CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS - PART 1

Approved Executive 6 papers

AI summaryCabinet recommends Council approve further Churchgate regeneration funding and orders a review of council communications transparency, ahead of appointing specialist development expertise.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMore funding plus a communications review
MoneyNot stated
What happens nextFull Council decisionOn the additional funding request
Who it affectsHitchin town centre5.6 acre Churchgate Regeneration Zone

What was decided

Cabinet recommends Council approves additional capital or revenue funding for the next phase of the Churchgate Regeneration Project, with the figures set out in a separate Part 2 report. Report P3

Cabinet instructs officers to undertake a review of the Council's external communications approach, focused on transparency, accessibility and the visibility of key decision-making information.

Why

The project has progressed significantly since the last Full Council update in July 2025 and Overview and Scrutiny discussions in February 2026, moving into a more mature, evidence-led phase. Report P3, P269

Baseline reviews, market testing, an Investment Prospectus and a public consultation gathering 1,505 survey responses and over 1,000 visitors to the Consultation Hub have been completed. Report P12, P112, P113, P118

Market engagement has shown strong investor and developer interest in Hitchin and confidence in the credibility of the opportunity and the Council's commitment to delivery.

What happens next

If Council approves, the Council will appoint specialist regeneration and development expertise to refine a deliverable scheme, test assumptions and move into delivery planning. Report P271

High level viability assessment of development options is already underway, building on the themes set out in the Development Principles report. Report P269

A communications review will be carried out, with future regeneration decisions intended to be informed, evidence-led and commercially robust.

Options considered

  • Chosen: Approve additional funding and appoint specialist development expertise. Next logical step from the evidence-led phase, reflecting consistent market and specialist advice Report P269, P271

Implications

  • Financial: Additional capital or revenue funding is sought, but the specific figures sit in a Part 2 report that has not been supplied here.
  • Legal: Cabinet's role is to recommend to Council, so the final funding decision rests with Full Council.
  • Risk: The Council intends to keep control of the project as it develops, with investment and risk kept proportionate to the level of certainty at each stage.
  • Equalities: Public consultation included workshops with community groups, schools and engagement with hard to reach and young residents, with feedback informing the principles. Report P112, P246
  • Climate: Public consultation asked residents to rate sustainable and environmentally friendly aspects; the emerging principles include green infrastructure, low carbon and smart mobility. Report P238, P265

Who and where

  • Residents and visitors of Hitchin town centre Report P3, P112
  • Current tenants of Churchgate Centre Report P9, P112
  • Hitchin Market traders and the Market Board Report P5, P99, P238
  • Local school children and young residents Report P112, P246
  • Households across the wider North Hertfordshire district (leaflet drop) Report P112

Timeline

  • August 2022: Council acquired the long leasehold of Churchgate Centre and merged it with its freehold Report P3
  • Q3 2023: Lambert Smith Hampton commissioned via the Crown Commercial Service framework Report P4, P10
  • Q1 2024: Multi-disciplinary team of Leonard Design Architects and KMC Transport Planning appointed Report P7, P11
  • May 2024: Investment Prospectus presented at UKREiiF in Leeds Report P12
  • September 2024: Leaflet drop to households across the whole District Report P112
  • 16th September to 3rd November 2024: Public consultation ran, with over 1,000 visitors to the Hub and 1,505 survey responses Report P112, P113, P118
  • December 2024 onwards: Development viability appraisals began Report P12
  • Q4 2024: Hitchin retail vacancy rate reported at 8.1 percent against a national average of 19.1 percent Report P107
  • July 2025: Last Full Council update on the project
  • February 2026: Overview and Scrutiny Committee discussions on the project
  • Second half of 2025 (envisaged): Procurement process to commence, subject to viability and preferred roadmap to delivery Report P12

Plain English for the jargon

  • CRZ: Churchgate Regeneration Zone, the 5.6 acre site including the Churchgate Centre, Hitchin Market and four car parks
  • LSH: Lambert Smith Hampton, the council's commissioned property adviser
  • RIF: Regeneration and Investment Framework, the evidence-based spatial and development strategy being prepared
  • UKREiiF: UK Real Estate Investment and Infrastructure Forum annual conference
  • SuDS: Sustainable Drainage Systems, green infrastructure to manage rainwater
  • CCS: Crown Commercial Service framework used to commission LSH
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24

Resolved

That Cabinet: RECOMMEND TO COUNCIL: That it: (1) Approves the additional capital / revenue funding set out in the Part 2 report to support the next phase of the Churchgate Regeneration Project. (2) Instructs officers to undertake a review of the Council’s external communications approach, with a specific focus on improving transparency, accessibility, and the visibility of key decision?making information. REASONS FOR RECOMMENDATION: (1) Since the last Full Council update in July 2025, and subsequent Overview & Scrutiny Committee discussions in February 2026, the Churchgate Regeneration Project has progressed significantly and moved into a substantially more mature and evidence-led phase. (2) Over the past year, the Council has undertaken an extensive programme of work to respond directly to key matters raised by Members and stakeholders, including viability, parking, public realm, market provision, delivery options, governance and long-term town centre sustainability. This has included financial analysis, specialist technical work, Project Board workshops and Member briefings. (3) This work has enabled the Council to move from high-level vision setting into a more informed, evidence-led and delivery-focused phase. (4) Alongside this, the Council has also undertaken early engagement with the development and investment sector to inform future procurement, delivery and partnership decisions. Feedback from this work has demonstrated strong market interest in Hitchin and increased confidence in both the credibility of the opportunity and the Council’s commitment to delivering a high-quality regeneration programme for the town centre. (5) The recommendations within this report therefore represent a logical progression from the work completed to date and are intended to ensure that future decisions regarding the regeneration of the site are informed, evidence-led and commercially robust. (6) The proposed next stage of work is materially different from earlier strategic and visioning exercises. The Council is now seeking to appoint specialist regeneration and development expertise to work alongside the project team in refining a deliverable scheme, testing assumptions in greater detail, reducing uncertainty and supporting the transition from strategic visioning into delivery planning and implementation. (7) This phased approach enables the Council to retain control of the project as it develops, whilst ensuring that investment and risk remain proportionate to the level of certainty and information available at each stage. (8) The proposed next phase reflects the consistent feedback received through market engagement and specialist advice: that the appropriate next step is a structured feasibility and delivery-planning phase focused on shaping a viable, deliverable and investment [1] ready regeneration scheme for Hitchin town centre.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 24 pages

Summary

05 Next Steps

03 Churchgate Regeneration Zone, Hitchin Town Centre 00 Introduction

Introduction Churchgate Regeneration Zone North Herts Council (NHC) acquired the long leasehold interest of the Churchgate Centre in August 2022, and effectively merged the leasehold interest with the freehold interest already in the Council’s ownership. Their outright ownership of the centre and adjacent land provides the opportunity, for the first time, for the potential comprehensive redevelopment of the 5.6 acre site. The wider opportunity site is referred to as the ‘Churchgate Regeneration Zone’ (CRZ).

Lambert Smith Hampton (LSH) was initially commissioned by North Herts Council (NHC) in 2023 via 5 the Crown Commercial Service (CCS) framework to review and advise on the market potential for the regeneration of the Churchgate Centre and adjacent (surface car park) sites under its ownership.

The Churchgate Regeneration Zone (CRZ) comprises the Churchgate Centre, Hitchin Market and the 4 Portmill Lane, Biggin Lane and St Mary’s Square Car Parks (see plan).

The first phase of work comprised: • A review of ownerships and identification of any potential issues that might impact on future 7 development (e.g. restrictive covenants, rights of way, long leases, further land assembly, etc).

• A planning policy overview and assessment of any factors/considerations that might impact 3 (positively and negatively) on the development (e.g. conservation area, proximity of listed buildings, sight lines to St Mary’s Church etc). 9 • A market overview of different uses (retail, leisure, employment, civic, community, market, residential types, etc.) and broad ‘value parameters’ to help understand the most viable and optimum mix of 2 uses; as well as an early understanding of any potential barriers to development and delivery, and 1 what mitigation steps may be needed to reduce risks. 8 These inter-related work streams were set out in LSH’s ‘Market Assessment & Planning Overview’ report, including recommendations on next steps. This report was prepared for the Council in September 2023, and the key findings were summarised and presented to the client team and to: • Churchgate Project Board - 17 October 2023; and • All Council Members - 9 November 2023. 6 At these meetings it was formally agreed a ‘Regeneration & Investment Framework’ (RIF) be prepared to provide the robust evidence-based spatial strategy, and planning / design / development framework Key needed to help inform the Council’s planning of, and decision-making on the potential redevelopment of Site Boundary the CRZ. The RIF is being prepared in accordance with key Policy SP9 (on Design and Sustainability), to 1 Churchgate Shopping Centre 2 The Market address the requirements of Policies HT11 (on Town centre uses and site-specific allocation criteria) of 3 St Mary’s Car Park the adopted Local Plan (November 2022). 4 Portmill East Car Park 5 Portmill West Car Park Working in collaboration with the Council’s Churchgate Project Board team (comprising Councillors, 6 Biggin Lane Car Park the Managing Director (MD), Finance Director (FD) and Key Council Officers) a multi-disciplinary 7 St Mary’s Church & Churchyard consultancy team was assembled in early 2024 comprising masterplanners / urban designers (Leonard 8 The Biggin Design Architects) and transport planners (KMC Transport Planning) via a competitive process. 9 Market Place Image Caption

04 05 Churchgate Regeneration Zone, Hitchin Town Centre 00 Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1. Development Principles May 2025Report 24 pages DownloadRead as text
PDF
2. Churchgate Car Parking Assessment Markides November 2025Report 14 pages Download
PDF
3. Community Provision Study Leonard Design November 2025Report 42 pages Download
PDF
4. Public Realm Assessment Leonard Design November 2025Report 54 pages Download
PDF
5. Churchgate Regeneration Zone Massing DiagramsReport 1 pages Download
PDF
CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS: PART 1Report 10 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS - PART 1This decision
  2. Churchgate regeneration project update & next steps - part 1Approved
  3. Churchgate regeneration project update & next steps - part 1Noted
  4. 7b - ITEM REFERRED FROM CABINET: 20 NOVEMBER 2018 - REGENERATION OF CHURCHGATE SHOPPING CENTREDecided
  5. Regeneration of churchgate shopping centreAgreed
  6. 5a - item referred from hitchin committee: 13 november 2018 - regeneration of churchgate shopping centreDecided

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open