enabling and encouraging other providers to develop more affordable homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Small Sites Options Appraisal and Modular- Next StepsReport 7 pages DownloadRead as text

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies