CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Hertfordshire District Council
Cabinet, Tuesday 21 November 2017 at 7.30pm

SECOND QUARTER CAPITAL MONITORING 2017/18

Noted Executive 3 papers

Cabinet noted this item on Tuesday 21 November 2017. Below is the council's own wording, with the papers it was decided on.

Item59

Resolved

(1) That the forecast expenditure of £14.520million in 2017/18 on the Capital programme, as set out in Paragraph 8.2 of the report, be noted, and the changes detailed in Table 3 of the report, which resulted in a net decrease of the working estimate of £0.304million, be approved; (2) That the changes to the Capital Programme for 2018/19 and onwards as a result of the revised timetable of schemes detailed in Table 2 of the report, increasing the estimated spend in 2018/19 by £0.923million (re-profiled from 2017/18), be noted, and that these be incorporated into the draft Capital Programme for 2018/19 onwards; and (3) That the position of the availability of capital resources, as detailed in Table 4 of the report, and the requirement to keep the Capital Programme under review for affordability, be noted. REASON FOR DECISION: To approve revisions to the Capital Programme, and to ensure that the Capital Programme is fully funded. (1) That the forecast expenditure of £14.520million in 2017/18 on the Capital programme, as set out in Paragraph 8.2 of the report, be noted, and the changes detailed in Table 3 of the report, which resulted in a net decrease of the working estimate of £0.304million, be approved; (2) That the changes to the Capital Programme for 2018/19 and onwards as a result of the revised timetable of schemes detailed in Table 2 of the report, increasing the estimated spend in 2018/19 by £0.923million (re-profiled from 2017/18), be noted, and that these be incorporated into the draft Capital Programme for 2018/19 onwards; and (3) That the position of the availability of capital resources, as detailed in Table 4 of the report, and the requirement to keep the Capital Programme under review for affordability, be noted. REASON FOR DECISION: To approve revisions to the Capital Programme, and to ensure that the Capital Programme is fully funded.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1To update Cabinet on progress with delivering the capital programme for 2017/18, as at the end of September 2017, indicating its impact upon the approved capital programme for 2018/19 - 2020/21. The current estimate is a decrease in spend in 2017/18 from that reported in the First Quarter Capital Monitoring report of £0.619million, and an increase in spend in future years of £0.923 million. The most significant individual changes are the inclusion of the purchase of new Fitness Equipment at Hitchin and Royston Leisure Centres, and the re-profiling of John Barker Place and Property Improvements into 2018/19.

Recommendations

2.1That Cabinet notes the forecast expenditure of £14.520million in 2017/18 on the capital programme, paragraph 8.2 refers, and approves the changes detailed in table 3 which resulted in a net increase on the working estimate of £0.304million.

2.2That Cabinet notes the changes to the capital programme for 2018/19 and onwards as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in 2018/19 by £0.923million (re-profiled from 2017/18). These will be incorporated in to the draft capital programme for 2018/19 onwards.

2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4, and the requirement to keep the capital programme under review for affordability.

Reasons for recommendations

3.1Cabinet is required to approve revisions to the capital programme.

3.2Cabinet is required to ensure that the capital programme is fully funded.

Alternative options considered

4.1Options for capital investment are considered as part of the Corporate Business Planning process.

CABINET (21.11.17) 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.

6. FORWARD PLAN

6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 28 July 2017.

Background

7.1In February 2017, Council approved the capital programme for 2017/18 to 2020/21. This was subsequently amended by reprogramming from 2016/17 and re-profiling at the first quarter.

7.2The Medium Term Financial Strategy for 2017 to 2022 confirmed that the Council will seek opportunities to utilise capital funding (including set aside receipts) for invest to save schemes and proposals that generate higher rates of return than standard treasury investments. This is one way the Council will allocate resources to support organisational transformation that will reduce revenue expenditure.

8. RELEVANT CONSIDERATIONS

Capital Programme 2017/18

8.1Summaries of the capital programme by Council priority and service are shown in appendix A together with the overall funding analysis and projected availability of capital funding balances (set aside and capital receipts). The full programme is detailed in Appendix B and shows the revised costs to date, together with the expected spend from 2017/18 to 2020/21 and the funding source for each capital scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 10: Appendix AAppendix 364 KB Download
PDF
Item 10: Appendix BAppendix 581 KB Download
PDF
SECOND QUARTER CAPITAL MONITORING 2017/18Report 269 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. SECOND QUARTER CAPITAL MONITORING 2017/18This decision
  2. Second quarter treasury management review 2025/26Noted
  3. Second quarter capital budget monitoring review 2025/26Noted
  4. Second quarter revenue budget monitoring 2025/26Noted
  5. Second quarter treasury management review 2025/26Decided
  6. Second quarter capital monitoring review 2025/26Approved

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies