AI summaryNewham Strategic Development Committee approves Section 73 application to vary plans and materials conditions at 36 New Barn Street, Plaistow, a 32-unit 100% affordable housing scheme, subject to a s106 legal agreement.
Written from the decision and the officer reportPDF Pro
OutcomeAgreed
Moneys106 contributions including £34,200 zero carbonPlus monitoring fees, permit-free admin and construction contribution
What happens nexts106 legal agreement to be completedWithin six months, otherwise the Director can refuse
Who it affects32 affordable homes at New Barn Street100% London Affordable Rent, 11 one-bed, 8 two-bed, 11 three-bed, 2 four-bed
What was decided
The Committee agreed the reasons for approval as set out in the officer report and delegated authority to the Director of Place Making to grant planning permission subject to completion of a s106 legal agreement and the conditions in Appendix 1. Report P2, P4
If the s106 legal agreement is not completed within six months, the Director of Place Making is delegated power to refuse planning permission. Report P5
The Section 73 application varies Condition 2 (approved plans and drawings) and Condition 9 (materials requiring subsequent approval) of the original 2022 permission, but does not change the number of units or building heights. Report P57, P62
Why
The amendments are described as minor and acceptable, enabling the scheme to meet PassivHaus standards, deliver sustainability, enhance thermal comfort, support net-zero energy and reduce the carbon footprint. Report P204
Officers considered the changes would, on balance, safeguard the character and appearance of the local environment and neighbour amenity, with no consultation objections received. Report P205, P85, P86
What happens next
A s106 legal agreement must be completed within six months covering affordable housing, zero carbon, transport, local labour, apprenticeships and a £15,000 construction contribution. Report P5, P13, P14, P15, P16
If the s106 is not completed in that time, the Director of Place Making can refuse planning permission. Report P5
The money
£34,200 Zero Carbon Contribution at £95 per tonne for 30 years, payable on completion of the s106 agreement Report P14
£7,500 S106 monitoring and implementation fee, payable on completion Report P12
£2,000.00 Car parking permit-free agreement administration and monitoring fee Report P15
£5,000 Travel Plan monitoring fee (indexed by RPI), payable on completion Report P15
£15,000 Construction Contribution, payable on completion of the s106 agreement Report P16
£14,312,245.86 Construction contract value, used to calculate apprenticeship target of 3 Newham resident apprentices Report P16
£50 Driving credit per residential unit for a 3 year free Car Club membership Report P15
Options considered
Chosen: Grant planning permission subject to s106 legal agreement and conditions. Amendments considered minor and acceptable; would help scheme meet PassivHaus standard and improve design from as-built Report P2, P145, P146, P204
Rejected: Refuse the application. Officers concluded the changes safeguard character and amenity and there were no consultation objections Report P205, P85, P86
Implications
Equalities: Officers concluded there are no adverse equalities issues for this application. Report P25
Legal: Permission is granted under Section 73 of the Town and Country Planning Act, varying the original 2022 consent; the s106 must be completed within six months. Report P57
Climate: The application supports the scheme achieving PassivHaus Standard, with 42% renewable energy from air source heat pumps and PV panels, plus a £34,200 zero carbon contribution. Report P46, P14, P180, P181
Risk: Site is in Flood Zone 3; flood mitigation must follow the original Flood Risk Assessment and be reflected in the conditions. Report P54, P189, P195, P285
Other: The original 2022 permission predates the mandatory Biodiversity Net Gain date of 12 February 2024, so the 10% BNG requirement does not apply to this S73 application. Report P161, P162
Who and where
Future residents of the 32 London Affordable Rent homes (11 one-bed, 8 two-bed, 11 three-bed, 2 four-bed) Report P13, P36, P38, P39, P40
Neighbouring properties on and around New Barn Street, including Ravenscourt Primary School and occupiers of Stubbs Point Report P53, P83
The applicant (Kind & Co Builders Ltd) and Affordable Homes for Newham Report P33, P148
Newham residents seeking construction-phase jobs, with a target of 35% local labour and 3 apprenticeships Report P16
Timeline
22 April 2022: Original planning permission 21/03040/LA3 granted for 32 residential units Report P51, P72
22 January 2026: 485 consultation letters sent to neighbouring properties Report P83
3 February 2026: Site notice erected, expiring 25 February 2026 Report P80
11 February 2026: Press notice advertised in the Newham Recorder, expiring 5 March 2026 Report P81
5 March 2026: Public consultation period expired with 0 responses received Report P48, P83
