Newport City Council
Cabinet, Wednesday 17 December 2025 at 4.00pm

Capital Programme Monitoring and Additions Report - October 2025

Approved Executive 1 paper

AI summaryNewport City Council Cabinet approved £1.914m of new additions to the 2025/26 capital programme and agreed to reprofile £12.705m of spending into future years against a revised £69.749m budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital programme changes and £12.705m reprofiling approved
Money£1.914m additions, £12.705m reprofiledNet additions to programme; reprofiling to future years
What happens nextImmediateHead of Finance to action
Who it affectsAll wardsCapital programme covers the whole authority

What was decided

Cabinet approved the additions to the Capital Programme set out in Appendix A. Report P12

Cabinet approved reprofiling £12.705m from the 2025/26 budget into future years, reducing the in-year budget to £69.749m. Report P11, P14, P32

Cabinet agreed the use of reserves from the unallocated prior year underspend: £70k for Regeneration studies and £50k to top up Road Safety Scheme funding.

Why

Forecast cost of £69.526m against the revised £69.749m budget leaves a small net variance of £223k. Report P11, P32

Available capital headroom stands at £14.375m, but new borrowing is limited by the Council's wider financial pressures and high interest rates. Report P44, P48, P67

The Council aims to maximise funding from sources other than borrowing and to prioritise capital expenditure within the current affordability envelope. Report P40, P41, P65

What happens next

The Head of Finance will action the approved changes immediately. Report P17, P18

Cabinet will receive further capital monitoring reports through the year, with final slippage approval at year end. Report P21

St Mary's Primary School is being re-tendered and a further decision will be made on next steps. Report P37

The money

  • £12.705m reprofiling of 2025/26 capital budget into future years Report P14
  • £1.914m net additions to the capital programme (largely grants) Report P11, P27, P31
  • £69.749m revised 2025/26 capital programme budget Report P11, P28, P32, P34, P104
  • £223k forecast variance against revised budget Report P11, P32, P34
  • £70k from reserves for Regeneration studies
  • £50k from reserves to top up Road Safety Scheme
  • £14.375m capital headroom available Report P44, P48, P67
  • £86.142m original 2024/25 starting capital budget Report P11

Options considered

  • Chosen: Approve the changes to the Capital Programme and note the projected outturn position, including the use of capital receipts. Preferred option; ensures the programme reflects latest grants and reprofiling needs Report P60, P64
  • Chosen: Note the available headroom and prioritise future capital expenditure to maintain spend within the affordability envelope. Recognises revenue pressures from future borrowing can add to the MTFP gap Report P61, P65
  • Rejected: Not to take forward some or all of the changes to the Capital Programme. No reason given in the report; not the preferred option Report P62

Implications

  • Financial: Reprofiling moves £12.705m of capital spending from 2025/26 to later years; forecast outturn is £69.526m against a £69.749m budget. Report P11, P14, P32
  • Financial: Capital headroom of £14.375m remains available but new borrowing is limited by the Council's medium-term financial pressures and high interest rates. Report P44, P67, P68
  • Risk: Risks include overspend against approved budget, programme growth from unforeseen events, and excessive slippage between financial years. Report P56
  • Legal: Cabinet has the executive power to approve the capital programme additions set out in the report and Appendix A, with no further legal implications. Report P69, P70
  • Climate: The capital programme includes schemes that reduce carbon footprint, such as low carbon buildings, LED replacement, active travel and electric vehicle purchases. Report P89
  • Other: The programme supports the Wellbeing of Future Generations (Wales) Act 2015 and the Council's Corporate Plan objectives. Report P71, P76, P77

Who and where

  • All wards in Newport Report P9
  • School communities, through the Sustainable Communities for Learning programme, Caerleon Comprehensive, Whiteheads, St Mary's and Welsh Medium projects Report P37
  • Regeneration areas, including Transporter Bridge, new Leisure Centre and Pride in Place projects Report P37
  • Disabled residents, through the Disabled Facilities Grants programme Report P37, P107
  • Road users, through the Fleet Replacement Programme and Road Safety Scheme Report P37
  • Service users of the Civic Centre, homelessness accommodation, and adult social care telecare Report P37, P107, P108

Timeline

  • October 2025: Monitoring period for capital expenditure to date Report P3, P21
  • December 2025: Nant Gwenlli refurbishment works expected to complete Report P37
  • 10 December 2025: Report dated Report P92
  • 17 December 2025: Cabinet decision Report P2
  • January 2026: Caerleon Comprehensive School main construction programme expected to commence Report P37
  • Early 2026: Transporter Bridge Visitor Centre contractor to remobilise for landscaping works Report P37
  • 2026/27: Transporter Bridge project completion forecast; new Leisure Centre construction continues; £5,706k reprofiled for St Mary's Report P37

