Revenue Budget Monitoring

Decided Executive 6 papers

Cabinet decided this item on Monday 14 November 2016. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

CAB 63/16 The Cabinet Member for Finance and Resources introduced a report informing the Cabinet that a s at September 2016, the Councils revenue budget is more or less ‘on budget’ (compared to the position in July which showed £1.18m overspending). Although the position is balanced overall, there remain significant overspends within the service areas. These areas were identified in full in the report. Cabinet was informed by the Cabinet Member that the over- spend had been offset by non-service underspends on Council tax benefit rebates), Council tax surplus and Teachers pension savings. The reported position excluded schools, which are currently reporting a deficit position of £2.5m. The overall service position (including Schools) is £4.26m overspend, however, Schools have nil effect on the overall Council position as any variance against base budget is matched by a corresponding reserve transfer to or from schools balances. The Cabinet member stated that the net position assumes, as always at the early stages of the year, that the contingency budget of £1.47m is ‘committed’. There are no known commitments on this currently and if this remained the case at year-end, the position would be £1.5m underspend. The Cabinet Member informed colleagues that although the position has improved by £1.2m since that reported in July, as required by Cabinet; officers must continue to focus on specific action to address each of the overspending areas and ensure the emphasis remains on improving the position where possible and manage within budget. Non –service budgets will not necessarily be able to mitigate against service area overspending in the future. Cabinet Members considered the Cabinet member had presented a positive report but recognised the need for management action and the 2017/18 budget needs to resolve the underlying service areas budget issues robustly.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Budget Monitoring Position – September 2016 Adult & Community Services OVERALL NET POSITION Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Budget (£'000) 39,219 39,219 39,219 39,219 39,189 39,326 39,326 39,326 39,326 39,326 39,326 39,326 Forecast (£'000) 40,402 40,402 40,402 40,121 40,009 39,995 39,995 39,995 39,995 39,995 39,995 39,995 Variance (£'000) 1,183 1,183 1,183 902 820 669 669 669 669 669 669 669

Key Elements of Budget Variances: STAFFING Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Budget (£'000) 12,247 12,247 12,247 12,247 12,218 12,239 12,239 12,239 12,239 12,239 12,239 12,239 Forecast (£'000) 12,383 12,383 12,383 12,328 12,349 12,340 12,340 12,340 12,340 12,340 12,340 12,340 Variance (£'000) 136 136 136 81 131 102 102 102 102 102 102 102

DELIVERY OF MTRP Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar SAVINGS

MTRP Target (£'000) 1,712 1,712 1,712 1,712 1,712 1,712 1,712 1,712 1,712 1,712 1,712 1,712 Forecast Savings (£'000) 1,712 1,654 1,774 1,771 1,781 2,005 2,005 2,005 2,005 2,005 2,005 2,005 Variance (£'000) 0 58 -62 -59 -69 -293 -293 -293 -293 -293 -293 -293 FIP Reconciliation period MAY JUN JUL AUG SEP

AREA OF Budget Forecast Variance Status Comments RISK £000 £000 £000

Majority of overspend due to the following: £150k under delivery of Double Handling Community Saving, £178k reduction in SPG grant, £143k unachievable inflationary increase on Care 27,629 28,649 1,020 R income, £400k historic budget deficit, £50k loss of respite income Budget Monitoring Position – September 2016 Adult & Community Services SIGNIFICANT VARIANCES Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Community Care Packages 956 660 578 575 External Residential & Non Resi income 328 521 524 445 Integrated Community Equipment -84 -78 -89 -89

Staffing Budgets 136 81 131 102 Transport Savings (mainly Homecare) -113 -105 -109 -108

Supplies & Services 0 -113 -138 -134

Other -40 -64 -77 -122 Variance (£'000) 0 0 1,183 902 820 669 0 0 0 0 0 0 Budget Monitoring Position – September 2016 Adult & Community Services

Change since last month Current & Emerging Risks / Opportunities (Including non delivery of MTRP savings)

The £1.020m overspend on community care budgets has reduced by £82k since last month. Despite an increase in overall client numbers forecasts now include an additional £150k SPG funding due to an agreement that funding will be identified for core expenditure by March 2017.

The main reasons for the £1.02m overspend is as follows: • £178k reduction is SPG with no corresponding reduction to package cost • £143k unachievable income inflation added to 16/17 budget • £150k undeliverable Double Handling saving (full target of £300k) • £400k inherent pressure from prior years (pressure now added in 17-18 MTRP) • £50k loss of respite income due to fairer charging policy

Integrated Community Equipment Budget £89k u/spend – This is due to the NCC budget allocation being higher than the agreed pooled contribution. This budget can be re-allocated to areas of pressure.

Staffing budgets £102k overspend – Decrease compared to last month. Previous years have tended to underspend overall based on early achievement of savings projects as a result of redundancies. There are significantly less staff in adult services that in prior years as a result of outsourcing services and therefore less scope to make savings in this area. Currently, the vacancy turnover target is not being achieved.

Transport savings currently being forecasted are as a result of lower car allowances being claimed for homecare staff however there is a planned restructure of extra-care and homecare staff that may need reconfiguring of budgets.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Adults Budget Monitoring Dashboard Sept 2016Report 94 KB DownloadRead as text
PDF
Childrens Budget Monitoring Dashboard Sept 2016Report 94 KB Download
PDF
Directorate Budget Monitoring Dashboard Sep 2016Report 78 KB Download
PDF
Education Budget Monitoring Dashboard September 2016Report 100 KB Download
PDF
Revenue Budget MonitoringReport 484 KB Download
PDF
ab Overall Budget Monitoring Dashboard Sept 2016Report 116 KB Download

At this meeting

Whole meeting

Who was there

9 of 9 attended
DW
Councillor Debbie WilcoxChair, present
PC
Councillor Paul CockeramCommittee Member, present
GG
Councillor Gail GilesCommittee Member, present
DH
Councillor Debbie HarveyCommittee Member, present
RJ
Councillor Roger JeavonsCommittee Member, present
RP
Councillor Robert PooleCommittee Member, present
JR
Councillor John RichardsCommittee Member, present
RT
Councillor Ray TrumanCommittee Member, present
MW
Councillor Mark WhitcuttCommittee Member, present

On this subject at Newport

Search all
  1. Revenue Budget MonitoringThis decision
  2. Revenue Budget Outturn - 2025/26Noted
  3. 2026-27 Revenue Draft Budget and MTFP: Draft ProposalsAgreed
  4. November Revenue Budget MonitorNoted
  5. September Revenue Budget MonitorNoted
  6. Revenue Budget MonitorNoted

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies