2025-26 YEAR END REPORT OF RISK MANAGEMENT GOVERNANCE

Noted Executive 2 papers

AI summaryCabinet noted North Herts' 2025-26 year-end risk management governance report and recommended Council do the same, recording seven red corporate risks in early May.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCouncil also asked to note the report
MoneyNot stated
What happens nextCouncil to note the reportAt a future Full Council meeting
Who it affectsCouncil risk management governanceSeven red corporate risks identified

What was decided

Cabinet noted the year-end report on risk management governance and recommended that Council also note it. Report 2.1

The recommendation was made to provide assurance that the Council is effectively managing risk and to meet the annual review requirement of the Risk Management Strategy. Report 3.1, 9.3

Why

The Council's Risk Management Strategy requires this annual review to be presented to Council, and Cabinet has responsibility for the management of risk. Report 3.1, 9.2

At the time Appendix A was finalised in early May, the Council had seven red corporate risks, the two highest scoring being Local Government Reorganisation and Devolution, and Resourcing. Report 1.2

What happens next

The report will be referred on to Full Council for noting. Report 2.1, 7.2, 9.3

The Council Delivery Plan will continue to report on key projects, risks and performance indicators to Cabinet on a quarterly basis. Report 7.1

Options considered

  • Rejected: No alternative options considered. Alternatives would not adhere to the adopted Risk Management Strategy Report 4.1

Implications

  • Legal: The Finance, Audit and Risk Committee's Terms of Reference require it to monitor the effective development and operation of risk management and corporate governance. Report 9.1
  • Risk: Good risk management supports and enhances the council's decision making, and the regular review of its effectiveness helps ensure risk management works well. Report 11.1, 11.2
  • Equalities: No direct equalities implications arise from this report, though the Public Sector Equality Duty still applies. Report 12.1, 12.2
  • Financial: There are no direct financial implications arising from this report. Report 10.1
  • Other: There are no direct environmental, HR or social value implications arising from this report. Report 13.1, 14.1, 15.1

Who and where

  • North Hertfordshire District Council, in its approach to managing risk Report 1.1, 7.3
  • The Finance, Audit and Risk Committee, which supports good governance Report 7.2, 9.1
  • The Cabinet and Full Council, which receive risk management reports Report 7.1, 7.2, 9.2
  • The Risk and Performance Management Group (RPMG), which reviews corporate risks Report 5.1

Timeline

  • 15th May 2026: Report referred to in the Forward Plan Report 6.1
  • Early May (when Appendix A was finalised): Seven red corporate risks identified Report 1.2
  • 2026-06-16: Cabinet meeting where the report was noted

Plain English for the jargon

  • LGR: Local Government Reorganisation
  • RPMG: Risk and Performance Management Group
  • FAR Committee: Finance, Audit and Risk Committee
  • Red corporate risk: A risk scored at the highest level on the council's risk scale, with the seven listed scoring 7 or 8
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That Cabinet noted the report. RECOMMENDED TO COUNCIL: That it: (1) Note the report. REASON FOR RECOMMENDATION: To provide assurance that the Council is effectively managing risk. The Council’s Risk Management Strategy details that this annual review should be presented to Council. Cabinet have responsibility for the management of risk. That Cabinet noted the report. RECOMMENDED TO COUNCIL: That it note the report. REASON FOR RECOMMENDATION: To provide assurance that the Council is effectively managing risk. ... view the full minutes text for item 13.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 4 pages

Executive summary

1.1This report provides an update on the effectiveness of the Risk Management governance arrangements at the Council.

1.2At the time Appendix A was finalised (early May), the Council had seven red corporate risks. The two risks with the highest scores relate to Local Government Reorganisation (LGR) and Devolution, and Resourcing. A significant element of the LGR risk specifically relates to resourcing/ staffing. The remaining five red risks (with scores of 7 or 8) are two over-arching risks (cyber risk and financial sustainability) and three project risks (Churchgate, decarbonisation phase 2 and museum collection facility).

Recommendations

2.1That the Committee comment on the Risk Management Governance update as attached at Appendix A and recommend that Cabinet refer it on the Council.

Reasons for recommendations

3.1To provide assurance that the Council is effectively managing risk. The Council’s Risk Management Strategy details that this annual review should be presented to Council. Cabinet have responsibility for the management of risk.

Alternative options considered

4.1None, as alternatives would not adhere to the adopted Risk Management Strategy.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Relevant managers provide regular updates on the risks that they are responsible for. The Council’s Risk and Performance Management Group (RPMG) regularly review risks, especially those identified as corporate risks. The RPMG is usually attended by the Executive Member for Resources, and has standing invites to members of the Cabinet, Finance, Audit and Risk Committee, and Overview and Scrutiny Committee. 6. FORWARD PLAN

6.1This report does not contain a recommendation on a key Executive decision but was referred to in the Forward Plan on 15th May 2026.

Background

7.1The Council’s key projects, risks and performance indicators are reported to Cabinet on a quarterly basis in the Council Delivery Plan report. When required, this report is also considered by Overview and Scrutiny Committee and can be used to guide their work programme.

7.2The Finance, Audit and Risk (FAR) Committee support good governance, and receive a mid-year and end of year report on Risk Management governance. The mid-year report is referred on the Cabinet. The end of year report (this report) is referred on to Cabinet and Council.

7.3The Council’s approach to Risk Management is set out in the framework, which is made up of a Policy Statement, Policy, and Strategy.

8. RELEVANT CONSIDERATIONS

8.1The end of year report on Risk Management governance is attached as Appendix A. The Appendix includes the following:

• The Council’s approach to managing and overseeing risk (sections 3-6). • The corporate risks and actions taken to manage those risks (section 7) • An overview of service risks as those more significant service risks could become corporate risks (section 8). • Performance in carrying out risk reviews and training, and detailing new and archived risks (sections 9-12) • Activities that are part of or provide significant support to risk management (sections 13-15). • Action plans for improving risk management (sections 16 and 17). The FAR Committee are encouraged to consider the effectiveness of these actions.

9.1The FAR Committee’s Terms of Reference include “to monitor the effective development and operation of risk management and corporate governance, agree actions (where appropriate) and make recommendations to Cabinet” (Constitution 10.1.5 (t)).

9.2Cabinet’s Terms of Reference include “To take decisions on resources and priorities, together with other stakeholders and partners in the local community, to deliver and implement the budget and policies decided by the Full Council. To monitor performance and risk in respect of the delivery of those policies and priorities” (Constitution 5.7.3).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025-26 YEAR END REPORT OF RISK MANAGEMENT GOVERNANCEReport 4 pages DownloadRead as text
PDF
2025-26 Year end report on Risk Management GovernanceAppendix 1 15 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. 2025-26 YEAR END REPORT OF RISK MANAGEMENT GOVERNANCEThis decision
  2. 2025-26 year end report on risk management governanceDecided
  3. Extension of appointment of independent member of finance, audit and risk committeeDecided
  4. Report on risk management governance (year-end update)Noted
  5. Risk management governance - year end reviewNoted
  6. Report on risk management governance (year-end update)Decided

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open