Planning Control Committee, Thursday 24 July 2025 at 7.00pm

24/02455/FP LAND OPPOSITE WYMONDLEY GRID STATION AND TO THE SOUTH OF SPERBERRY HILL, ST IPPOLYTS, HERTFORDSHIRE

Approved Planning 3 papers

Planning Control Committee approved this item on Thursday 24 July 2025. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

That Application 24/02455/FP be GRANTED planning permission subject to the reasons and conditions set out in the report of the Development and Conservation Manager, with the amendments to Condition 4, Condition 9, Condition 12, Condition 14, Condition 16, Condition 18, Condition 24, Condition 25 and Condition 27, the removal of Condition 10 and 11 and the addition of Condition 29, as follows: ‘Condition 4 No development approved by this planning permission shall take place (including ground works or vegetation clearance) until a construction environmental management plan (CEMP: Biodiversity) has been submitted to and approved in writing by the local planning authority. The CEMP (Biodiversity) should be informed by the 2024 Ecological Assessment and a pre-construction badger survey and include the following. a) Risk assessment of potentially damaging construction activities. b) Identification of "biodiversity protection zones". c) Practical measures to avoid or reduce impacts during construction. d) The location and timing of sensitive works to harm to biodiversity features. e) The times during construction when specialist ecologists need to be present on site to oversee works. f) Responsible persons and lines of communication. g) The role and responsibilities on site of an ecological clerk of works ( ECoW ) or similarly competent person. h) Use of protective fences, exclusion barriers and warning signs. i) The approved CEMP shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details, unless otherwise agreed in writing by the local planning authority. Reason: To minimise the impact of the construction process on the biodiversity and ecology of the site, in line with Policy NE2 and NE4 of the Local Plan. Condition 9 A) No development approved by this permission shall take place/commence until an Archaeological Written Scheme of Investigation has been submitted to and approved by the Local Planning Authority in writing and in accordance with the programme of work as set out in the Archaeological Brief (P01/22/0709/3). The scheme shall include an assessment of archaeological significance and research questions; and: 1. The programme and methodology of site investigation and recording. 2. The programme and methodology of site investigation and recording as required by the evaluation. 3. The programme for post investigation assessment. 4. Provision to be made for analysis of the site investigation and recording. 5. Provision to be made for publication and dissemination of the analysis and records of the site investigation. 6. Provision to be made for archive deposition of the analysis and records of the site investigation. 7. Nomination of a competent person or persons/organisation to undertake the works set out within the Archaeological Written Scheme of Investigation. B) The development shall take place/commence in accordance with the programme of archaeological works set out in the Written Scheme of Investigation approved under condition (A). C) The development shall not be occupied/used until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under condition (A) and the provision made ...
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Planning Control Committee, 40 pages

Location: Land Opposite Wymondley Grid Station And To The South Of Sperberry Hill St Ippolyts Hertfordshire

Applicant: [name removed]: Proposed solar farm measuring 35.5 hectares with associated battery storage and ancillary infrastructure

Ref. No: 24/02455/FP

Officer: Ben Glover

Date of expiry of statutory period: 29/01/2025

Extension of statutory period: 30/07/2025

Reason for Delay:

Discussions and negotiations on various technical aspects, further information received and additional consultation exercises that was undertaken as a result.

Reason for Referral to Committee:

The site area for this application exceeds 0.5ha and therefore under the Council's scheme of delegation, the Council’s Planning Control Committee must determine this application.

Members should be aware that if they are minded to approve the application, the proposal would not need to be referred to the Secretary of State, as the site is not considered to be inappropriate development in the Green Belt and therefore does not meet the requirement to consult the Secretary of State.

1. Relevant History

1.124/01666/SO - Proposed solar farm measuring 35.5 hectares with associated battery storage and ancillary infrastructure – EIA not Required issued on 07/10/2024.

1.222/00709/FP - Proposed solar farm measuring 35.5 hectares with associated battery storage and ancillary infrastructure (as amended by revised and additional information November 2022) – Refused on 22/11/2023 for the following reasons:

1. The application site is located within an area designated as Green Belt, within which there is a presumption against inappropriate development unless very special circumstances can be demonstrated. In the opinion of the Local Planning Authority this planning application proposes inappropriate development in the Green Belt which would harm the Green Belt by reason of inappropriateness and cause harm to the purposes of the Green Belt as defined in paragraph 147 of the National Planning Policy Framework (NPPF). Taken together, the Green Belt and other harms in this case are not considered to be clearly outweighed by the benefits identified. In the circumstances, looking at the application as a whole, very special circumstances are not considered to exist to justify the development in the Green Belt as required by NPPF paragraphs 148 and 151, Wymondley NP Policy GB1 and Local Plan Policy GB5.

2. The proposal would result in unacceptable harm to the character and appearance of the surrounding area in which the site is located. Whilst measures are proposed to mitigate the impact of the proposed development, and the proposal would not be permanent, there would nevertheless be long term harm to rural character and appearance of the area, including the visual amenities of users of the local public footpaths. The proposal would therefore conflict with Local Plan Policies NE2 and NE12 which seek to avoid unacceptable harm to landscape character and appearance.

1.321/02628/SO - Screening Opinion: Proposed 25MW solar farm and 12.5MW battery storage facility – EIA not required issued on 05/11/2021.

1.415/01532/1 - Solar farm of approximately 5 Mega Watts of electricity generating capacity, comprising the installation of solar photovoltaic panels and associated infrastructure, including electrical inverter and transformer buildings, substations, communications and storage buildings, new access, access tracks, fencing and landscaping (as amended by drawing nos. 2218.AP.001.0 Rev I, 003.1 Rev C, 006.3 Rev B, 009.1 Rev A, 010.2 Rev A, G239_1, 2 & 3 received 4/11/15) – Refused on 24/02/2016.

1.514/01576/1SO - Proposed Solar PV development – EIA not required issued on 30/06/2014.

2. Policies

2.1National Planning Policy Framework (2024)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/02455/FP LAND OPPOSITE WYMONDLEY GRID STATION AND TO THE SOUTH OF SPERBERRY HILL, ST IPPOLYTS, HERTFORDSHIREReport 40 pages DownloadRead as text
PDF
PlanReport 4 MB Copy on its way
PDF
Written Update 24 July Planning Committee Meeting Item 6: 24-02455-FPReport 201 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. 24/02455/FP LAND OPPOSITE WYMONDLEY GRID STATION AND TO THE SOUTH OF SPERBERRY HILL, ST IPPOLYTS, HERTFORDSHIREThis decision
  2. 25/01708/op land opposite heath farm, briary lane, royston, hertfordshireRefused
  3. 19/02192/fp land opposite flint house, london road, st ippolyts, hertfordshireApproved
  4. 18/00747/op land opposite heath farm, briary lane, royston, hertfordshireRefused
  5. 17/04239/op - land on the north east side of priors hill, opposite hill farm and north of danefield road, priors hill, pirton, hertfordshireApproved

More from North Hertfordshire Planning Control Committee

All decisions
MeetingDecisionOutcome
1 Oct 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
1 Oct 2026 Minutes - 3 september 2026That the Minutes of the meeting of the Committee held on 3 September 2026 be approved as a true record of the proceed... Approved Open
1 Oct 2026 Notification of other businessThere was no notification of other business. Decided Open
1 Oct 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open
1 Oct 2026 Public participationThe Chair confirmed that the registered speakers were in attendance. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies