CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS - PART 1

Noted Scrutiny 2 papers

AI summaryNorth Hertfordshire's Overview and Scrutiny Committee noted an update on the Churchgate regeneration project and recommended Cabinet ask Full Council to approve additional funds, with details in a separate Part 2 report.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRecommended Cabinet refer to Full Council
MoneyAdditional funds sought, figures in Part 2 report
What happens nextCabinet on 16 June 2026Full Council on 16 July 2026
Who it affectsChurchgate regeneration zoneHitchin town centre area

What was decided

The committee noted the recommendation to Full Council and Cabinet and noted the update and next steps for the Churchgate regeneration project. Report 2.1

The committee recommended to Cabinet that it recommends Council approves the allocation of additional funds, with the detail in a separate Part 2 report. Report 2.2, 10.1

Why

To ensure the committee is content with the decisions being put forward to Cabinet on 16 June 2026 and to Full Council on 16 July 2026. Report 3.1

The report gives members a chance to discuss progress and ask the Executive Member and project team questions in advance of the Cabinet meeting. Report 7.1, 3.1

What happens next

Cabinet is asked to consider the project on 16 June 2026, with Full Council to follow on 16 July 2026. Report 3.1, P2

A Pre Market Engagement exercise closes on 5th June 2026, with a verbal update given at the meeting on 9th June. Report P22

If approved, procurement will begin to appoint a partner to advise on disposal and development of the site. Report P2, P18

The money

  • Additional funds (figure in Part 2 report) Further budget required for the next stage of the project Report 10.1, 2.2

Options considered

  • Rejected: No alternative options considered. The report states none were considered Report 4.1

Implications

  • Financial: Officers recognise additional budget is needed; the figures are set out in a separate Part 2 report. Report 10.1
  • Risk: The project is monitored under the Council's Pentana system, with the team meeting the Risk Officer every two months. Report 11.1, 11.2
  • Risk: The Pre Market Engagement exercise is intended to de-risk the project and provide a robust evidence base for the next stage. Report 11.3
  • Legal: The committee is not a decision-making body; its role is to note the decision being taken to Cabinet and Full Council. Report 9.1
  • Equalities: Decision-making must have due regard to the Public Sector Equality Duty. Report 12.1
  • Other: Social Value will be considered and incorporated in any procurement, depending on its value and scope. Report 13.1
  • Climate: The report identifies no known environmental impacts or requirements. Report 14.1
  • Staffing: The report identifies no human resource impact. Report 15.1

Who and where

  • Churchgate regeneration zone in Hitchin Report P2, 7.1
  • Developers and partner organisations (12 met during Soft Market Testing) Report P15
  • North Hertfordshire councillors (43 attended three All Member Briefings) Report P16
  • Executive Member and Shadow Executive Members briefed through the Project Board Report 5.1
  • Neighbouring councils, via joint attendance at the UK Real Estates and Investment Forum with Invest Hertfordshire Report P17

Timeline

  • March 2026: Soft Market Testing exercise launched with Project Board approval Report P15
  • April and May 2026: Three All Member Briefings held, attended by 43 members Report P16
  • May 2026: Pre Market Engagement exercise launched with Procurement colleagues Report P18
  • 15 May 2026: Decision notified to the public in the Forward Plan Report 6.1
  • 5th June 2026: Pre Market Engagement exercise due to close Report P22
  • 9th June 2026: Overview and Scrutiny Committee meeting held Report P22
  • Mid 2026 to Late 2026: Partner Procurement phase Report P18, P20
  • Late 2026 to Early 2027: Feasibility and Shaping phase Report P20
  • 2027 to 2028: Pre Development, Planning and Delivery phase Report P20
  • 16 June 2026: Cabinet meeting to consider the project Report 3.1
  • 16 July 2026: Full Council meeting to consider the project Report 3.1

Plain English for the jargon

  • UKREiiF: UK Real Estates and Investment Forum, held in Leeds, where the team promoted the project
  • Soft Market Testing: Meetings with interested developers to gauge market interest and gather feedback before formal procurement
  • Pre Market Engagement: A procurement exercise to appoint a partner to advise on disposal and development strategy
  • Pentana: The Council's risk management system used to monitor the project
  • Lambert Smith Hampton: Property consultancy working with the project team at the UKREiiF event
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the recommendation to Full Council and Cabinet was noted, and that the Overview & Scrutiny Committee also noted the provided update/next steps of the project. RECOMMENDED TO CABINET: That Cabinet recommends that Council approves the allocation of additional funds, referencing the Part 2 report. REASON FOR RECOMMENDATION: To ensure that the Overview & Scrutiny Committee are content with the decisions being put forward to Cabinet on 16 June 2026 and to Full Council on 16 July 2026. This report provides an overview of the recent work completed and details how the project team and Project Board propose to move forward – providing the Committee with an opportunity to ask any further details.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 5 pages

Executive summary

To provide an update on the project progress so far, and report on suggested next steps and milestones in preparation for the Cabinet decision in June and Full Council decision in July.

The proposed Cabinet decision is as follows: Approval to commence the next steps as set out in the report, subject to Full Council approval, which will enable the Council to commence procurement in order to select a supplier to evaluate the viability, feasibility, and deliverability of the Churchgate Regeneration Zone.

Recommendations

2.1That the recommendation to Full Council and to Cabinet decision is noted, and that the Overview & Scrutiny Committee also note the provided update/next steps of the project.

2.2That Cabinet recommends that Council approves the allocation of additional funds referencing the Part 2 report.

Reasons for recommendations

3.1The recommendation is to ensure that the Overview & Scrutiny Committee are content with the decisions being put forward to Cabinet on 16 June 2026 and to Full Council on 16 July 2026. This report provides an overview of the recent work completed and details how the project team and Project Board propose to move forward – providing the Committee with an opportunity to ask any further details.

Alternative options considered

4.1None.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1The Executive Member and Shadow Executive Member/s have been kept up to date on this decision via either/or Project Board attendance or scheduled Executive Member Briefings.

5.2The team hosted three All Member Briefings throughout April and May 2026.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 15 May 2026.

Background

7.1This report has been written to provide the Overview & Scrutiny Committee with an update on the Churchgate Regeneration Zone project, in line with the pending Cabinet decision. This is an opportunity for Members to discuss the progress of the project and ask the Executive Member and Project Team any relevant questions in preparation for the Cabinet meeting.

8. RELEVANT CONSIDERATIONS

8.1Since the last update provided to Overview & Scrutiny Committee in February 2026, the project team have made significant progress and remain on track against the project timeline. Please see below for a breakdown of the progress to date:

Mid 2026 – Governance and Direction: In March 2026 the team (with Project Board approval) launched a Soft Market Testing exercise to find out what the level of interest is from the developer/partner market. This consisted of a series of meetings with registered interested parties and included an overview of the Councils position (due diligence carried out so far, consultation, direction of travel, Local Government Reorganisation etc). This step was valuable and allowed the project team to determine the level of interest and gain detailed feedback on what the developer industry would like to see in the projects next steps. The team reported that whilst the developers continue to work in a volatile market, the level of interest in Churchgate is high but requires more viability, de-risking and further due diligence before stepping into the delivery Procurement phase. The team met with 12 organisations (of different types), and gaged different levels of interest – with most reporting a strong market interest and viewed the project as a high-quality, investable opportunity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS: PART 1Report 5 pages DownloadRead as text
PDF
Churchgate Regeneration Project & Next Steps Part 1: UpdatedReport 5 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS - PART 1This decision
  2. Churchgate regeneration project update & next steps - part 1Approved
  3. Churchgate regeneration project update & next steps - part 1Approved
  4. 7b - ITEM REFERRED FROM CABINET: 20 NOVEMBER 2018 - REGENERATION OF CHURCHGATE SHOPPING CENTREDecided
  5. Regeneration of churchgate shopping centreAgreed
  6. 5a - item referred from hitchin committee: 13 november 2018 - regeneration of churchgate shopping centreDecided

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies