Item8
Resolved
For the reasons set out in the report and its appendices Cabinet RESOLVED to AGREE: i) To approve additional Development stage loan funding of £3.9m along with additional Investment stage loan funding of £9.9m to Populo Living for the Plaistow Hub scheme. Noting that this would increase the Newham equity, market loan funding facility by £9.9m to a total of £93.7m. Alternatives Considered 1. The alternative of not providing additional development and investment stage funding would leave Populo unable to complete the project and unable to repay the Council its investment to date. Since the investment scheme remains viable for both Populo Living and LBN, this report recommends provision of additional funding required to complete the project.
Word for word from the decision Newham published for this meeting.