That the Capital Programme Outturn 2017/18 report be noted. RECOMMENDED TO CABINET: That, in view of the fact that Capital funds are likely to be depleted within the next few years, it be ensured that regular scrutiny of the Capital Programme is carried out by the Cabinet. REASON FOR DECISION: To provide an opportunity for the Committee to comment as appropriate on the Capital Programme Outturn 2017/18. That the Capital Programme Outturn 2017/18 report be noted. RECOMMENDED TO CABINET: That, in view of the fact that Capital funds are likely to be depleted within the next few years, it be ensured that regular scrutiny of the Capital Programme is carried out by the Cabinet. REASON FOR DECISION: To provide an opportunity for the Committee to comment as appropriate on the Capital Programme Outturn 2017/18.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1As at the end of financial year 2017/18, there is a reduction in spend compared to quarter 3 of £1.495million. The majority of this change is for expenditure that will now be incurred in 2018/19. The forecast increase in spend in future years is £1.506million.
Recommendations
2.1That Cabinet notes expenditure of £9.484million in 2017/18 on the capital programme, paragraph 8.2 refers, and in particular the changes detailed in table 3 which resulted in a net increase on the working estimate of £0.011million.
2.2That Cabinet approves the adjustments to the capital programme for 2018/19 and onwards as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in 2018/19 by £1.506million (re-profiled from 2017/18).
2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability.
2.4That Cabinet approves the application of £1.437million of capital receipts towards the 2017/18 capital programme and the drawdown of £6.390million from set aside receipts, paragraph 8.6 refers.
Reasons for recommendations
3.1Cabinet is required to approve adjustments to the capital programme.
3.2Cabinet is required to ensure that the capital programme is fully funded.
FAR COMMITTEE (18.6.18) 4. ALTERNATIVE OPTIONS CONSIDERED
4.1Options for capital investment are considered as part of the Corporate Business Planning process.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.
6. FORWARD PLAN
6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 16th February 2018.
Background
7.1In February 2017, Council approved the capital programme for 2017/18 to 2020/21. This was subsequently amended by reprogramming from 2016/17 and changes in forecasts at quarter 1, 2 and 3. In February 2018, Council approved the capital programme for 2018/19 to 2021/22.
7.2The Medium Term Financial Strategy for 2018 to 2023 confirmed that the Council will seek opportunities to utilise capital funding (including set aside receipts) for invest to save schemes and proposals that generate higher rates of return than standard treasury investments. This is one way the Council will allocate resources to support organisational transformation that will reduce revenue expenditure.
8. RELEVANT CONSIDERATIONS
Capital Programme 2017/18
8.1Summaries of the capital programme by Council priority and service are shown in appendix A together with the overall funding analysis and projected availability of capital funding balances (set aside and capital receipts). The full programme is detailed in Appendix B and shows the revised costs to date, together with the expected spend from 2018/19 to 2021/22 and the funding source for each capital scheme.
8.2The outturn capital expenditure for 2017/18 is £9.484million. This is a reduction of £1.495million on that reported at the end of the third quarter. The decrease in spend is largely due to re-profiling spend in to future years. Table 1 below details the changes from what was reported at Quarter 3. Table 1- Current Capital Estimates (compared to Quarter 3 forecasts) 2017/18 2018/19 2018/19 to £M £M 2021/22 £M Estimate as at Q3 2017/18 10.978 16.649 4.565 Change from Q3 Estimate -1.494 1.506 0 Outturn 2017/18 9.484 18.155 4.565
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.