CAB 04/18 The Chair of Cabinet presented the latest update on the capital budget, showing steady progress on the delivery of the Council’s capital programme and individual schemes, including the 21st century schools projects. Attention was drawn to the additions since Cabinet’s last report on this in November, as detailed on p86 of the agenda: St Julian’s High Building Improvements (£145k) Glan Llyn Fixtures, Fittings and Furniture (£50k) Schools Computer Replacements Programme (£116k) Maplewood Play Area (reduced by £184k) Otherwise the programme was unchanged and continued to be on track. 1. To approve the additions to the Capital Programme requested in the report. 2. To note the capital expenditure position as at November 2017. 3. To note the balance of and approve the allocation of in-year capital receipts. Heads of Service; Accountancy Teams; Service Area Project Managers; NORSE Property Services. Implemented By: Assistant Head of Finance Implementation Timetable: Immediate 1. To approve the additions to the Capital Programme requested in the report. 2. To note the capital expenditure position as at November 2017. 3. To note the balance of and approve the allocation of in-year capital receipts.
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject Capital Programme Monitoring and Additions November 2017 Purpose To submit to Cabinet for approval, requests for new capital schemes to be added to the Council’s Capital Programme.
To update Cabinet on current spending against the Capital Programme schemes highlighting the forecast outturn position for the programme as at November 2017.
Author Senior Finance Business Partner (Capital)
Ward All Wards
Summary The report requests that new schemes be added to the programme. The report also updates Cabinet on the current capital expenditure position as at the end of November 2017 along with the forecast outturn for 2017/18. The net effect of the forecasts provided shows an overall Authority-wide underspend variance of £10,157k against the budget of £46,919k. This includes forecast slippage of budget into 2018/19 to the value of £8,024k, giving a true forecast underspend of £2,133k.
The report also updates Cabinet on the current position regarding capital receipts. To date £886k has been received in-year (excluding JV receipts); which is a significant amount towards the £1,000k target.
Proposal To approve the additions to the Capital Programme requested in the report.
To note the capital expenditure forecast position as at November 2017.
To note the balance of and approve the allocation of in-year capital receipts.
Action by Assistant Head of Finance
Timetable Immediate This report was prepared after consultation with:
Heads of Service Accountancy teams for relevant service areas Relevant Service Area Project Managers NORSE Property Services Signed Background 2017/18 is the final year of the current four-year capital programme originally approved by Council in February 2014 at an overall cost of £80.551 million. Over time, a number of changes have been made to the programme due to emerging developments, re-evaluation of priorities and the availability of specific funding sources; these changes have been reported to and approved by Cabinet on a quarterly basis over the past three years. The total budget for the period as a whole now stands at £132.292 million, which has increased slightly from the September 2017 report. The table below summarises the changes made to date:
2014/15 2015/16 2016/17 2017/18 Total Report £000’s £000’s £000’s £000’s £000’s Budget Budget Budget Budget Original Programme 42,619 12,222 11,414 14,296 80,551 Actual Budget Budget Budget Capital Programme Outturn 27,197 39,993 27,813 20,063 115,066 Report 14/15 Actual Actual Budget Budget Capital Programme Outturn 27,197 25,783 42,137 18,198 113,315 Report 15/16 Actual Actual Actual Budget Capital Programme Outturn 27,197 25,783 32,393 39,456 124,829 Report 16/17 Capital Programme Monitoring 27,197 25,783 32,393 43,312 128,685 & Additions Report July 2017 Capital Programme Monitoring 27,197 25,783 32,393 46,792 132,165 & Additions Report Sept 2017 This Report 27,197 25,783 32,393 46,919 132,292
Changes to the approved Capital Programme The changes to the capital programme identified in this report have increased the overall size of the current year programme by £127k since reported in September 2017. Appendix A shows the revised capital programme for 2017/18 including the proposed changes which are to be approved by Cabinet. This has increased the borrowing requirements by £50k for 2017/18, but this has already been factored into the work undertaken for the 2018/19 capital programme. These changes are summarised in the paragraphs below.
St Julian’s High Building Improvements (£145k) –. The school has submitted a bid which has been approved to increase the capacity of the school toilets. Scheme is expected to be completed in 2017/18. This has been funded from schools works reserve.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.