CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Hertfordshire District Council
Overview and Scrutiny Committee, Tuesday 18 September 2018 at 7.30pm

1ST QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2018-19

Noted Scrutiny 4 papers

Overview and Scrutiny Committee noted this item on Tuesday 18 September 2018. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

RESOLVED; That the report entitled 1st Quarter Monitoring Report on Key Projects For 2018-19 be noted. REASON FOR DECISION: To enable the Overview and Scrutiny Committee to consider and comment on the 1st Quarter Monitoring Report on Key Projects for 2018-19.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Executive summary

1.1This monitoring report provides a 1st quarter update on the delivery of the key projects for 18/19, first identified to the Committee in March 2018.

Recommendations

2.1That delivery against the key projects for 18/19 be noted and commented on by the Overview & Scrutiny Committee

Reasons for recommendations

3.1To enable achievements against the key projects for 2018/19 to be considered.

Alternative options considered

4.1There are no alternative options as this is a monitoring report.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1No external consultation has been undertaken in the preparation of this report as it is a monitoring report. Members will, however, be aware that a report setting out the key projects was brought to this Committee on 20 March 2018. 6. FORWARD PLAN

6.1This report does not contain a recommendation on a key decision and has not been referred to in the Forward Plan.

Background

7.1This report provides details on the status of the key projects for 18/19. It does not include any projects initiated after the document was agreed and is not a full report on all the projects that the Council is undertaking.

7.2This report summarises the status of each of the key projects. Overall, where the delivery has been solely down to the Council good progress has been made. The following symbols have been used to summarise progress.

Status key Project Halted / funding not available/ Extremely Late Project behind original due date/ unlikely to hit original due date. Project not due for completion in 2018/19 or has not reached due date Project Completed.

8. RELEVANT CONSIDERATIONS

8.1At the Overview & Scrutiny Committee meeting in July 2016, it was agreed that monitoring progress against key projects would take place on a more frequent basis and be reported quarterly.

8.2The 1st Quarter monitoring report against key projects for 2018/19 is included in Appendix A.

8.3Appendix A includes the original milestones for reporting progress which were reported to this Committee in March 2018 and progress made against those actions. In addition, updates may have been provided to Executive Members and where relevant through the Members Information Service. Progress against some, will also have been monitored through the Capital monitoring reports to the Finance Audit and Risk Committee and to Cabinet. 8.4 At the Overview & Scrutiny committee meeting in December 2017 it was agreed that completed projects would be removed from the report, once they had been reported to O&S. In line with this, it is proposed that the Office Accommodation Project, the Community Centre Leases and Working with Health Partners projects are all removed from future monitoring reports.

8.5The Lessons Learned report for the Office Accommodation Project is included in Appendix B. This was signed off on the final Project Board meeting on 11th June 2018.

8.6At the March Meeting, the list of new projects included the Extension to the Royston Leisure Centre, which was subject to a satisfactory business case being produced by Stevenage Leisure Limited. However, the business case from SLL concluded that the project was not currently feasible under the current contract term, as the costs could not be recovered in the remaining term of the contract. In the first quarter capital monitoring report, Cabinet decided to move the capital budget from 2018/19 to 2019/20, Therefore it is proposed that this project be removed from the monitoring reports for 2018/19. Should there be a change in forecast demand the option will be revisited.

8.7A list of questions raised at the June meeting of the Committee is included as Appendix C along with the Officer responses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1ST QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2018-19Report 277 KB DownloadRead as text
PDF
1st Quarter Monitoring against Key Projects for 2018/19Appendix A 347 KB Download
PDF
Lessons Learned: Office Accommodation ProjectAppendix B 115 KB Download
PDF
List of questions raised at June meeting.Appendix C 232 KB Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. 1ST QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2018-19This decision
  2. First quarter revenue budget monitoring 2026/27Noted
  3. First quarter capital budget monitoring review 2026/27Noted
  4. First quarter revenue budget monitoring 2026/27Approved
  5. First quarter capital budget monitoring review 2026/27Approved
  6. Third quarter capital budget monitoring review 2025/26Noted

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies