RECOMMENDED TO CABINET: (1) That the increase in the score for the “Waste – Depot/Transfer Station” sub-risk from an 8 to a 9 be approved; (2) That a new “Waste – Food and Garden Waste” sub-risk, with a score of 5, be approved; (3) That the overall score for the Waste and Street Cleaning Contract renewal” risk remain unchanged at a score of 8; and (4) That the Annual Report on Risk and Opportunities Management 2017/18, as set out at Appendix B to the report, be supported and referred to Council for approval. REASON FOR DECISION: To comply with the Risk and Opportunities Management Strategy, which stipulates that an Annual Risk Management report is taken to Council.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1To provide the Committee with an update on the Corporate risks.
- The Waste sub risk for Depot/ Transfer station has been reviewed and increased from an 8 to a 9 on the Matrix. - A new Waste sub risk for Food and Garden Waste has been introduced with a score of 5 on the Matrix.. - The overall Score for the Waste & Street Cleansing Contract Renewal remains unchanged at 8.
1.2To present the Committee with the Annual Report on Risk & Opportunities Management.
Recommendations
2.1That the Committee notes and refers the changes in the Corporate risks to Cabinet
2.2That the Committee notes and refers the Annual report on Risk & Opportunities Management to Cabinet and then Full Council.
Reasons for recommendations
3.1The responsibility for ensuring the management of the risks is that of Cabinet.
3.2This Committee has responsibility to monitor the effective development and operation of risk management.
Alternative options considered
4.1There are no alternative options that are applicable
FAR COMMITTEE (18.6.18) 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation has been undertaken with SMT and the Risk Management Group (this includes Councillor Cunningham as Risk Management Member ’champion’) and these recommendations were supported. Lead Officers discuss these risks with the relevant Executive Member.
6. FORWARD PLAN
6.1This report does not contain a recommendation on a key decision and has not been referred to in the Forward Plan.
Background
7.1At the March meeting of the Finance, Audit and Risk Committee the following changes to the Corporate risks were approved and referred on to Cabinet. These were subsequently approved by Cabinet.
- Office Accommodation reduction in score to 3 - Waste & Street Cleansing Contract renewal sub risk - Northern Transfer station increase in score to 8 - Waste & Street Cleansing Contract renewal sub risk Commingled Waste score increase in score to 7.
7.2The Committee also noted the information regarding the re-tendering of the Councils Insurance arrangements.
FAR COMMITTEE (18.6.18) 8. RELEVANT CONSIDERATIONS
8.1Corporate Risks
8.1.1 The Corporate Risks summarised in Table 1 have been reviewed and agreed by SMT. Members are able to view the current risk descriptions on Pentana (was Covalent), the Council’s performance and risk management software. The changes to the assessment of the current Corporate risks & opportunities are outlined in sections 8.2 and 8.3. Table 1 shows the last date that the risk was reviewed by the risk owner.
Table 1: Risk and Opportunities Matrix – Proposed Changes
4 7 9 Income Generation Local Plan (13.04.18) (30.04.18)
3 Sustainable Managing the Council’s High Development (2 x Sub Finances (30.04.18) Risks) North Hertfordshire Museum and Hitchin Town Hall Project (08.02.18)
2 5 8 Increased Cyber Risks (19.03.18) Homelessness and Use of Likelihood
B&B (04.04.18) 2 Waste and Street Medium Workforce Planning Cleansing Contract (27.03.18) Renewal (9 x Sub Risks)
1 3 6 Office Accommodation (31.01.18)
1 Low
1 2 3 Low Medium High
Impact
FAR COMMITTEE (18.6.18) 8.2 Waste Sub Risk – Depot/Transfer Station. In February 2018 Officers reviewed the risk and increased the likelihood risk score to “High” (3). This is to reflect the emerging issues relating to the installation of a Fire Suppression System and the Environment Agency permit/licence at the Buntingford Depot. This proposed change will move the Waste sub risk from 8 to 9 on the Matrix. The overall score for the Waste and Street Cleansing Contract renewal remains at 8.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.