Capital Programme Monitoring and Additions - July

Approved Executive 1 paper

Cabinet approved this item on Wednesday 10 September 2025. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision : Cabinet - · Approved the additions to the Capital Programme requested in the report (Appendix A). · Noted the predicted capital expenditure outturn position for 2025/26. · Approved the reprofiling of £14.8m from the 2025/26 budget into future years. · Noted the available remaining capital resources (‘headroom’) and the earmarked usage of that resourcing. · Noted the inclusion of the Treasury Management prudential indicators, included within the report. · Noted the headroom as per the report.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 10 September 2025

Subject Capital Programme Monitoring and Additions Report – July 2025 Purpose To provide Cabinet with a forecast of capital outturn against budget based on the activity incurred up to the end of July 2025

To submit to Cabinet, for approval, requests for new capital projects to be added to the Council’s Capital Programme.

To note the amendments to the capital programme

To update Cabinet on the current available capital resources (‘headroom’).

To update Cabinet on the position in relation to Treasury Management prudential indicators as at July 2025.

Author Chief Accountant / Head of Finance

Ward All

Summary The Council has an extensive capital programme, investing across the authority in areas such as schools, heritage assets, energy efficiency schemes, invest to save programmes and in the regeneration of the city centre. This report updates the Cabinet on its capital programme and the forecast for the 2025/26 financial year, and specifically:

- The starting capital programme budget for 2024/25 was £86.142m. Additions (largely grants) and revisions have increased the budget by a net £10m and reprofiling of budgets into future years have reduced this year’s budget by £14.8m, to provide a revised budget of £80.540m - Against this revised budget, costs are predicted to be £80.546m introducing a very slight variance of £6k.

Proposal 1. To approve the additions to the Capital Programme requested in the report (Appendix A) 2. To note the predicted capital expenditure outturn position for 2025/26 3. To approve the reprofiling of £14.8m from the 2025/26 budget into future years 4. To note the available remaining capital resources (‘headroom’) and the earmarked usage of that resourcing. 5. To note the inclusion of the Treasury Management prudential indicators, included within the report. 6. To note the headroom as per the report Action by Head of Finance

Timetable Immediate This report was prepared after consultation with:

▪ Service Budget Holders and Project Managers ▪ Capital Assurance Group ▪ Norse Representatives ▪ Head of Finance

Signed Background

The Council has a rolling 5-year capital programme, with a new year added on each year. Cabinet receive monitoring updates throughout the financial year and the Capital Programme is updated to reflect changes as they are received i.e. additions and amendments. Following previous years approaches, approval of slippage, and associated revisions to budgets, will only be sought as part of any reprofiling exercises that are completed in-year, with final approval for slippage being sought at the end of the financial year when outturn is known.

The changes to the programme to date are shown in summary form in the table below, the detail of which is shown in Appendix A.

Table 1: Current Capital Programme

2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 Total Outturn Budget Budget Budget Budget Budget £’000 £’000 £’000 £’000 £’000 £’000 £’000 Initial Budget 91,600 86,142 30,835 31,170 41,772 32,544 147,709

Revisions / Reprofiling (14,814) 14,814 - Additions/deletions/ 9,213 782 9,995 Amendments

July Budget agreed in 79,452 80,540 46,431 31,170 41,772 32,544 232,457 September Cabinet

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitoring and Additions: JulyReport 353 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
DB
Councillor Dimitri BatrouniChair, present
DD
Councillor Deb DaviesCommittee Member, present
MS
Councillor Mark SpencerCommittee Member, present
ES
Councillor Emma Stowell-CortenCommittee Member, present
LL
Councillor Laura LaceyCommittee Member, present
JH
Councillor Jason HughesCommittee Member, present
JC
Councillor James ClarkeCommittee Member, present
YF
Councillor Yvonne ForseyCommittee Member, present
SA
Councillor Saeed AdanCommittee Member, present
RH
Councillor Rhian HowellsCommittee Member, present

On this subject at Newport

Search all
  1. Capital Programme Monitoring and Additions - JulyThis decision
  2. Capital Programme Monitoring and Additions Report - 2025/26 OutturnApproved
  3. Capital Programme Monitoring and Additions Report - October 2025Approved
  4. Capital Programme Monitoring and Additions OutturnApproved
  5. Capital Programme Monitoring and Additions Report - November 2024Approved
  6. Capital Programme Monitoring and Additions - September 2024Approved

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies