Newport City Council
Cabinet, Monday 14 November 2016 at 11.00am

Capital Programme Monitoring and Additions

Approved Executive 1 paper

Cabinet approved this item on Monday 14 November 2016. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

CAB 64/16 The Cabinet Member for Finance and Resources introduced a report informing Members of the current position in relation to the Capital Programme The Cabinet Member stated that the report sought approval from Cabinet to add 4 additional budgets into the capital programme: Three of these already exist in the programme but now have an increased budget due to additional grant award; the other was a new allocation for fit-out of the developer-built Jubilee Park Primary School, to be funded via borrowing and as advised to Cabinet in the Education report presented at the September meeting. The Cabinet Member stated that the Cabinet that the capital budget for 2016/17 currently stands at £48.1m, with expenditure as at the end of September totalling £8.1m. He stated that at this stage, this was not a concern as the trend is for expenditure to be higher during the second half of the financial year, particularly in quarter 4. The Cabinet Member suggested, however, that another review – like the one undertaken this time last year – of phasing of budgets was required. This would help ensure that slippage is kept to a minimum and timing of spend is realistic. The main area of slippage reported was within the Education service area due to delays in progressing with significant schemes. The 21 st Century Schools programme featured three ongoing schemes that are subject to the recent request for additional grant funding from Welsh Government, which could not be delayed, meaning that expenditure continues. It was reported that the outcome of the grant increase request should be known by January 2017, at which point the necessary budget increases will be made to the capital programme. Some of the other schemes were reported as making up the total slippage, these included asset maintenance and the Gypsy / Traveller Site, along with some Section 106 funded schemes Cabinet was also provided with an update on the capital receipts position as at the end of September – currently at around £7.9m which exceeds the original target of £7.5m. The Head of Finance stated that there is now a need to secure at least £9.5m in order to minimise borrowing requirements on the Council’s share of 21 st Century Schools cost pressures.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 14th November 2016

Item No:

Subject Capital Programme Monitoring and Additions September 2016 Purpose To submit to Cabinet for approval, requests for new capital schemes to be added to the Council’s Capital Programme.

To update Cabinet on current spending against the Capital Programme schemes highlighting the forecast outturn position for the programme as at September 2016.

Author Senior Finance Business Partner (Capital)

Ward All Wards

Summary The report requests that new schemes be added to the programme. The report also updates Cabinet on the capital expenditure forecast position and the current position regarding capital receipts.

Proposal To approve the additions to the Capital Programme requested in the report.

To note the capital expenditure forecast position as at September 2016 and to note and approve the ‘risk’ in spending on approved 21C schools projects before confirmation of WG match funding is confirmed.

To note and approve the allocation of in-year capital receipts.

Action by Assistant Head of Finance

Timetable Immediate This report was prepared after consultation with:

 Heads of Service  Accountancy teams for relevant service areas  Relevant Service Area Project Managers  NORSE Property Services

Signed Background  In February 2014, the Council approved a four year Capital Programme to cover the financial years 2014/15 to 2017/18 totalling £80.551 million. We are now in the third year of the four-year programme, and over time changes have been made to the programme to revise the total budget to £119.684 million. The table below summarises the changes made to date:

Report 2014/15 2015/16 2016/17 2017/18 Total £000’s £000’s £000’s £000’s £000’s Budget Budget Budget Budget Original Programme 42,619 12,222 11,414 14,296 80,551 Actual Budget Budget Budget Capital Programme Outturn 27,197 39,993 27,813 20,063 115,066 Report 14/15 Capital Programme Monitoring 27,197 26,146 39,036 18,198 110,577 and Additions January 2016 Actual Actual Budget Budget Capital Programme Outturn 27,197 25,783 42,137 18,198 113,315 Report 15/16 Capital Programme Monitoring 27,197 25,783 46,823 18,198 118,001 and Additions July 2016 This Report 27,197 25,783 48,131 18,573 119,684

 The changes to the capital programme identified in this report have increased the overall size of the remaining two year programme by £1,683k. The resulting changes to the funding of the capital programme are: o Increase in external grant – £1,298k o Increase in unsupported borrowing – £385k

 Responsible officers have written to all Heads of Service to request discussions on emerging priorities in terms of corporate capital investment needs over the medium term, in order to inform the new rolling four-year capital programme to begin in 2017/18. In addition, the new Corporate Plan and administration will also be key factors in developing the new programme. It is important that project budget managers continue to provide accurate projections of expenditure, due to slippage and borrowing implications.

 Cabinet will note that budgets are likely to be subject to significant change depending on the decisions made following the recent submission by the Education service area to Welsh Government. This submission requests an extension to the current approved funding envelope on a match funding basis in order to address the current forecast shortfalls in project budgets. Cabinet have already approved the actual projects but their funding solution can’t be confirmed until WG review the Council’s submission for match funding. It is important to note that, until a decision is made by WG on the availability of grant funding, a number of projects are currently progressing at a risk that the full financial cost of the shortfall will be borne by the Council. Delaying progress on these schemes would otherwise incur avoidable costs and jeopardise completion deadlines. Current budgets and funding will be updated in January after WG decision on match funding

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitoring and AdditionsReport 660 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
DW
Councillor Debbie WilcoxChair, present
PC
Councillor Paul CockeramCommittee Member, present
GG
Councillor Gail GilesCommittee Member, present
DH
Councillor Debbie HarveyCommittee Member, present
RJ
Councillor Roger JeavonsCommittee Member, present
RP
Councillor Robert PooleCommittee Member, present
JR
Councillor John RichardsCommittee Member, present
RT
Councillor Ray TrumanCommittee Member, present
MW
Councillor Mark WhitcuttCommittee Member, present

On this subject at Newport

Search all
  1. Capital Programme Monitoring and AdditionsThis decision
  2. Capital Programme Monitoring and Additions Report - 2025/26 OutturnApproved
  3. Capital Programme Monitoring and Additions Report - October 2025Approved
  4. Capital Programme Monitoring and Additions - JulyApproved
  5. Capital Programme Monitoring and Additions OutturnApproved
  6. Capital Programme Monitoring and Additions Report - November 2024Approved

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies