North Hertfordshire District Council
Cabinet, Tuesday 20 January 2026 at 7.30pm

SECOND QUARTER CAPITAL BUDGET MONITORING REVIEW 2025/26

Noted Executive 2 papers

AI summaryCabinet noted 2025/26 capital forecast of £26.416M and approved re-profiling of £1.773M of spend into 2026/27 across the capital programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRe-profiling and resources position noted
Money£26.416M (2025/26 forecast)Down £1.298M on Q1; up £1.773M in 2026/27
What happens nextQuarterly reviewKeep programme under review for affordability
Who it affectsCapital programme 2025/26 onwardsSeveral scheme budgets re-profiled

What was decided

Cabinet noted forecast capital expenditure of £26.416M in 2025/26. Report 2.1

Cabinet approved adjustments to the 2026/27 capital programme, with a £1.773M increase in estimated spend, after scheme timetable revisions and the Museum storage update. Report 1.2, 2.2, 8.4

Cabinet noted the position on capital resources and the need to keep the capital programme under review for affordability. Report 2.3, 8.6, 8.7

Why

Cabinet is required to approve capital programme adjustments and ensure the programme is fully funded. Report 3.1

Several scheme timetables have changed, shifting spend from 2025/26 into 2026/27. Report 1.2, 8.4

Capital resources are limited and the cost of using capital receipts affects general fund affordability. Report 8.7

What happens next

Environmental Health to review Home Repair Assistance eligibility criteria and the £5,000 grant cap so the budget can be fully allocated in 2026/27. Report 8.4

Estates to bring forward options to Executive Members on next steps for Charnwood House, likely recommending a new long-lease marketing. Report 8.4

From 2026/27 the Council will need to start charging a Minimum Revenue Provision to the general fund and consider external borrowing for further capital spend. Report 8.8

The money

  • £26.416M Forecast capital expenditure 2025/26
  • £1.298M Decrease on 2025/26 forecast since Q1 report Report 1.2
  • £1.773M Increase in 2026/27 estimated spend (re-profiling) Report 1.2, 8.4
  • £0.600M Museum and Commercial Storage re-profiled to 2026/27 Report 1.2, 8.4
  • £0.346M Resurface Lairage Car Park re-profiled to 2026/27 Report 1.2, 8.4
  • £0.300M Charnwood House re-profiled to 2026/27 Report 1.2, 8.4
  • £0.235M Parking Charging Payments Management System re-profiled to 2026/27 Report 1.2, 8.4
  • £0.201M Home Repair Assistance Grants re-profiled to 2026/27 Report 1.2, 8.4
  • £0.475M Net increase in overall costs of schemes in 2025/26
  • £16.758M Decarbonisation Project current forecast Report P18
  • £4.2M Anticipated total overspend tolerance over ten-year programme
  • £127.0M Capital assets owned by the Council Report 8.1
  • £40k per year Approximate interest earned per £1.0M invested
  • £0.59M Capital Financing Requirement at 31 March 2025 (negative figure) Report 8.8

Options considered

  • Chosen: Consider options for capital investment as part of the Corporate Business Planning process. No alternatives to this monitoring report are presented Report 4.1

Implications

  • Financial: The Capital Financing Requirement has moved from negative £0.59M into positive territory, meaning the Council will have to borrow to fund the 2025/26 capital programme, with Minimum Revenue Provision charged to the General Fund in 2026/27. Report 8.8
  • Financial: Using capital receipts without replacement reduces cash for investment and therefore interest income; £1.0M of cash earns about £40k a year in interest.
  • Legal: Section 151 of the Local Government Act 1972 requires proper administration of financial affairs; Section 28 of the Local Government Act 2003 supports the quarterly monitoring approach. Report 9.3, 9.4
  • Legal: Significant additions to the budget must be approved by Full Council under the Constitution. Report 9.2
  • Legal: Asset disposals must be handled under the Council's Contract Procurement Rules. Report 9.1
  • Risk: Project risks are managed by individual project managers and recorded on a project risk log, with key risks recorded on the Council's risk management software. Report 11.2
  • Equalities: No direct equalities implications arise from the capital programme itself; an equality analysis is required for any new investment over £50k or affecting more than two wards. Report P33
  • Other: No direct human resource implications from the report. Report 15.1
  • Other: No known environmental impacts from the recommendations; some projects at section 8.4 may need environmental assessment as they progress. Report 14.1

Who and where

  • Council-wide capital programme covering 2025/26 to 2034/35 Report 1.2, 7.1, 8.1
  • Museum and Commercial Storage project (acquisition complete, now re-profiled) Report 8.4
  • Lairage Car Park resurfacing and stairwell windows/doors (delayed by access and contract issues) Report 8.4
  • Charnwood House scheme in Hitchin (options to be brought to Executive Members) Report 8.4
  • Parking Charging Payments Management System procurement Report 8.4
  • Home Repair Assistance grant recipients (eligibility and cap to be reviewed) Report 8.4
  • Decarbonisation Project (forecast up to £16.758M due to construction variations) Report P18
  • Refuse and Recycling bin service (extra bin type and demand pressures) Report P19

Timeline

  • February 2025: Council approved the Integrated Capital and Treasury Strategy 2025/26 to 2034/35 Report 7.1
  • 31st March 2025: Capital Financing Requirement recorded as negative £0.59M Report 8.8
  • From 2026/27: Minimum Revenue Provision charges to the General Fund begin if borrowing is required Report 8.8
  • End of September 2025: Position reported in this Q2 review Report 1.1
  • 23rd September 2025: Q1 capital monitoring report to Cabinet
  • 21st November 2025: Forward Plan notification of this key Executive decision Report 6.1
  • 20th January 2026: Cabinet decision on Q2 capital monitoring

Plain English for the jargon

  • CFR: Capital Financing Requirement, a measure of the Council's outstanding capital borrowing need.
  • MRP: Minimum Revenue Provision, the charge a council must make to revenue to repay capital borrowing.
  • S106: Section 106 planning obligation receipts from developers used to fund capital schemes.
  • Decarbonisation Project: Public Sector Decarbonisation scheme, with a current cost forecast of £16.758M.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That Cabinet: (1) Noted the forecast expenditure of £26.416M in 2025/26 on the capital programme, paragraph 8.3 refers. (2) Approved the adjustments to the capital programme for 2026/27, as a result of the revised timetable of schemes detailed in table 2 and 3 and the update on the museum storage project, increasing the estimated spend by £0.773M. (3) Noted the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability. REASON FOR DECISIONS: Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded. That Cabinet: (1) Noted the forecast expenditure of £26.416M in 2025/26 on the capital programme, paragraph 8.3 refers. (2) Approved the adjustments to the capital programme for 2026/27, as a result of the revised timetable of schemes detailed in table 2 and 3 and the update on the museum storage project, increasing the estimated spend by £0.773M. (3) Noted the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability. REASON FOR DECISIONS: Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 8 pages

Executive summary

1.1To update Cabinet on progress with delivering the capital programme for 2025/26, as at the end of September 2025.

1.2To update Cabinet on the impact upon the approved capital programme for 2025/26 – 2034/35. The current estimate is a decrease in spend in 2025/26 of £1.298M and an increase in spend in 2026/27 £1.773M. The most significant individual changes to the forecast spend in 2025/26 for reprofiling into 2026/27: £0.600M The Museum and Commercial Storage project, £0.346M Resurface Lairage Car Park, £0.300M Charnwood House, £0.235M Parking Charging Payments Management System and £0.201M Home Repair Assistance Grants.

Recommendations

2.1That Cabinet notes the forecast expenditure of £26.416M in 2025/26 on the capital programme, paragraph 8.3 refers.

2.2That Cabinet approves the adjustments to the capital programme for 2026/27, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend by £1.773M.

2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability.

Reasons for recommendations

3.1Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded. 4. ALTERNATIVE OPTIONS CONSIDERED

4.1Options for capital investment are considered as part of the Corporate Business Planning process.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 21st November 2025.

Background

7.1In February 2025, Council approved the Integrated Capital and Treasury Strategy for 2025/26 to 2034/35. The reports for Capital and Treasury have been split for the quarterly monitoring updates.

8. RELEVANT CONSIDERATIONS

8.1The Council has £127.0M of capital assets that it currently owns. The Investment Strategy set out the reasons for owning assets that are not for service delivery, including an assessment of Security, Liquidity, Yield and Fair Value. There have been no significant changes in relation to these since the last quarter. Capital Programme 2025/26 8.2 The full capital programme is detailed in Appendix A and shows the revised costs to date, together with the expected spend from 2025/26 to 2035/36 and the funding source for each capital scheme. 8.3 Capital expenditure for 2025/26 is estimated to be £26.416M. This is a decrease of £1.298M on the forecast in the 1st quarter report (reported to Cabinet on 23rd September 2025). Table 1 below details changes to capital programme.

Table 1- Current Capital Estimates 2025/26 2026/27 2027/28 to £M £M 2035/36 £M Original Estimates approved by 21.063 5.147 18.413 Full Council February 2025 Changes approved by Cabinet in 0.627 3rd Qrt 2024/25 Public Sector Decarbonisation 1.143 project 2025/26 2026/27 2027/28 to £M £M 2035/36 £M Changes approved by Cabinet in 5.203 2024/25 Capital Outturn report Executive Member – Finance and 0.040 I.T. approved additional Expenditure Changes at Q1 -0.452 0.838 0.608 Shared Prosperity Grant Funding 0.090 Changes at Q2 -1.298 1.773 Current Capital Estimates 26.416 7.758 19.021

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Qrt 2 Capital App A 2526RecV4.pdfAppendix 3 pages Download
PDF
SECOND QUARTER CAPITAL BUDGET MONITORING REVIEW 2025/26Report 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. SECOND QUARTER CAPITAL BUDGET MONITORING REVIEW 2025/26This decision
  2. Second quarter treasury management review 2025/26Noted
  3. Second quarter revenue budget monitoring 2025/26Noted
  4. Second quarter treasury management review 2025/26Decided
  5. Second quarter capital monitoring review 2025/26Approved
  6. Second quarter treasury management review 2025/26Decided

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies