SECOND QUARTER REVENUE BUDGET MONITORING 2025/26

Noted Executive 1 paper

AI summaryNorth Hertfordshire Cabinet approved an £846k cut to 2025/26 net spending and noted a £555k rise for 2026/27, including £408k carried forward to specific projects.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarter 2 budget changes agreed
Money£846k cut 2025/26, £555k rise 2026/27Net working budget changes
What happens nextBuilt into 2026/27 draftChanges feed February budget setting
Who it affectsGeneral Fund, all servicesPlus several specific projects

What was decided

Cabinet noted the Quarter 2 revenue budget monitoring report for 2025/26. Report 2.1

Members approved an £846k decrease in the 2025/26 General Fund net working budget. Report 2.2, 8.2

Cabinet noted a £555k increase in the 2026/27 General Fund budget, to be built into the draft. Report 2.3, 8.2

Why

Members can monitor and adjust budgets within the overall framework set by Corporate Business Planning. Report 3.1

Cabinet's terms of reference require quarterly monitoring and in-year adjustments to keep the budget balanced. Report 9.1

Quarterly monitoring acts as a control to reduce the risk of unplanned overspending. Report 11.2

What happens next

The £555k increase will be incorporated into the draft 2026/27 revenue budget for the February budget setting cycle. Report 2.3, 8.2

Officers will carry forward £408k of unspent 2025/26 budget to fund named projects in 2026/27. Report 1.1, 8.2

Council Tax and Business Rates forecasts will be refreshed in January with December data, informing 2026/27 funding. Report 8.10

The money

  • £846k decrease in 2025/26 net expenditure Report 1.1, 2.2, 8.2
  • £555k increase in 2026/27 General Fund net expenditure Report 2.3, 8.2
  • £408k unspent 2025/26 budget requested for carry forward to 2026/27 Report 1.1, 8.2
  • £147k ongoing impact in future years from 2025/26 changes Report 1.1
  • £24.496million current working budget for 2025/26 Report 1.1, 7.1
  • £22.914million original 2025/26 revenue budget approved by Council Report 7.1, P11
  • £1.682million budgets carried forward into 2025/26 from the previous year
  • £526k of the carried forward budget now forecast not to be spent in 2025/26
  • £1.341million efficiencies built into the original 2025/26 budget Report 8.3
  • £200k extra Planning Control application fee income expected from government fee increase Report P16
  • £100k transfer to Planning earmarked reserve from additional fee income Report P16
  • £4.445m expected grant allocation for business rate reliefs in 2025/26 Report 8.13
  • £2.861million planned release from reserve to the General Fund in 2025/26 Report 8.13
  • £1.2million forecast business rates levy liability for 2025/26, funded from reserve Report 8.12
  • £2.9m forecast Council share of Business Rates Collection Fund surplus at year end Report 8.11
  • £250k forecast surplus on the Council Tax Collection Fund at year end Report 8.10
  • £1,365k known financial risks realised by end of Quarter 2 Report 8.15

Options considered

  • Chosen: Approve the budget changes as set out in table 3 and paragraph 8.2. Budget holders consider the variances necessary and appropriate to manage service delivery Report 2.2, 2.3, 4.1
  • Rejected: Manage variances within the existing budget. Budget holders consider the reported variances necessary and cannot be absorbed Report 4.1

Implications

  • Financial: Forecast underspend of £846k against the 2025/26 working budget of £24.496million, partly offset by £408k of carry forward requests. Report 1.1, 8.1, 8.2
  • Financial: Net carried forward General Fund balance at 31 March 2025 is projected to be £846k higher than the working budget assumed. Report P31, P32
  • Legal: Cabinet must keep the budget under review and recommend a balanced budget to Council; the report supports this duty. Report 9.1
  • Equalities: Any new revenue investment proposal of £50k or more, or affecting more than two wards, requires a brief equality analysis. Report 12.2
  • Climate: No known environmental impacts or requirements apply to this report. Report 14.1
  • Staffing: No direct human resource implications, though several variances relate to vacant posts and maternity cover. Report 15.1, P16
  • Risk: Known financial risks realised in Quarter 2 totalled £67k, mainly public inquiry consultant costs and a Careline client loss. Report 8.15, P34, P35, P36, P37

Who and where

  • All council service directorates, whose net budget allocations were re-profiled this quarter Report 7.2, P13
  • Customers and IT service users, with a temporary help desk post proposed to continue Report P16
  • Leisure and Community Wellbeing users, with an apprentice role extension requested Report P16
  • Planning applicants, facing higher statutory fees from 1 April 2025 and changes to pre-application advice charges Report P16
  • Town centre users in the district, as the Town Centres Strategy consultation runs to January 2026 Report P16
  • Car park season ticket holders, following a local employer's decision not to renew Report P16
  • Environmental Health service, with the four-year apprenticeship now starting in 2026/27 Report P16
  • Council Tax and Business Rates payers, through the Collection Fund surplus and levy position Report 8.10, 8.11, 8.12

Timeline

  • February 2025: Council approved the 2025/26 revenue budget of £22.914million Report 7.1, P11
  • March 2025: Cabinet approved £807k of 2025/26 budget changes from the Q3 2024/25 monitoring Report P11
  • June 2025: Cabinet approved £202k of 2025/26 changes from the 2024/25 Outturn report Report P11
  • July 2025: Council approved £120k additional funding for a Churchgate Project Manager Report P11
  • 21st November 2025: Key decision first published in the Forward Plan Report 6.1
  • December 2025: Council approved the latest Medium-Term Financial Strategy 2026-2030 Report 8.11
  • January 2026: Town Centres Strategy public consultation due to finish Report P16
  • January 2026: Next Investment Strategy due to be finalised Report P16
  • 20 January 2026: Cabinet considered and approved the Q2 revenue budget monitoring report
  • February 2026: Council expected to set the 2026/27 revenue budget Report 8.6
  • Spring 2026: Possible adoption of the Town Centres Strategy Report P16
  • Summer 2026: Supplementary Planning Document finalised as a web-based resource Report P16
  • September 2026: Environmental Health Apprentice due to start the dedicated course Report P16

Plain English for the jargon

  • General Fund: The council's main revenue account for day-to-day spending on services
  • Working budget: The current budget for the year after approved in-year changes
  • Carry forward: Unspent budget moved into the next financial year for a specific agreed purpose
  • Earmarked reserve: Money set aside in a reserve for a specific future use
  • Collection Fund: Account where council tax and business rates are held and shared between billing and major precepting authorities
  • EPR: Extended Producer Responsibility funding from central government for packaging recycling costs
  • NHB: New Homes Bonus, a government grant linked to new homes in the district
  • ENIC: Employer National Insurance Contributions grant from central government
  • MTFS: Medium-Term Financial Strategy, the council's multi-year financial plan
  • SPD: Supplementary Planning Document, which provides further detail on policies in the Local Plan
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That Cabinet: (1) Noted this report. (2) Approved the changes to the 2025/26 General Fund budget, as identified in table 3 and paragraph 8.2, an £846k decrease in net expenditure. (3) Noted the changes to the 2026/27 General Fund budget, as identified in table 3 and paragraph 8.2, a total £555k increase in net expenditure. These will be incorporated in the draft revenue budget for 2026/27. REASON FOR DECISIONS: Members are able to monitor, make adjustments within the overall budgetary framework and request appropriate action of Services who do not meet the budget targets set as part of the Corporate Business Planning process. That Cabinet: (1) Noted this report. (2) Approved the changes to the 2025/26 General Fund budget, as identified in table 3 and paragraph 8.2, an £846k decrease in net expenditure. (3) Noted the changes to the 2026/27 General Fund budget, as identified in table 3 and paragraph 8.2, a total £555k increase in net expenditure. These will be incorporated in the draft revenue budget for 2026/27. REASON FOR DECISIONS: Members are able to monitor, make adjustments within the overall budgetary framework and request appropriate action of Services who do not meet the budget targets set as part of the Corporate Business Planning process.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 14 pages

Executive summary

1.1The purpose of this report is to inform Cabinet of the summary position on revenue income and expenditure forecasts for the financial year 2025/26, as at the end of the second quarter. The forecast variance is an £846k decrease in the net working budget of £24.496million, of which £408k is requested to be carried forward to fund specific activities in the next financial year, with an ongoing impact in future years of a £147k increase. Explanations for all the significant variances are provided in table 3.

Recommendations

2.1That Cabinet note this report.

2.2That Cabinet approves the changes to the 2025/26 General Fund budget, as identified in table 3 and paragraph 8.2, an £846k decrease in net expenditure.

2.3That Cabinet notes the changes to the 2026/27 General Fund budget, as identified in table 3 and paragraph 8.2, a total £555k increase in net expenditure. These will be incorporated in the draft revenue budget for 2026/27.

Reasons for recommendations

3.1Members are able to monitor, make adjustments within the overall budgetary framework and request appropriate action of Services who do not meet the budget targets set as part of the Corporate Business Planning process.

Alternative options considered

4.1Budget holders have considered the options to manage within the existing budget but consider the variances reported here necessary and appropriate.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Consultation on the budget monitoring report is not required. Members will be aware that there is wider consultation on budget estimates during the corporate business planning process each year. 6. FORWARD PLAN

6.1The report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 21st November 2025.

Background

7.1Council approved the revenue budget for 2025/26 of £22.914million in February 2025. As at the end of Quarter Two, the working budget has increased to £24.496million. Table 1 below details the approved changes to this budget to get to the current working budget:

Table 1 - Current Working Budget £k Original Revenue Budget for 2025/26 approved by Full Council 22,914 Quarter 3 2024/25 Revenue Budget Monitoring report – 2025/26 807 budget changes approved by Cabinet (March 2025) 2024/25 Revenue Budget Outturn report – 2025/26 budget changes 202 approved by Cabinet (June 2025) Churchgate Viability and Next Steps report – additional funding for a 120 specialist Project Manager approved by Council (July 2025) First Quarter Revenue Budget Monitoring 2025/26 – working budget 453 changes approved by Cabinet (September 2025) Current Working Budget 24,496

7.2The Council is managed under Service Directorates. Table 2 below confirms the current net direct resource allocation of each Service Directorate and how this has changed from the budget allocations published in the Quarter Two revenue monitoring report. The other budget transfers during the quarter primarily relate to the allocation of the Corporate Apprenticeship Scheme and Graduate Trainee scheme resource to the relevant service areas.

Table 2 – Service Directorate Budget Allocations Net Direct Current Net Working Changes Other Direct Budget at approved at Budget Working Quarter One Quarter One Transfers Budget Service Directorate £k £k £k £k Chief Executive 1,125 (369) (434) 322 Customers 3,955 (8) 186 4,133 Enterprise 1,402 (73) 36 1,365 Environment 7,821 892 30 8,743 Governance 2,412 43 81 2,536 Place 1,494 (140) (3) 1,351 Regulatory Services 2,837 (74) 44 2,807 Resources 2,997 182 60 3,239 TOTAL 24,043 453 0 24,496

8. RELEVANT CONSIDERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SECOND QUARTER REVENUE BUDGET MONITORING 2025/26Report 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. SECOND QUARTER REVENUE BUDGET MONITORING 2025/26This decision
  2. Second quarter treasury management review 2025/26Noted
  3. Second quarter capital budget monitoring review 2025/26Noted
  4. Second quarter treasury management review 2025/26Decided
  5. Second quarter capital monitoring review 2025/26Approved
  6. Second quarter treasury management review 2025/26Decided

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies