London Borough of Newham
Strategic Development Committee, Tuesday 28 April 2026

1 Stansfeld Road. Beckton, London E6 5LU

Deferred Committee 1 paper

AI summaryNewham Strategic Development Committee defers 79-home Beckton scheme to improve viability, affordable housing offer, design and housing mix.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredto a future meeting of the Strategic Development Committee
Money£150,000 affordable housing contribution proposedplus £474,450 local employment contribution and other S106 sums
What happens nextReturn to a future meetingto address developer profit, grants, affordable housing, DRP design and housing mix
Who it affects1 Stansfeld Road, Beckton E6 5LUsite of proposed 79 private homes in four blocks

What was decided

The Strategic Development Committee resolved to defer the application rather than approve it, as the officer report had recommended. Report P1, P2

Reasons for deferral were: to seek improvements to developer profit, pursue grants and on-site affordable housing, clarify design through further Design Review Panel engagement, and review housing mix to improve viability.

Why

Officers had recommended approval, subject to a Section 106 legal agreement, on a 100% private scheme with a £150,000 off-site affordable housing contribution, an early-stage and late-stage viability review, and various planning conditions. Report P2, P3, P25, P26, P27

An independent viability review by Quintic Advisory found the scheme generated a residual land value of £107,626, a £182,374 deficit against the £290,000 benchmark, and the applicant's consultant identified a £4.917m deficit, leaving no surplus for on-site affordable housing. Report P268

Seven objections were received from adjoining occupiers, raising concerns over building height and massing, loss of light and privacy, traffic, parking, water and drainage, impacts on Jake Russell Walk, local amenity, HMO risk, bird nuisance and who the housing would serve. Report P80, P120, P121

What happens next

The application will be brought back to a future meeting of the Strategic Development Committee after further work on viability, design, housing mix and affordable housing.

If the application is later approved, the Director of Place Making is delegated authority to grant permission subject to completing the S106 legal agreement; if the agreement is not completed within six months, the Director may refuse permission. Report P3, P5

The money

  • £150,000 Off-site affordable housing contribution (+BCIS), payable on implementation Report P25
  • £474,450 Construction jobs contribution to Newham residents (+RPI), payable on implementation Report P29
  • £50,000 Contribution towards Royal Albert DLR Station improvements (+BCIS) Report P33
  • £5,265 Travel Plan Monitoring Fee (+RPI) Report P34
  • £5,265 Travel Plan Measures Contribution (+RPI) Report P35
  • £2,000 Car-free development administration cost Report P38
  • £12,500 S106 monitoring and implementation fee, payable on completion of the deed Report P22
  • £100,000 Design monitoring contribution if architects are not retained Report P46
  • £45,121 Carbon offset contribution at £60 per tonne over 30 years (+BCIS) Report P42
  • £26,804,460 Build cost used to calculate the construction jobs yield Report P259

Options considered

  • Rejected: Approve the application subject to a Section 106 legal agreement and conditions (officer recommendation). Committee chose to defer to seek improvements to developer profit, affordable housing, design and housing mix Report P1, P2
  • Chosen: Defer the application to a future meeting. To allow improvement on developer profit, seeking grants and on-site affordable housing, DRP design clarification, and review of housing mix to improve viability

Implications

  • Financial: The scheme is shown by an independent viability review to be unviable for on-site affordable housing, with a £182,374 deficit against the £290,000 benchmark land value, and the applicant's consultant reports a £4.917m deficit. Report P268
  • Legal: Approval would have been subject to a Section 106 legal agreement with an early-stage viability review if not substantially implemented within two years, and a late-stage review at 75% of units sold, with 80% of any surplus to the Council. Report P26, P27
  • Equalities: Officers concluded there are no adverse equalities issues and the provisions of the Human Rights Act 1998 have been taken into account. Report P50, P51, P52, P53, P54
  • Climate: The scheme proposes 82% on-site renewable energy through air source heat pumps and solar panels, a 949sqm green roof, an Urban Greening Factor of 0.7, and a £45,121 carbon offset contribution to reach zero carbon. Report P42, P78
  • Risk: London City Airport requested a Bird Hazard Management Plan and a glint and glare condition on photovoltaic cells; no statutory consultees raised objections subject to conditions. Report P149, P150, P151

Who and where

  • Adjoining residents on Richard House Drive, who raised seven objections on height, daylight, privacy, traffic, parking, drainage and amenity Report P80, P118, P120
  • Future occupants of the proposed 79 private homes, including 8 wheelchair user units Report P64, P72, P92, P94
  • Newham residents seeking construction-phase employment, through a 35% local labour target and £474,450 contribution Report P29, P30, P62
  • Royal Albert DLR Station users, through a £50,000 S106 improvement contribution Report P33, P147
  • Adjacent allotments and Beckton District Park South, which adjoin the site Report P86

Timeline

  • 30 October 2025: 287 consultation letters sent to neighbouring properties Report P111
  • 5 November 2025: Site notice erected and press notice advertised in the Newham Recorder, both expiring 26 November 2025 Report P108, P109
  • 20 November 2025: Public consultation period expired Report P111
  • 26 November 2025: Expiry of consultation period as stated in the fact sheet, with 7 objections and 0 letters of support received Report P80, P111
  • 28 April 2026: Strategic Development Committee meeting at which the application was deferred

Plain English for the jargon

  • Section 106 (S106) legal agreement: A planning obligation under section 106 of the Town and Country Planning Act 1990 used to secure financial contributions and other commitments from a developer.
  • Design Review Panel (DRP): An independent panel of design experts that reviews the design quality of major planning applications, in this case advising the Council on the Beckton scheme.
  • Viability Tested Route: A process under London Plan Policy H5 where a scheme that does not meet the affordable housing threshold must be supported by a financial viability assessment.
  • PTAL: Public Transport Accessibility Level, a 1 to 6 scale (with 6 being best) measuring access to public transport; the site is rated 3.
  • CIL: Community Infrastructure Levy, a charge that local authorities can collect from new development to fund infrastructure.
  • Use Class C3: The planning use class for residential dwellings, as distinct from houses in multiple occupation (C4) or other uses.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

Decision The Strategic Development Committee RESOLVED to DEFER the application to a future meeting. The reasons for deferral being: To allow an opportunity for improvement on the level of developer profit, seeking grants and onsite affordable housing, Clarification on design through engagement with DRP and a review of housing mix to improve viability
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Strategic Development Committee

Recommendations

The Strategic Development Committee is asked to resolve to:

1. agree the reasons for approval as set out in this report;

2. delegate authority to the Director of Place Making to grant planning permission subject to the completion of a legal agreement under s106 of the Town and Country Planning Act 1990 (as amended) and all enabling powers, based on the Heads of Terms identified at Appendix 2 of this report and the Conditions listed in Appendix 1 of this report and summarised below; and

London Borough of Newham 1 Stansfeld Road

3. if within six months of the resolution the legal agreement has not been completed, the Director of Place Making is delegated power to refuse planning permission.

Conditions – Summary

A summary of the proposed condition is set out below. Please refer to Appendix 1 for the proposed conditions in full.

1. Statutory Time Limit 2. Approved Plans and Documents

Pre-commencement conditions

3. Construction / Demolition Environmental Management Plan 4. Demolition and Construction Logistic Plan 5. Land Contamination 6. Archaeology 7. Piling Method Statement 8. Unexploded Ordnance

Prior to above ground works conditions

9. Surface Water Drainage Strategy 10. Bird Hazard Management Plan 11. Biodiversity Net Gain 12. Materials and Detailed Design 13. Detailed Drawings 14. Landscape Design 15. Secured by Design 16. Details of Accessible and Adaptable Units 17. Cycle Parking

Prior to first occupation / use conditions

18. Fixed Plant Machinery 19. Environmental Noise – Residential 20. Travel Plan 21. Blue Badge Parking Management Plan 22. Delivery and Servicing Management Plan 23. Photovoltaic cells (Glint & Glare) 24. Car Park Management Plan

Compliance conditions

25. Items Fixed to the Façade 26. On site Generation 27. Air Quality, Ultra Low NOx boiler 28. Highways

London Borough of Newham 1 Stansfeld Road

S106 – Heads of Terms

The Section 106 Legal Agreement Heads of Terms agreed between the Council and the Applicant are set out below:

Administrative

1. Payment of the Council’s reasonable professional and legal costs, whether or not the agreement completes.

2. Payment of the Council’s reasonable fees in monitoring and implementing the S106, including the need to appoint third party/independent advisors in relation to such, payable at £12,500 (payable on completion of the deed).

3. Indexing – All contributions and payments to be index linked from the date of the resolution to grant planning permission to the date on which payment is made, using BCIS or RPI index as indicated below.

Affordable Housing

4. £150,000 offsite affordable housing contribution (+BCIS), payable on implementation of the development.

5. The Applicant shall undertake an Early-Stage Viability Review if substantial implementation is not reached within two years of grant of planning consent. If the review identifies an improvement in viability, additional affordable housing units shall be delivered on-site. Where the surplus is insufficient to support additional on-site units, the Applicant shall pay the surplus to the Council as a financial contribution with 100% of the surplus allocated to the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1 Stansfeld Road. Beckton, London E6 5LUReport 1.5 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 12 attended
RT
Councillor Rachel TrippChair, present
JB
Councillor James BecklesMember, absent
AG
Councillor Alan GriffithsMember, present
BY
Councillor Blossom YoungMember, present
SM
Councillor Shaban MohammedMember, absent
MS
Councillor Madeleine Sarley PontinMember, present
TP
Councillor Terence PaulMember, present
JM
Councillor John MorrisVice-Chair, present
MM
Councillor Mehmood MirzaMember, absent
JC
Jane CustanceOfficer, expected
JB
James BoltOfficer, expected
SF
Shirley FortuneSecretary, expected

On this subject at Newham

Search all
  1. 1 Stansfeld Road. Beckton, London E6 5LUThis decision
  2. Radiate Festival Beckton District Park South, Stansfeld Road, Beckton, E6 5LTRefused
  3. Will Thorne Pavillion, Stansfeld Road,Beckton, London E6 5LTAgreed
  4. The Stables Stansfeld Road, Beckton London E16 2ALAgreed

More from Newham Strategic Development Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 Sunborn London Yacht, Western Gateway, Canning Town, London E16 1AADecision The Strategic Development Committee NOTED the Officer Update Report and RESOLVED to AGREE: 1. agree the reas... Noted Open
28 Apr 2026 Land At 10 To 11 Brunel Street And 36 To 48 Shirley Street, Canning Town, London E16 1HUDecision The Strategic Development Committee unanimously RESOLVED to AGREE: 1. The reasons for approval as set out in... Agreed Open
28 Apr 2026 Holiday Inn Express 1 - 3 Silvertown Way, Canning Town, London E16 1EADecision The Strategic Development Committee unanimously RESOLVED to AGREE: 1. Agree the reasons for approval as set ... Agreed Open
21 Apr 2026 36 New Barn Street Plaistow, London E13 8JYDecision Strategic Development Committee RESOLVED to AGREE 1. the reasons for approval as set out in the report; 2. d... Agreed Open