10 March 2026: Application previously presented to Strategic Development Committee and deferred to seek attendance of the applicant Report P64
21 April 2026: Strategic Development Committee resolves to approve, subject to s106 within six months Report P5
Plain English for the jargon
Section 73 application: Application to vary or remove conditions attached to an existing planning permission
s106 legal agreement: A legal agreement under section 106 of the Town and Country Planning Act 1990 used to secure planning obligations such as affordable housing or financial contributions
PassivHaus Standard: A high standard of sustainable design delivering enhanced indoor comfort, improved air quality and high energy efficiency
PTAL: Public Transport Accessibility Level, a score from 0 to 6b indicating access to public transport; the site has a rating of 3
Flood Zone 3: Area assessed as having a high probability of flooding
London Affordable Rent: A tenure set at roughly a third of market rents, targeted at lower-income households in London
BNG: Biodiversity Net Gain, a requirement for developments to deliver at least a 10% increase in biodiversity value compared with the pre-development site
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Decision Strategic Development Committee RESOLVED to AGREE 1. the reasons for approval as set out in the report; 2. delegated authority to the Director of Place Making to grant planning permission subject to the completion of a legal agreement under s106 of the Town and Country Planning Act 1990 (as amended) and all enabling powers based on the Heads of Terms identified at Appendix 2 of the report and the Conditions listed in Appendix 1 of the report; and 3. if within six months of this resolution the legal agreement has not been completed, the Director of Place Making is delegated power to refuse planning permission.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
The Strategic Development Committee is asked to resolve to:
1. agree the reasons for approval as set out in this report;
London Borough of Newham [36 New Barn Street]
2. delegate authority to the Director of Place Making to grant planning permission subject to the completion of a legal agreement under s106 of the Town and Country Planning Act 1990 (as amended) and all enabling powers based on the Heads of Terms identified at Appendix 2 of this report and the Conditions listed in Appendix 1 of this report and summarised below; and
3. if within six months of this resolution the legal agreement has not been completed, the Director of Place Making is delegated power to refuse planning permission.
Conditions – Summary
A summary of the proposed condition is set out below. Please refer to Appendix 1 for the proposed conditions in full.
1. Statutory Time Limit 2. Approved Drawings and Documents 3. Demolition Method Statement 4. Demolition and Construction Logistics Plan 5. Construction Method Statement 6. Surface Water Drainage Details 7. Contamination 8. Secure by Design 9. Materials Requiring Subsequent Approval 10. Window and Door Details 11. Hard and Soft Landscaping 12. Piling Method Statement 13. Operational Management Plan – Resident Amenity and Play Space 14. Noise 15. Cycle Parking 16. Carbon Emissions 17. Parking Design and Management Plan 18. Delivery and Servicing Plan 19. Travel Plan 20. Fire Statement 21. Biodiversity 22. Building Regulations M4(2) and M4(3) 23. Overheating 24. Rainwater Pipes, Flues and Grilles 26. Flood Risk 27. Water Usage 28. Electrical Vehicle Charging Points 29. Access to Cycle Stores 30. Obscure Glazed Windows
S106 –Heads of Terms
London Borough of Newham [36 New Barn Street]
The Section 106 Legal Agreement Heads of Terms agreed between the Council and the Applicant are set out below:
Administrative 1. Payment of the Council’s reasonable professional and legal costs, whether or not the agreement completes. 2. Payment of the Council’s reasonable fees in monitoring and implementing the S106 obligations payable on completion of the agreement. (£7,500) 3. Indexation of payments from the date of committee resolution to the date of actual payment as established for each contribution or fee as BCIS-All in Tender Price Index (BCIS); or Retail Price Index (RPI). 4. Late interest payment if monies are not paid in accordance with the deed.
Housing 5. Provision of 11x1 bed units (A0.05, A1.04, A1.06, A2.04, A2.06, B0.01, B0.02, B1.02, B2.02, B3.02, B4.02) 8x2 bed units (B1.03, B1.04, B2.03, B2.04, B3.03, B3.04, B4.04, B4.04), 11x3 bed units (A0.01, A0.02, A0.03, A0.04, A1.05, A2.03, A2.05, B1.01, B2.01, B3.01, B4.01) and 2x4 bed units (A2.01, A2.02) at London Affordable Rent.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
1 Stansfeld Road. Beckton, London E6 5LUDecision The Strategic Development Committee RESOLVED to DEFER the application to a future meeting. The reasons for d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.