That Cabinet: 1. Approved the additions to the Capital Programme requested in the report (Appendix A). 2. Noted the predicted capital expenditure outturn position for 2024/25. 3. Noted the amendments and indicative slippage for the capital programme. 4. Noted the available remaining capital resources (‘headroom’) and the earmarked usage of that resourcing. 5. Noted the inclusion of the Treasury Management prudential indicators, included within the report. 6. Noted the use of the headroom as noted in the report.
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject Capital Programme Monitoring and Additions Report – November 2024 Purpose To provide Cabinet with a forecast of capital outturn against budget based on the activity incurred up to the end of November 2024
To submit to Cabinet, for approval, requests for new capital projects to be added to the Council’s Capital Programme, and reprofiling of schemes where applicable.
To note the amendments and indicative slippage for the capital programme
To update Cabinet on the current available capital resources (‘headroom’).
To update Cabinet on the position in relation to Treasury Management prudential indicators as at November 2024.
Author Chief Accountant / Head of Finance
Ward All
Summary The Council has an extensive capital programme, investing across the authority in areas such as schools, heritage assets, energy efficiency schemes, invest to save programmes and in the regeneration of the city centre. This report updates Cabinet on its capital programme and the forecast for the 2024/25 financial year, and specifically:
- The starting capital programme budget for 2024/25 was £90.7m. This was revised to £82.7m at the September Cabinet meeting and £87.5m at the November Cabinet meeting. This report requests approval to increase the 24-25 budget by a net £4.056m to now be £91.6m. £404k of this relates to new additions to the programme and £3.650m relates to reprofile of schemes - Against this revised budget, costs are predicted to be £80.5m introducing a £11m net variance, predominantly slippage.
Proposal 1. To approve the additions to the Capital Programme requested in the report (Appendix A)
2. To note the predicted capital expenditure outturn position for 2024/25
3. To note the amendments and indicative slippage for the capital programme
4. To note the available remaining capital resources (‘headroom’) and the earmarked usage of that resourcing. 5. To note the inclusion of the Treasury Management prudential indicators, included within the report.
6. To note the use of the headroom as noted in the report
Action by Head of Finance
Timetable Immediate
This report was prepared after consultation with:
▪ Service Budget Holders and Project Managers ▪ Capital Assurance Group ▪ Norse Representatives ▪ Head of Finance
Signed Background
The Council has a rolling 5-year capital programme, with a new year added on each year. Cabinet receive monitoring updates throughout the financial year and the Capital Programme is updated to reflect changes as they are received i.e. additions and amendments. Following previous years approaches, approval of slippage, and associated revisions to budgets, will only be sought as part of any reprofiling exercises that are completed in-year, with final approval for slippage being sought at the end of the financial year when outturn is known.
The changes to the 2024/25 year of the programme to date are summarised in the table below; the detail of which is shown in Appendix A and which also includes the additions/adjustment over the full programme period.
Revised November 24 61,225 91,599 47,562 8,524 6,487 7,565 161,733
Additions
Appendix A confirms that total additions and deletions are £404k with £3.650m being brought forward from 2025/26. This is in relation to the reprofiling of the Sustainable Communities for Development programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.