Plain English for the jargon

  • Capital headroom: Available unspent capital resources that can be allocated to new projects without new borrowing
  • Reprofiling: Moving capital budget between financial years to reflect revised spending plans
  • MRP (Minimum Revenue Provision): The minimum amount the Council must set aside each year to repay debt used for capital spending
  • Prudential Indicators: CIPFA-required measures the Council uses to set and monitor capital and borrowing limits
  • Section 106 funding: Developer contributions towards infrastructure and services, agreed when planning permission is granted
  • MTFP (Medium Term Financial Plan): The Council's planning document setting out its revenue and capital position over coming years
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Decision : That Cabinet – § approved the additions to the Capital Programme requested in the report (Appendix A); § noted the predicted capital expenditure outturn position for 2025/26; § approved the reprofiling of £12.705m from the 2025/26 budget into future years; § noted the available remaining capital resources (‘headroom’) and the earmarked usage of that resourcing; § noted the inclusion of the Treasury Management prudential indicators, included within the report; § noted the headroom as per the report; § noted the use of reserves, funded from the unallocated prior year underspend reserve: · £70k for Regeneration studies. · £50k to top up the Road Safety Scheme funding due to higher take up.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 17 December 2025

Subject Capital Programme Monitoring and Additions Report – October 2025 Purpose To provide Cabinet with a forecast of capital outturn against budget based on the activity incurred up to the end of October 2025

To submit to Cabinet, for approval, requests for new capital projects to be added to the Council’s Capital Programme.

To note the amendments to the capital programme

To update Cabinet on the current available capital resources (‘headroom’).

To update Cabinet on the position in relation to Treasury Management prudential indicators as at October 2025.

Author Chief Accountant / Head of Finance

Ward All

Summary The Council has an extensive capital programme, investing across the authority in areas such as schools, heritage assets, energy efficiency schemes, invest to save programmes and in the regeneration of the city centre. This report updates the Cabinet on its capital programme and the forecast for the 2025/26 financial year, and specifically:

- The starting capital programme budget for 2024/25 was £86.142m. This was revised to £80.540m by Cabinet via the Capital Programme Monitoring and Additions Report – July 2025. Further additions (largely grants) and revisions have increased the budget by a net £1.914m and reprofiling of budgets into future years have reduced this year’s budget by £12.705m, to provide a revised budget of £69.749m - Against this revised budget, costs are predicted to be £69.526 introducing a very slight variance of £223k.

Proposal 1. To approve the additions to the Capital Programme requested in the report (Appendix A)

2. To note the predicted capital expenditure outturn position for 2025/26

3. To approve the reprofiling of £12.705m from the 2025/26 budget into future years

4. To note the available remaining capital resources (‘headroom’) and the earmarked usage of that resourcing. 5. To note the inclusion of the Treasury Management prudential indicators, included within the report.

6. To note the headroom as per the report

Action by Head of Finance

Timetable Immediate

This report was prepared after consultation with:

▪ Service Budget Holders and Project Managers ▪ Capital Assurance Group ▪ Norse Representatives ▪ Head of Finance Background

The Council has a rolling 5-year capital programme, with a new year added on each year. Cabinet receive monitoring updates throughout the financial year and the Capital Programme is updated to reflect changes as they are received i.e. additions and amendments. Following previous years approaches, approval of slippage, and associated revisions to budgets, will only be sought as part of any reprofiling exercises that are completed in-year, with final approval for slippage being sought at the end of the financial year when outturn is known.

The changes to the programme to date are shown in summary form in the table below, the detail of which is shown in Appendix A.

Table 1: Current Capital Programme

2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 Total Outturn Budget Budget Budget Budget Budget £’000 £’000 £’000 £’000 £’000 £’000 £’000 Initial Budget 91,600 86,142 30,835 31,169 41,771 32,544 147,709

Revisions / Reprofiling (14,814) 14,814 0 Additions/deletions/ 9,213 782 9,995 Amendments

July Budget agreed in 79,452 80,540 46,431 31,169 41,771 32,544 232,455 September Cabinet

Revisions / Reprofiling (12,705) 12,705 0 Additions/deletions/ 1,914 223 2,138 Amendments

Revised October Budget 79,452 69,749 59,360 31,169 41,771 32,544 234,594

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitoring and Additions Report: October 2025Report 367 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
DB
Councillor Dimitri BatrouniChair, present
DD
Councillor Deb DaviesCommittee Member, present
MS
Councillor Mark SpencerCommittee Member, present
ES
Councillor Emma Stowell-CortenCommittee Member, present
LL
Councillor Laura LaceyCommittee Member, apologies
JH
Councillor Jason HughesCommittee Member, present
JC
Councillor James ClarkeCommittee Member, present
YF
Councillor Yvonne ForseyCommittee Member, present
SA
Councillor Saeed AdanCommittee Member, present
RH
Councillor Rhian HowellsCommittee Member, present

On this subject at Newport

Search all
  1. Capital Programme Monitoring and Additions Report - October 2025This decision
  2. Capital Programme Monitoring and Additions Report - 2025/26 OutturnApproved
  3. Capital Programme Monitoring and Additions - JulyApproved
  4. Capital Programme Monitoring and Additions OutturnApproved
  5. Capital Programme Monitoring and Additions Report - November 2024Approved
  6. Capital Programme Monitoring and Additions - September 2024Approved

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies